🧱 CFC 224Tinsmithing: shaping, junctions and thermal expansionChapter 8 of 10 in the section

Parapet coping: inward slope, fixing and joints

This chapter details the execution rules for a sheet-metal parapet coping. You will be able to correct the slope of the wall top towards the inside of the roof, size the projection of the drip edges to protect the façade renders, fit concealed fixing cleats and size the expansion cover strips to absorb thermal movement without water ingress.

Key takeaways

  • Always direct the coping slope inwards to prevent staining of the façade.
  • Form a projecting drip edge on each side to break the return of water by capillary action.
  • Avoid through-fixing screws in favour of continuous clips or sliding non-penetrating cleats.
  • Fit watertight cover strips at the joints to absorb the thermal expansion of the sheets.

Direction of slope and drip edge clearance to protect the façade

A badly inclined coping turns every rainy spell into aesthetic and structural damage. When water stagnates on the metal top or runs towards the outer face, atmospheric dust accumulates along the band and then streaks down the mineral render. These blackish runs quickly damage the masonry and cause the premature detachment of the render through repeated freeze-thaw cycles. The primary role of the parapet coping is to discharge rainwater exclusively towards the gutter or the inner slope of the pitched roof.

To guarantee this directed drainage, the upper face must have a continuous minimum slope of 2 to 3% towards the roof. As the raw masonry of the wall top is frequently delivered flat or out of plumb towards the outside, the metal roofer must never lay the metal directly on this non-compliant concrete. Under art. 365 CO, if the material supplied by the client or the ground designated by the client is found to be defective, or if any other circumstance jeopardises the proper or timely execution of the work, the contractor must inform the client immediately. The correction is made by interposing a wedged board sheathing or a treated tilting fillet, cut with a circular saw to the required angle.

Recommended geometric parameters for forming copings
Profile elementMinimum dimensionFunctional role on the structure
Transverse slope2% (inwards)Drains dirty water towards the roof slope without retention
Drip (projection)20 mm from the finished facePrevents water from running down the render or concrete
Return fold (drip edge)Angle closed to 45°Breaks the water meniscus and eliminates capillary action
Outer drop height50 mm below the drip edgeProtects the wall top against driving rain

Breaking capillary action requires a projecting drip edge on each face of the parapet, both on the façade side and on the inner side. On the outer edge, the return fold must stand at least 20 mm clear of the finished face of the façade to form an effective drip that breaks the surface tension of the liquid. On the inner side, the drip edge overhangs the upstand of the roof slope connection without crushing it, thus preventing water from being drawn back under the coping during windy spells.

Indirect mechanical fixing and management of thermal movement by cover strips

The fundamental rule in parapet metalwork prohibits any mechanical penetration of the flat upper face of the coping. Piercing the metal at the top of the piece with screws fitted with sealing washers creates unavoidable points of water ingress: under the combined action of ultraviolet radiation, cold and the expansion movements of zinc or aluminium, the elastomer washers harden, crack and lose their grip within a few seasons. Water then penetrates directly into the timber or concrete substrate below.

Mechanical retention is achieved by indirect clipping onto continuous fixing battens or anchor cleats previously plugged into the wall top. These galvanised sheet or stainless steel fixing profiles have a rigid fold at the bottom onto which the hem fold of the coping snaps. This system allows the work to resist the suction forces caused by wind at the roof edge in accordance with the SIA 118 standard and the rules of the trade, while allowing the material to slide freely lengthwise.

  1. Fitting the tilting fillet and underlayFix the timber support wedged to the required slope, then roll out a breathable separating membrane to prevent any corrosion of the underside.
  2. Plugging the fixing cleatsAnchor the clipping strips or continuous cleats on either side of the wall top with fixings suited to the substrate, without piercing the drip zone.
  3. Installing the connecting under-stripsAt each joint, place a preformed under-strip of identical profile, fitted with a central rib or an inward return.
  4. Snapping on the coping profilesFit the coping lengths onto the clipping cleats, leaving the calculated thermal expansion gap at the joint.

The connection between two lengths of sheet must never be rigidly soldered over long runs, otherwise buckling and tearing will result under thermal stresses. The watertightness of the joints relies on the fitting of expansion cover strips or under-strips. These metal pieces, approximately 150 to 200 mm wide and formed to the inner dimensions of the coping, collect the drops entering through the joint and discharge them towards the inside of the roof.

Fold design, drip edge clearance and concealed anchoring

On gable or party-wall parapets bordering a pitched roof, the formed sheet coping performs a fundamental function: protecting the wall top against water ingress and keeping run-off water durably away from the façades. A coping whose seating is horizontal or sloping outwards is a systematic defect that fouls the masonry and saturates the external renders. To guarantee damage-free drainage, the table of the profile must have a slope oriented unequivocally towards the gutter, the roof slope or the internal outlet. The inclination must compensate for the irregularities of the raw structure and prevent any formation of standing puddles that would promote premature oxidation or the deposit of abrasive sediments.

Crossing the wall heads also requires careful treatment of the overhanging edges. To break the surface tension of the water and prevent the liquid from rising by capillary action under the metal or licking the render, each edge of the coping ends in a drip edge folded outwards. This drip, folded at an angle of 30° to 45°, must leave a clearance of at least 20 millimetres from the finished face of the building. On the external façade as well as on the inner face turned towards the roof, the lower edge must not come into direct contact with the render or the external insulation. This free distance ensures ventilation under the sheet and eliminates any risk of blackish streaks caused by concentrated run-off during heavy rain at the top of the wall.

Expansion joints, draining cover strips and installation method

Metal profiles undergo considerable linear expansion between winter frosts and summer heat. A coping in a single piece or soldered from end to end over a length exceeding six metres would quickly deform with pronounced buckling, eventually tearing out its anchor points. The metal roofer therefore divides the work into standard sections of two to three metres, connected by a system of expansion cover strips. These connecting pieces allow adjacent elements to slide freely along the longitudinal axis without losing their geometric alignment or compromising resistance to driving rain.

Thermal behaviour and cover strip tolerances for metals commonly used in sheet-metal work
Formed metalUsual thicknessThermal gap for 3 mRecommended method of assembly
Rolled titanium-zinc0.70 to 0.80 mm5 to 6 mmUnder-strip with central rib and end clipping
Quarter-hard copper0.60 to 0.70 mm4 to 5 mmFlat slider with undercut and retaining clips
Powder-coated aluminium1.00 to 1.50 mm7 to 9 mmCentral cover strip dry-fitted with spring brackets
Tinned stainless steel0.50 to 0.60 mm3 to 4 mmDraining under-strip soldered on one side and free on the other

The draining cover strip is the ideal solution for closing the joint without binding the material. Placed under the line where the two copings meet, this intermediate sheet follows the inner profile exactly and has a central fold or embossings that break capillary rise. Water that crosses the gap left between the two profiles runs down this under-strip, which systematically discharges it on the inner side towards the roof thanks to the transverse slope of the substrate. No bead of elastomer sealant must be injected on the surface to close this gap: the jointing mass would eventually come away under the effect of continuous thermal friction, retaining moisture instead of expelling it.

  1. Preparing the slope formationCheck the masonry wall top and fit a chamfered board or calibrated trapezoidal wedges to obtain a continuous gradient of at least 2% towards the inner slope.
  2. Fitting the clipping strips and under-stripsPlug the continuous edge cleats onto both vertical faces of the parapet, then mechanically fix the draining under-strips at each element joint.
  3. Engaging the outer foldPresent the coping section by first engaging the outer drip edge clip on the continuous cleat to lock the hold against façade wind.
  4. Inner clipping and setting the gapFold the table inwards, clip the lower clip on the roof side and check the specified expansion gap with a rule before engaging the next section.

Recording defects, technical remedial work and handling of faulty workmanship

A parapet coping laid with a reverse slope or restrained by through-fixings inevitably leads to damage. Concentrated staining and blackish runs appear on the façade render with every driving rain, while water that has seeped under the sheet wets the insulation, rots the timber supports and damages the masonry. As soon as the defect is noted during the execution check, the metal roofer must refuse any surface patch-up and immediately undertake a complete rework in accordance with the technical rules of the trade.

  1. Diagnosis and methodical removalLocate precisely the drainage defect, the lack of drip edge projection or the mechanical restraint. Unclip the profiled elements without twisting the zinc or aluminium strips, dismantling first the cover strips and the corner pieces formed in the workshop.
  2. Correcting the seating and realigningAdd bevelled battens or stable wedging to restore a clear gradient towards the inner slope. Reposition the outer edge to leave a clear gap between the drip of the drip edge and the façade render.
  3. Fitting concealed fixings and cover stripsSystematically replace any sheet pierced by a through-fixing. Refit the whole assembly on fixing cleats clipped on the underside, then fit draining expansion cover strips complete with their sealing strip without blocking thermal sliding.

As regards the contractor's liability, quality requirements remain strict. Under art. 368 CO, the client may demand the rectification of the defective metalwork. Bringing it into compliance requires permanently eliminating reverse slopes and upper perforations, so that water runs exclusively towards the internal outlets of the pitched roof without risk of soiling the façade or rotting the supporting boards.

Frequently asked questions

Why is it strictly forbidden to screw a coping from above?

Drilling directly through the upper face creates an immediate water path. Under daily and seasonal temperature variations, the metal sheet continually expands and contracts. This axial movement shears the neoprene sealing washer, makes the drill hole oval and loosens the screw. Run-off water then seeps directly under the coping, soaking the board sheathing and the parapet with no possibility of spontaneous drying.

What minimum slope should be given to the coping towards the inside of the roof?

A minimum slope directed towards the inner roof is essential to prevent water from stagnating and tipping towards the external façade. On the construction site, this gradient is achieved by means of bevel-cut board sheathing or trapezoidal wedges firmly fixed to the wall top. This inclination ensures that all dust and rainwater is conveyed towards the gutter or the ventilated eaves without ever soiling the external render.

Why must the coping be fitted with a drip edge on both faces?

The outer drip edge prevents rainwater from returning to lick the façade through surface tension, which avoids dirty streaks and render detachment. On the inner side, the drip edge provides the same capillary break above the waterproofing or underlay connection. Without this double drip fold set sufficiently clear of the face of the wall, capillary rise and residual moisture end up bypassing the sheet and wetting the head of the wall.

How does the expansion cover strip work between two lengths of sheet?

The cover strip is a preformed underlying sheet, placed astride beneath the joint of two copings. It ensures continuity of the support and collects any water ingress to discharge it towards the front. The two coping elements are laid with a gap of a few millimetres, without being soldered or riveted together. This arrangement allows the metal to slide freely with temperature variations without distorting the line of the parapet.

Texts and standards cited

  • CO art. 368client's rights in the event of defects in the work