Key takeaways
- A continuous minimum slope of five millimetres per metre ensures rapid drainage of water without residual deposits.
- Hook spacing must not exceed fifty centimetres, in order to rule out any sagging under snow load.
- Deflection between supports holds a layer of standing water which bursts the joints during freezing.
- Systematic water testing validates the actual slope and the complete absence of reverse slope before acceptance.
Determine the hook spacing and set the minimum drainage slope
On a pitched roof, a suspended or half-round gutter is subjected to severe mechanical stresses: the dead weight of the metal, the volume of water during intense stormy downpours, and the surcharge of compacted snow or ice sliding down from the roof slope. When the supports are too widely spaced or poorly aligned, the metal profile deflects under the load. This localised sagging creates troughs where residual water inevitably accumulates. In winter, these layers of standing water turn into blocks of ice that obstruct the line of flow, deform the bottom of the gutter and cause soldered seams or expansion joints to burst.
| Geographical zone / Load | Profile girth | Maximum permitted spacing | Consequence of undersizing |
|---|---|---|---|
| Lowland (below 600 m) | 250 mm to 330 mm | 500 mm | Visible deflection at mid-span under heavy rain |
| Pre-Alps and Jura (600 to 1000 m) | 330 mm to 400 mm | 450 mm | Sagging of the front bead under the weight of the ice plug |
| High altitude (above 1000 m) | All girths | 400 mm | Pull-out of the fixing screws or twisting of the hook straps |
Marking out is carried out by calculating the overall drop between the high point and the start of the downpipe. On a roof slope ten metres long, a slope of 5 mm per metre requires a total fall of 50 mm. The sheet-metal worker fixes the first hook at the upper level, allowing for the clearance under the drip edge, then positions the low hook at the eaves outlet. The guide line is marked with a stretched chalk line or a nylon line under high tension, supplemented by a water level or a laser level to eliminate any visual error caused by possible deformations of the roof structure.
Eliminate deflection between supports and carry out the water-flow check
The deflection between two successive hooks must under no circumstances exceed two millimetres when empty, and must remain negligible under the nominal water load. Excessive spacing produces a "belly" in the gutter, an area where suspended solids (leaves, moss, tile grit) settle by sedimentation. This acidic sludge accelerates pitting corrosion of zinc or copper. In winter, the transformation of this wet deposit into ice causes a lateral thrust that spreads the outer bead and damages the overall alignment of the eaves line.
- Precise bending of the hook strapsUse a graduated hook-bending tool, applying a constant progression of angle and length, to respect the flow line set out with the chalk line.
- Recessing and screwing onto rafter or eaves boardNotch the roof timber to the thickness of the hook strap to ensure a flush surface, then fix each piece with at least two suitable stainless-steel wood screws.
- Seating and fixing of the metal profilePlace the gutter sections in the hooks, clip the outer bead onto the hook noses and fold down the rear tabs without restricting thermal expansion movements.
- Drainage test with running waterPour a continuous volume of at least ten litres of clean water at the highest point of the drainage line to observe the dynamic behaviour of the water as far as the outlet stub.
The water test record is the guarantee of compliant execution. In accordance with art. 364 CO, the contractor is liable for the proper and faithful execution of the work according to the recognised rules of the trade. The flow test immediately reveals false levels that cannot be detected by eye, particularly at soldered joints where an excess thickness of filler metal can form an artificial dam. Upon delivery of the gutter, art. 367 CO provides that the client checks the condition of the work; the water test carried out jointly on the construction site prevents any later dispute relating to water retention or eaves overflow.
Behaviour under load and limiting deflection between supports
Under the action of the dead weight of the metal, the peak storm flow and above all the surcharges of accumulated snow or ice, the suspended gutter works in bending between its supports. If the hook spacing is too large or the cross-section of the flat iron is insufficient, the sheet sags beyond its elastic limit. This permanent deflection between two supports, called a "belly", breaks the continuity of the profile. The gutter ceases to ensure continuous flow and breaks up into a series of retention troughs.
Hook spacing remains the direct lever for keeping the deflection below this critical threshold. On the Swiss Plateau, below 600 m altitude, the centre-to-centre spacing must not exceed 450 to 500 mm for sheet profiles of 0.60 to 0.70 mm (copper, zinc-titanium). In pre-Alpine or Jura regions subject to increased snow loads according to standard SIA 261, the spacing is reduced to between 350 and 400 mm, with reinforced hooks of 30 x 5 mm. Any profile that bellies retains atmospheric sediment and leaves, creating local acidification conducive to pitting corrosion. In winter, the volume of residual water freezes, exerts tension on the clips and breaks up the assembly soldering.
| Material and girth | Altitude < 600 m | Altitude ≥ 600 m | Minimum hook section |
|---|---|---|---|
| Copper 0.60 mm (girth ≤ 333 mm) | 500 mm | 400 mm | 25 x 4 mm |
| Zinc-titanium 0.70 mm (girth ≤ 333 mm) | 450 mm | 350 mm | 30 x 4 mm |
| Stainless steel 0.50 mm (girth ≤ 333 mm) | 500 mm | 400 mm | 25 x 5 mm |
| Box gutter, sheet 0.80 mm | 400 mm | 300 mm | 30 x 5 mm |
Minimum drainage slope and water-testing protocol
To ensure self-draining rainwater discharge and avoid muddy deposits, the gutter must imperatively maintain a continuous minimum slope of 5 mm per metre, i.e. 0.5 %. For box gutters receiving large catchment areas, a slope increased to 10 mm per metre (1.0 %) is an essential safeguard against blockage. This geometry depends on marking out with the chalk line and on the regularity of the hook bending when setting the slope. Any carelessness in alignment creates intermediate low points where residual water stands instead of flowing towards the outlet sump or the stub.
- Complete cleaning of the gutter bedSweep the bottom of the channel thoroughly to remove cutting filings, residues of soldering flux and site dust, which block the flow or initiate pitting corrosion.
- Alignment check with a chalk lineStretch a line along the outer bead to detect any vertical misalignment or deflection between two consecutive hooks before introducing water.
- Dynamic flow testAt the upper end of the line, pour a calibrated volume of at least 20 litres of clean water with a watering can, at a constant flow rate, in order to observe the speed of the water stream towards the outlet.
- Recording of standing-water zonesWait ten minutes after gravity drainage, then use a metal rule to measure the depth and extent of any persistent puddles in the profile.
Systematic performance of this dry-run test validates the installation before the eaves strips are fitted and the first courses of tiles or slates are closed in. For this operation carried out at the edge of the roof slope, OTConst provides for appropriate measures to prevent falls from a fall height of more than 2 m. Entering the results of the water test in the site diary certifies the conformity of the work with regard to the risks of frost and standing water.
Handling non-conformities: reverse slope, standing water and rework on the construction site
When a water test reveals water retention or a reverse slope, the sheet-metal worker must immediately suspend the laying of the adjacent roofing. Standing water deeper than the thickness of a sheet of zinc or copper signals a geometric anomaly. In winter, the trapped water turns to ice, increases in volume and puts stress on the seamed joints or expansion joints. If the profile bellies between two rafters, the problem comes either from hook spacing that is too wide or from faulty wedging on the edge fascia board. Leaving this defect in place exposes the work to permanent deformation and to overflow towards the façade during storms.
- Findings and survey of the low pointsRemove the residual water with a clean sponge, mark the standing-water zone with a grease crayon and measure the deflection between supports using a two-metre aluminium straightedge fitted with a spirit level.
- Formal notice to site managementIf the false level comes from a sagging roof structure or a warped cornice board installed by a third party, record the reservation in writing in accordance with standard SIA 118 before any modification.
- Height correction of the hooksRemove the beads or retaining clips, loosen the fixing screws and insert bevelled rot-proof shims under the base of the hooks to restore the minimum slope of five millimetres per metre.
- Reinforcement of the support lineIf the deflection under load exceeds one millimetre under manual pressure, add an intermediate hook fixed to a solid timber spacer firmly anchored between the rafter heads.
According to CO, if any other circumstance jeopardises the proper or timely execution of the work, the contractor must inform the client immediately, failing which he bears the consequences. Once the shims and reinforcements are in place, a second watering test in the presence of site management validates complete drainage of the profile towards the outlet before the verge tiles are laid.
Frequently asked questions
What minimum slope should be adopted to guarantee drainage without standing water?
The recommended minimum slope in sheet-metal work is five millimetres per metre, i.e. zero point five per cent. This value compensates for the execution tolerances of the roof structure and ensures complete gravity drainage of rainwater towards the outlet sump. A lower slope considerably increases the risk of standing water at the soldered overlaps in the event of slight settlement of the structural work.
How should you react if the roof structure shows a deflection that reverses the flow line?
A gutter must never be fitted onto a deformed roof structure without formal notification. The sheet-metal worker must record the defect in writing to site management in accordance with standard SIA 118. Correction is made by compensating the height with custom-made hooks with variable heels or by applying trapezoidal furring pieces fixed directly onto the rafters before final installation.
What maximum spacing should be observed between two half-round gutter hooks?
The usual spacing between two hooks must not exceed forty-five to fifty centimetres for a suspended gutter in zinc or copper. In mountain regions or on roofs exposed to heavy snow loads, this spacing must be reduced to thirty-three or forty centimetres in order to prevent deflection of the metal profile and pull-out of the fixings under the weight of ice.
How should the water test be carried out after installation on the construction site?
The test is carried out in dry weather before the roofing is closed in. A volume of about twenty litres of water is poured at the upper end of the gutter line. The flow is observed as far as the outlet fitting. No residual puddle must remain after ten minutes. If visible retention is present, the height adjustment of the hooks must be corrected before acceptance.
Texts and standards cited
- COmaterial and ground: the contractor is liable for the good quality of the material he supplies; if the material supplied by the client or the ground designated by him is found to be defective, or if any other circumstance jeopardises the proper or timely execution of the work, he must inform the client immediately, failing which he bears the consequences (para. 3)
- norme SIA 118General conditions for the execution of construction work
