🧱 CFC 224Penetrations, dormers and special detailsChapter 1 of 10 in the section

Roof window: installation height, weatherproofing connection and underlay connection

This chapter details the rules of the trade for positioning and weatherproofing a roof window on a pitched roof. You will learn how to set out the unit within the rafter pitch, ensure the continuity of the underlay using the collar and the upstream diverter gutter, then connect the surface metalwork to the roofing material to rule out any lasting water ingress.

Key takeaways

  • Position the frame between 90 and 110 centimetres above the finished floor to ensure a good view and easy operation.
  • Always connect the rainproof collar to the frame before closing up the roofing, to avoid hidden water ingress.
  • Install an inclined diverter gutter upstream of the trimmer opening to drain water from the underlay.
  • Select a connection kit strictly suited to the profile and the wave height of the material.

Positioning the frame and locking in the weatherproofing of the underlay

The height positioning of a roof window meets precise criteria of ergonomics and roofing layout. The ideal sill height is between 90 and 110 cm above the finished interior floor, allowing an unobstructed view from a seated position, while the top of the frame reaches 200 to 220 cm so that the upper handle can be operated without effort. On the roofing side, the bottom of the frame must rest on an intermediate bearing batten fixed above a complete row of whole tiles. Poor wedging forces awkward cutting of the sill tiles or dangerously reduces the cover of the lower weatherproofing apron, creating a serious risk of water ingress. This positioning ensures smooth shedding of rainwater at the surface while respecting the required ventilation beneath the roofing.

  1. Wedging and fixing the frameFix the metal brackets to the counter-battens and the load-bearing rafters. Check the levels, squareness and equal diagonals of the frame carefully before final screwing. Check the parallelism of the rebate clearances by engaging the sash.
  2. Installing the upstream diverter gutterCut the underlay between the rafters above the trimmer opening. Slide the metal diverter channel under the upper counter-battens with a minimum transverse slope of 2 %, so as to divert the flow towards the adjacent rafter bay.
  3. Connecting the cut upper sheetInsert the free edge of the existing membrane directly into the groove of the diverter gutter. The water running down the underlay upstream is caught before the obstacle and guided out of the opening.
  4. Pressing down the rainproof collarUnfold the preformed underlay sleeve around the frame. Staple it to the timber frame, fold it down onto the surrounding battening and seal each joint with a watertight and windtight acrylic adhesive tape.

Matching the flashing kit and taking care with the surface metalwork

The upper weatherproofing connection tolerates no improvisation and depends directly on the nature of the roofing material. Manufacturers offer prefabricated flashing kits according to the thickness and profile of the elements: kits for flat materials less than 16 mm thick such as natural slates or shingles, kits for tiles with strong wavy relief incorporating a flexible pleated apron, or recessed kits lowering the frame into the pitch to refine the appearance. For standing-seam metal roofing, the roofer fabricates a made-to-measure flashing in titanium-zinc or copper with sliding seam clips and welded step flashings. This workshop fabrication allows free expansion of the metal while neutralising the risk of capillary rise under the effect of prevailing winds.

Selection of connection kits and weatherproofing components
Roofing materialType of flashingSpecific installation detail
Clay plain tilesConnection for small flat elementsMetal step flashings interleaved under each course of tiles with full overlap.
Wavy interlocking tilesProfiled connection with flexible apronPleated apron pressed down onto the wave, foam filler cut to the curve of the tile.
Standing-seam metal roofingMade-to-measure flashingClip plates, side step flashings and watertight seams with no visible perforation whatsoever.

The metal pieces are installed in an unchanging stacking order: lower apron first, then side channels, and upper cover last. The lower apron is carefully pressed down with a mallet or roller onto the dusted tiles so as to follow the troughs and crests of the waves, without forming a pocket of standing water. The side and upper tiles are cleanly cut, leaving a free clearance of 30 to 60 mm along the drainage channel to prevent the build-up of needles or moss. No nail or screw may pass through the drainage channel; fixing is achieved by tabs folded over the battens.

Installing the underlay collar and the diverter gutter

The weatherproofing of a glazed penetration in a pitched roof must rest on two separate, superimposed barriers: the visible weatherproofing provided by the metal connection kit at the surface, and the hidden weatherproofing provided by the continuity of the underlay. If the primary connection beneath the roofing is neglected or poorly bridged, ingress of powder snow, condensation from the underside or scouring caused by driving rain runs along the frame without being drained away. This moisture then enters directly into the thermal insulation and counter-battening, causing insidious deterioration of the structural timber for years before the first visible sign on the ceiling.

  1. Opening and cutting the existing sheetCut the underlay membrane in a trapezoidal or envelope-shaped opening at the trimmer opening. Keep sufficient surrounding overhangs to allow a continuous vertical upstand against the outer perimeter of the frame.
  2. Fitting the weatherproofing collarUnfold the preformed collar around the perimeter of the frame. Staple the upper part of the flexible apron into the perimeter groove of the frame, then bond the perimeter skirt onto the existing rainproof membrane using a windtight and watertight acrylic adhesive tape.
  3. Installing the upstream water diverter gutterCut the counter-battening and the underlay sheet at a distance of 30 to 50 cm above the trimmer opening. Insert the metal drainage profile with a lateral slope of at least 2 % towards a neighbouring rafter bay free of penetrations. Fold the upper sheet down into the groove of the profile to ensure a downward overlap with no risk of backflow.

Installation height in the pitch and matching of the connection kits

The height position of the frame in the roof plane determines both proper gravity drainage and the minimum water cover beneath the roofing elements. A window installed too high or too low in relation to the tile gauge creates a point of mechanical blockage. Upstream, the distance between the frame and the upper row of roofing must allow runoff water to flow freely and the metal cover to be positioned, while downstream, the pleated apron must follow the relief of the tiles without creating a counter-slope.

Choosing the connection kit according to the nature and relief of the roofing material
Roofing materialSide connection profileMinimum upstream water coverMetalwork specifics
Clay plain tilesIndividual metal step flashings slid in at each course100 mm under the upper courseDirect overlap without protruding foam apron
Interlocking tiles with strong curvatureSide channels with malleable lower apron150 mm under the upper courseManual pressing down of the pleated collar into the mould base
Natural slates or fibre-cementThin interleaved brackets or step flashings80 mm under the upper courseCareful crimping on the roof battens
Profiled sheet or standing seamHemmed side strips with sliding tabs120 mm under the upper courseConnection by double folding or tin soldering

Selecting a factory connection kit that does not match the thickness or wave of the material exposes the works to water ingress in gusts. For standing-seam metal roofing or thin flat slate roofs, the use of universal connectors for wavy tiles leaves gaping side openings at the compressed foam strips. In these specific configurations, the roofer fabricates made-to-measure step flashings or assembles a surrounding channel in brazed copper or titanium-zinc, guaranteeing lasting weatherproofing without resorting to elastomeric filler sealants.

Water ingress damage: diagnosis and repair of concealed connections

Water ingress linked to a roof window often shows up several months, even several years, after acceptance of the roof. When stains appear on the interior lining or the insulation becomes soaked, the visible metalwork is rarely the only element at fault. The defect almost systematically originates in the underlay interface: torn collar, adhesive connection detached by thermal variations, or a missing upstream diverter gutter. Meltwater, backflow in strong winds and powder snow then bypass the frame on the underside of the tiles and slowly penetrate into the heart of the insulating build-up.

  1. Methodical removal of the roofing around the windowRemove the layer of tiles or slates over at least three courses above the trimmer opening and two courses on each side. Carefully unclip and unscrew the side profiles and the upper metalwork cover in order to reach the frame and the battens without bending the metal.
  2. Complete reconstruction of the underlay collarIf the membrane is cut flush with the frame without a watertight upstand, fit a new weatherproofing collar or strips of breathable membrane. Staple to the frame, bond with a special underlay polyurethane adhesive and connect the upper sheet airtight with an overlap of 150 mm.
  3. Installing and aligning the diverter gutterCut a section of counter-batten approximately 200 mm above the frame to insert the transverse gutter. Set a slope of at least 2 % towards a neighbouring rafter bay. Engage the upper underlay sheet in the channel to divert any condensation or lateral ingress water.
  4. Refitting the matching kit and adjusting the seating heightReassemble the connection kit elements suited to the roofing: pleated apron on curved tiles or step flashing channels on plain tiles. Check the height position of the frame in relation to the downstream tile gauge and observe a clearance of 60 to 80 mm upstream to avoid ice build-up.

Frequently asked questions

How should the roof window be connected if the existing underlay is a bituminised wood-fibre board?

On a rigid wood-fibre sub-roof, the flexible collar cannot simply be stapled. The board must be cleanly cut at a bevel above the trimmer opening to house the metal diverter gutter. The watertight connection is made using a self-adhesive bituminous or butyl sealing strip reinforced with aluminium, previously coated with a specific bonding primer on the board to ensure lasting adhesion against the upstand of the frame.

Why is it forbidden to omit the upstream diverter gutter on a low pitch?

On low pitches, water seeps more easily under the roofing by capillarity and runs directly onto the underlay sheet. Without an upstream diverter gutter inclined transversely, this film of water inevitably butts against the upper frame of the roof window. The static water pressure eventually breaches the adhesives or staples of the collar, causing insidious rotting of the upper cross-member of the trimmer opening.

Which connection apron should be chosen between a plain tile and an interlocking tile with strong relief?

For a plain tile or a slate, a kit with side step flashings and no visible pleated apron is installed, because the elements fit flush with the metalwork. By contrast, for an interlocking tile with strong curvature, a malleable pleated apron in lacquered aluminium or composite is essential at the foot of the window. It must be carefully pressed down with a mallet onto the wave of the lower tiles to block backflow.

How should the cutting of the roof battens be managed to respect the installation height of the frame?

The recess dimension depends strictly on the downstream tile gauge line. The batten supporting the bottom of the frame must be positioned precisely according to the manufacturer's marks and the wave height of the tiles. A batten set too low forces excessive cutting of the roofing under the window, weakening the seating of the connection. A batten set too high creates a rise that breaks the natural flow of water in the side channels.

Texts and standards cited

  • CO art. 368client's rights in the event of defects in the work: rejection, price reduction, remedying, damages