🧱 CFC 224Roofer safety, snow and roof maintenanceChapter 9 of 10 in the section

Roof maintenance manual: what is inspected, how often, and who may go up

On completion of the works, the roofer-plumber records the maintenance rules for the pitched roof in the work file. You will learn how to structure the maintenance manual, how to set realistic inspection frequencies for wooded or urban environments, how to list the critical check points and how to restate the safe-access requirements to protect your company's liability.

Key takeaways

  • Formally handing over the maintenance manual protects the roofer-plumber against claims for defects arising from use.
  • The annual inspection of valleys, verges and gutters prevents slow leaks under the underlay.
  • The frequency of visits is adapted to the surrounding tree cover, the prevailing winds and moss growth.
  • Only trained personnel may use the anchor points and fall-arrest devices installed on the roof slope.

The maintenance manual in the work file defines the limits of the company's liability

A leak occurring after three years of use because gutters are blocked by dead leaves or because rubble is blocking a recessed valley is not a construction defect. However, towards the client, the roofing and plumbing company can only be released from its liability if the rules of use and monitoring were formally defined in writing and handed over on delivery. Under art. 369 CO, the client's rights in respect of defects in the work are excluded where the defective execution is attributable to the client personally, in particular through obvious neglect of the routine maintenance required to preserve the materials.

  1. Drafting the project-specific documentSpecify the metals used (copper, titanium-zinc, powder-coated aluminium) and their oxidation behaviour, the nature of the small roofing elements (clay tiles, natural slates, fibre-cement) and the presence of accessories such as snow guards or ventilation tiles.
  2. Inventory of fall-restraint and access devicesAttach the exact layout plan of the safety hooks, anchor bars and lifelines installed on the roof slope, together with the initial inspection sheet and the instructions for the annual check.
  3. Formal handover to the clientRecord the manual in the operating binder handed to site management at the acceptance report, and have the acknowledgement of receipt signed.

This file must state unambiguously the consequences of a lack of maintenance: premature perforation of zinc flashings through the build-up of acidic organic matter, overflow of rainwater towards the thermal insulation during violent storms, or tiles weakened by frost being torn off in unventilated areas. The contractor also recommends taking out a periodic maintenance contract, priced indicatively according to the complexity of the roof.

Inspection intervals, critical points on the slope and safe access

Inspection intervals do not follow a single calendar: they depend directly on the geographical location, the pitch and the tree environment of the pitched roof. A roof exposed to prevailing winds carrying pine needles or deciduous leaves requires clearing twice a year, whereas an open slope on agricultural plain may be satisfied with one full annual examination, ideally planned for late autumn after all the leaves have fallen.

Inspection intervals and preventive actions according to the roof's environment
Environmental contextRecommended frequencyCritical inspection points
Dense tree cover in the immediate vicinity (deciduous, conifers)Twice a year (spring and late autumn)Hanging gutters, downpipes, recessed valleys, dormer aprons.
Urban or open rural setting, low pitchOnce a year (before winter)Leaf guards, chimney flashings, condition of flashings and finishing mastic joints.
Mountain area, heavy snow loadsOnce a year (at the spring thaw)Snow guards, fixing of ridge tiles, verge hooks, flatness of the slopes.

On the slope, the visual and manual inspection focuses first on the plumbing connections: no water retention behind ventilation pipes or chimney stacks, integrity of the seams on metal verges, freedom of movement for expansion of valley gutters and complete clearance of the underlay ventilation tiles. For the roof covering, the practitioner checks that the tiles are properly seated, that there is no frost cracking on the interlocks and that lichens retaining moisture are cleaned off.

Access to the gutters must be possible from secured internal access points (maintenance dormers with a reinforced threshold) or by aerial platform if no certified safety hook equips the eaves edge. Stating these technical limits in the manual protects the company if an unequipped third party acts imprudently on slippery battens or on materials made brittle by frost.

Critical points to inspect and intervals according to exposure

Preparing the maintenance manual requires a rigorous listing of the components of the pitched roof and of the plumbing work. The roofer-plumber records in it the elements exposed to mechanical stresses, temperature variations and weather. The inspection is not limited to a visual check from a distance on the ground; it targets specific critical points whose gradual failure causes concealed leaks before damaging the roof structure or the thermal insulation.

Check matrix for pitched roof components and recommended intervals
Work or componentDefects and deterioration looked forStandard intervalInterval in an exposed environment
Gutters, recessed channels and downpipesAccumulation of leaves, moss, sediment; blocked leaf guards; onset of corrosion or failure of soldered jointsOnce a year (late autumn)2 to 3 times a year (under forest cover or in a dense urban area)
Roof covering (clay tiles, concrete, slates)Cracked, broken tiles or tiles displaced by wind or frost; fouled interlocks; excessive lichen growthEvery 2 yearsAnnual (wooded north-facing slope or altitude above 1000 m)
Valleys, flashings, counter-flashings and plumbing connectionsCracking of the head sealing mastics, dislodged lead or zinc aprons, fouled chase clipsEvery 2 yearsAnnual (exposure to prevailing winds and large temperature swings)
Penetrations (chimneys, dormers, ventilation ducts)Adhesion of metal flashings, condition of drip edges, standing water on chimney back guttersEvery 2 yearsAnnual (alpine zone with compacted snow)
Snow guards and service hooksDeformation of tubular bars, fixings torn out under sliding load, loosened boltsOnce a year (before winter)Once a year, supplemented by a visual check after heavy snowfall
Eaves and overhangs (verges, drip edges)Deterioration of the underlay visible at the drip edge, blocked lower ventilation slots, pest nestsEvery 2 yearsAnnual (forest edge)

The microclimate dictates more frequent inspections. On agricultural plain or at the edge of a deciduous forest, organic deposits ferment quickly in copper or titanium-zinc plumbing components, generating corrosive acids that perforate thin metals through chemical attack beneath the sediment. In an alpine or pre-alpine setting, continuous frost blocks the slow flow of meltwater towards the eaves, causing temporary water retention that can get past the minimum overlaps if the verge clips or aprons are fouled. The manual must explicitly classify the building according to its location zone in order to justify the prescribed frequency.

Inclusion in the work file and release from liability

Drafting the maintenance manual is not a mere technical recommendation: it is the formal act that marks the boundary between a construction defect attributable to the tradesman and a fault resulting from the owner's negligence. Too often, a leak appearing after four years of use leads to a claim notice directed against the roofing and plumbing company, whereas the accumulation of dead leaves in a closed valley created backwater that rose above the waterproofing upstands. If no maintenance instructions were handed over in writing at acceptance, the client may plead legitimate ignorance of the technical obligations attached to their roof.

  1. Compiling the safety protocol and existing access arrangementsDraw up in the manual the roof access plan: location of the exit roof window, of the safety rungs and of the hooks for a roofer's ladder. Attach the layout diagram of the single anchor points or of the lifeline installed on the ridge, together with the manufacturer's initial inspection sheets.
  2. Defining the restrictions on workState formally in the document that work on the roof slope is reserved for qualified professionals with the personal fall-protection equipment required by the ordinance on construction work. Expressly exclude access by untrained persons to prevent falls through rooflights or fragile materials.
  3. Signed handover in the work fileInsert the maintenance manual in the work file handed to the client or to site management at final acceptance in accordance with SIA 118. Require the signature of a dated handover slip, which will be archived in the company file together with the execution drawings and the certificates of conformity.

The company systematically attaches to the manual a proposed addendum or a template periodic maintenance contract. Even if the client declines to take out this service with the company that carried out the work, this recorded refusal shows that the client was fully informed of the need for methodical follow-up. In the event of later water damage attributable to a blocked downpipe or to an unrepaired displaced tile, producing together the handover slip for the manual and the declined maintenance offer immediately rules out any characterisation as a hidden defect or an installation defect in the work.

Handling a leak dispute resulting from a lack of maintenance

When a leak occurs and the client gives notice of a defect, the reflex is to check without delay whether the problem stems from faulty workmanship or from a failure of maintenance. The contractor convenes a joint inspection record on the roof. On site, before any dismantling or cleaning, he takes overall and detail photographs: masses of dead leaves saturating the recessed gutters, moss blocking the side interlocks of clay tiles, conifer needles clogging the downpipe strainers or an accumulation of organic debris under the lead aprons. These material elements demonstrate irrefutably the physical blockage that directly caused rainwater to back up over the drip edge towards the insulation layers and the underlay.

  • The initial acceptance report with a written discharge proving that the technical maintenance manual was actually handed over.
  • The time-stamped photographic record establishing the fouling of the gutters or the plant colonisation of the interlocks.
  • An extract of the instructions handed over restating the inspection interval prescribed for the environment concerned.
  • The offer for restoration outside the warranty, stating the cost of the clearing and servicing work.

The contractor then compares these material findings with the requirements recorded in the work file handed over at acceptance. The signed maintenance manual attests the minimum interval prescribed, such as clearing twice a year at a forest edge, as well as the obligation to use qualified personnel equipped with appropriate protection. Under art. 369 CO, the client's rights in respect of defects in the work are excluded where the defective execution is attributable to the client personally. A clear failure to carry out the documented maintenance is precisely a cause attributable to the owner, which formally rules out the joint or contractual liability of the roofer-plumber for the leaks found. In the event of continued dispute, the technical expert opinion relies on SIA 118 to establish that the work as executed was entirely free of defects on delivery and complied with the technical rules.

Frequently asked questions

Can an owner instruct the caretaker to clean recessed gutters?

Going up on a pitched roof requires professional skills and strict fall-protection measures. The caretaker may only intervene if he has certified training in personal fall-protection equipment and if the building has compliant, inspected anchor points. Without secure access or proven qualification, the owner incurs civil liability. The work must then be entrusted to a qualified roofing or plumbing company.

At exactly what point must the maintenance manual be handed to the client?

The maintenance manual must be handed over at the acceptance of the work, formally included in the as-built file or work file. The contractor has it initialled and countersigned by the client or the client's professional representative as an annex to the acceptance report. A late handover, after a water-ingress loss has occurred, has no releasing value because the client could invoke an initial failure to inform about the constraints of use and maintenance of the roof.

Which specific points should be inspected after a violent storm or hail?

The post-storm inspection focuses first on water drainage: immediate removal of foliage and compacted hailstones in the metal valleys, downpipes and overflow outlets. On the roof covering side, the roofer-plumber checks for cracked or dislodged tiles, any torn-off snow guards and the integrity of the fixing brackets of the downpipes. He also checks that the force of the wind has not lifted the verge strips or deformed the flexible sealing flashings.

How can a move from an annual to a six-monthly inspection be justified?

The frequency depends directly on the immediate proximity of large deciduous trees or resinous conifers, and on exposure to prevailing winds. Pine needles and leaves form dense blockages very quickly. One visit in spring after pollination and a second in autumn after leaf fall avoid overloading the gutters before winter. The plant environment technically justifies this stricter recommendation set out in the manual handed to the owner.

Texts and standards cited

  • CO art. 369exclusion of the client's rights in respect of defects in the work where the defective execution is attributable to the client personally (instructions given contrary to the contractor's formal warnings, or any other cause)
  • SIA 118General conditions for the execution of construction works