Key takeaways
- The flue outlet must project at least fifty centimetres above the ridge to prevent any smoke backdraught.
- The safety clearance to combustible materials depends on the temperature class of the installed flue.
- The underlay penetration requires a watertight collar capable of absorbing thermal movement without tearing.
- Final validation of the work must be carried out with the master chimney sweep before any firing.
Height above the ridge and draught dynamics on a pitched roof
Positioning a chimney stack on a pitched roof is subject to strict physical and aeraulic constraints. The flue gas duct must necessarily terminate in a zone of laminar, stable airflow to guarantee constant negative pressure, whatever the direction of the prevailing winds. On Swiss roofs, the fire protection regulations issued by the Association of Cantonal Fire Insurance Institutions (AEAI) and standard SIA 232/1 set the minimum projection heights. An outlet located too low on the roof slope is subject to swirling air turbulence or downdraughts along the pitch, which causes immediate backdraught of combustion gases towards the connected appliance.
| Position on the roof slope | Horizontal distance to the ridge | Minimum outlet height | Aeraulic constraint addressed |
|---|---|---|---|
| Directly next to the ridge | Less than 4.00 m | 0.50 m above the ridge | Clears the cushion of compressed air created by the wind on the pitch. |
| Middle or lower part of the slope | More than 4.00 m | 1.00 m perpendicular to the slope and above the ridge | Avoids downward swirls of cold air in the hollow of the slope. |
| Roof against an adjacent building | Less than 10.00 m from a façade | 0.50 m above the zone of influence | Compensates for the negative-pressure zone generated by the vertical obstacle. |
For low-pitch roofs or buildings in exposed areas such as the pre-Alpine valleys and the Plateau corridor, turbulence effects often require extending the chimney head beyond the strict normative minimum. The roofing plumber then takes charge of designing a rigid guying system or a reinforced flashing to prevent tearing off under gusts. During such work on the upper parts of the roof, OTConst art. 41 provides for appropriate measures to prevent falls from a fall height of more than 2 m. The worker uses scaffolding or restraint equipment sized for the pitch.
Distance to combustible materials, weatherproofing of the penetration and acceptance
Passing through a timber roof structure raises the problem of permanent heat transfer between the flue wall and the roof structure. A flue transmits heat by conduction and direct radiation to the rafters, battens and underlay boards. The AEAI directives require a safety distance calculated from the temperature class of the flue liner. For a double-wall metal flue designated G50 or G100, the minimum free air gap to any combustible material must be 50 mm or 100 mm respectively. This annular space must never be filled with flammable synthetic insulation; only incombustible mineral wool of fire reaction group RF1 may be tolerated if the system is approved for it.
- Checking the trimmer frame and safety distancesMeasure the free space between the outer face of the flue and the timber trimmer frame cut by the carpenter, to ensure strict compliance with the AEAI dimensions before any closing-in.
- Watertight connection of the underlayFit a heat-resistant EPDM collar, bonded with acrylic tape to the underlay and turned up 150 mm against the metal wall to block water ingress.
- Providing annular ventilationProvide continuous ventilation airflow around the flue by means of a deflector drip so that accumulated heat is evacuated without allowing wind-driven water to enter.
- Fabricating the metal flashingFit the flashing, the apron flashing and the side soakers in titanium-zinc or copper, providing a chase collar that allows the flue liner to slide freely under thermal movement.
Acceptance of the work requires a direct exchange with the master chimney sweep before the final cladding of the stack. The chimney sweep checks the compliance of the distances to timber, the accessibility of the outlet and the condition of the expansion joints. Under CO art. 365, if a circumstance jeopardises the proper or timely execution of the work, the contractor informs the client. The finding of a trimmer frame that is too tight or of a vapour barrier bonded in contact with the pipe requires this immediate notice so that the load-bearing structure can be corrected. This interdisciplinary coordination ensures that the roof remains watertight while eliminating the risk of fire damage.
Outlet geometry and clearances to timber: the compromise between draught and fire clearance
Positioning a chimney stack on a pitched roof confronts the roofing plumber and the roofer with two opposing physical requirements. On the one hand, correct operation of the heat generator requires constant thermal draught, which depends on stable aerodynamic negative pressure. This negative pressure requires escaping the turbulence and overpressures created by the wind on the slopes, which pushes towards raising the flue well above the ridge line. On the other hand, fire safety requires strict separation of the hot wall from roof timbers, battening and combustible underlays, while limiting wind exposure and the lever arms that mechanically stress the watertight joints.
| Flue situation | Required outlet height | Minimum distance to timber | Associated construction measure |
|---|---|---|---|
| Close to the ridge (horizontal distance < 2.00 m) | 0.50 m above the ridge | According to the clearance rating of the certified flue (often 50 to 100 mm) | Open trimmer frame, incombustible rock wool packing (class A1) |
| Mid-slope (horizontal distance > 2.00 m) | At least 1.00 m perpendicular to the pitch | Clearance guaranteed without breaking the roof thermal bridge | High metal upstand with lead or flexible aluminium apron flashing |
| Dormer or roof window within 5.00 m | 1.00 m above the top of the nearest opening sash | Continuity of the vapour barrier stopped on an incombustible collar | Raising by an insulated double-wall element with rain cap |
| Roof with combustible roofing materials | 0.80 m above the ridge or 1.50 m along the pitch | Total prohibition of contact between the casing and the battens | Ventilated metal sleeve projecting below the roof structure |
Where the clearance measured between the outer face of the flue block or insulated metal flue and the rafters does not meet the fire clearance shown on the manufacturer's marking, the roofer must on no account plane down the timber member or slip in an ordinary compensating batten. If the framed opening delivered to the construction site proves non-compliant with the templates required by the AEAI fire protection regulations, the contractor warns the site management. In accordance with CO art. 365, the contractor reports defects in the ground or in the supplied elements that jeopardise the proper execution of the work, in order to demand that the carpenters redo the trimmer frame before battening.
Multilayer weatherproofing, sleeve ventilation and acceptance by the chimney sweep
The penetration of a pitched roof concentrates infiltration stresses. The connection begins at the level of the air and vapour barrier layer. The inner membrane must be connected to a special airtight collar, classified as flame-retardant, designed to withstand the permitted contact temperature. Higher up, the underlay sheet is turned up at least 15 cm along the flue shaft, fixed with a pure acrylic adhesive tape suitable for underlay membranes or mechanically clamped by a metal profile. Upstream of the opening, the roofer systematically installs a diagonal drainage gutter in the underlay to channel any condensation or leakage water towards the adjacent rafters.
The penetration of the metal elements fabricated by the roofing plumber – copper, pre-patinated zinc or aluminium sheet – must allow for thermal expansion of the flue liner. The lower upstand, the side soakers and the upstream water channel are never welded directly to the outer wall of a single-wall metal flue. A ventilation sleeve with an annular thickness of at least 20 mm must be provided between the active flue and the outer cladding casing. This ventilated annular void allows continuous removal of heat by natural convection, preventing heat build-up under the metal flashings and under the tile or slate roofing.
Final compliance of the outlet necessarily involves close coordination with the cantonal master chimney sweep before the final closing of the coverings under the roof. The chimney sweep validates accessibility to the top of the flue: where an outlet rises more than 1.20 m above the roof slope or on a pitch exceeding 30°, the roofing plumber and the roofer must provide the regulatory access devices, such as roof steps, compliant anchor hooks or a secured maintenance walkway. A deliberate breach of fire safety rules during execution, exposing persons to a risk to life when the appliance is fired, engages the criminal liability of the builder within the meaning of CP. The chimney sweep's signature on the thermal inspection certificate allows reservations to be lifted and validates the inclusion of the metalwork in the roof's warranty record.
Handling non-conformities: insufficient fire clearance, impaired draught and refusal of acceptance
On the construction site, the conflict between roof geometry and the flue outlet often arises late. Critical situations occur when the flue terminates too low in an aerodynamic overpressure zone, or when the roof trimmer frame does not respect the minimum clearance to the outer wall of the flue. If the fire clearance is not achieved when the upstand is being fitted, the roofing plumber must suspend the connection. Under CO art. 365, if a circumstance jeopardises the proper or timely execution of the work, the contractor informs the client. The notice of defects must state that fire safety cannot be guaranteed without modifying the structure or fitting an approved heat shield.
| Defect found | Technical origin | Corrective measure on the construction site | Responsible party |
|---|---|---|---|
| Fire clearance below the manufacturer's data | Trimmer frame too narrow or flue off-axis | Fitting a ventilated incombustible insulating shell or reworking the roof structure | Carpenter / Chimney installer |
| Air backdraught and insufficient draught | Outlet located below the ridge in the turbulence zone | Vertical extension of the double-wall flue and adaptation of the guying | Roofing plumber / Chimney installer |
| Condensation under the metal upstand | No ventilation of the sleeve or thermal bridge | Creating upper and lower ventilation openings protected against snow | Roofing plumber |
| Refusal of compliance at inspection | Flashing incompatible with the thermal class of the flue | Replacing the weatherproofing collar with a certified model | Roofing plumber / Installer |
In case of refusal at acceptance by the cantonal master chimney sweep, no firing may take place. Bringing the work into compliance often requires raising the flue liner or rebuilding the underlay connection with a flexible high-temperature-resistant collar. If the modification involves raising the flue more than one and a half metres above the roofing plane, the roofing plumber coordinates the anchoring of rigid guys to the load-bearing rafters. Any modification to the upstand must preserve the free expansion play of the metal and the free circulation of the ventilating air, ensuring that no heat build-up overheats the battens or the roof boarding.
Frequently asked questions
What to do if the outlet height at the ridge does not respect the turbulence-free zone?
When the flue terminates too low relative to the ridge or nearby obstacles, the negative pressure required for draught is lacking. The roofing plumber reports the anomaly to the site management. The solution is to add an insulated double-wall flue element at the top and adapt the zinc collar. If the free height exceeds the self-supporting limits of the system, rigid guys fixed to the roof structure are mandatory.
How to remedy an insufficient safety distance between the flue block and the roof timber?
If the safety clearance to combustible materials prescribed by the AEAI directives is not maintained in the trimmer frame, the roofing plumber must not fit the upstand. The carpenter must trim or offset the timbers if the structural design allows. Failing that, a certified incombustible heat shield, ventilated on its underside and validated by the fire protection authority, must be interposed between the hot wall and the timber.
What role does the master chimney sweep play before the final closing of the chimney flashing?
The master chimney sweep or fire inspector checks the compliance of the work before firing. Prior coordination on the route, the outlet height and the maintenance access avoids disputes. The sweep inspects in particular the distances to timber members, the annular ventilation of the sleeve and the presence of a flashing suited to the flue gas temperature. Formal approval is a condition for commissioning.
Why is it forbidden to seal the top of a metal upstand tightly around the flue?
The flue undergoes significant axial thermal expansion under the effect of the burnt gases. A rigid seal would break the metal or deform the upstand. Moreover, the annular space between the flue block and the sheet-metal cladding must imperatively remain ventilated to evacuate residual heat and prevent heat transfer to the combustible layers of the pitched roof.
Texts and standards cited
- CO art. 365material and ground: the contractor is responsible for the good quality of the material he supplies; if the material supplied by the client or the ground designated by him is found to be defective, or if another circumstance jeopardises the proper or timely execution of the work, he informs the client immediately, failing which he bears the consequences (para. 3).