Key takeaways
- From a fall height of two metres, collective protection becomes mandatory at the edge of the slope.
- The incline accelerates sliding and turns any loss of grip into an uncontrollable path towards the eaves.
- From a pitch of sixty degrees, working directly on the roof covering is strictly prohibited.
- Very steep slopes require work to be carried out exclusively from scaffolding or a mobile elevating work platform.
Fall height and sliding dynamics: the decisive pitch thresholds
On a pitched roof, collective safety is not limited to stopping a vertical fall at the eaves edge. The dynamics of an accident depend directly on the angle of the slope: the steeper the incline, the more the friction of the soles on the battens, tiles or underlay decreases in favour of gravitational acceleration. Under art. 41 OTConst, appropriate measures to prevent falls must be taken from a fall height of more than 2 m. This height is measured vertically below the roof edge, relative to the ground or to a lower level that would receive the fall. As soon as the pitch increases, the risk no longer lies only in tipping directly over the edge, but in being unable to stop a slide that begins several metres further up.
| Slope pitch | Physical behaviour | Minimum collective protection required |
|---|---|---|
| Pitch below 25° | Slide slowed by the grip of the materials | Perimeter guardrail or catch platform at the eaves edge. |
| Pitch between 25° and 60° | Rapid acceleration of the slide with no chance of recovery | Roofer's catch platform or catch scaffolding with protective wall. |
| Pitch above 60° | Fall equivalent to a vertical drop; impossible to stand upright | Working scaffolding or mobile elevating work platform. |
When work is carried out between 25 and 60 degrees, maintaining a stable working posture is very tiring on the ankles and lower back. The roofer or sheet-metal worker cannot move forward standing directly on the slope without aids to progression, such as roof ladders securely hooked onto the battens or slope brackets. Although this local equipment improves ergonomics, it never replaces the catch protection at the foot of the slope. If the underlay is damp or dusty, the coefficient of friction drops drastically, making perimeter catch protection at the bottom of the slope strictly indispensable from the very first hammer blow.
The 60-degree tipping point: securing work off the slope using an elevating work platform
Crossing the 60-degree threshold marks a fundamental technical break in the ordinance on construction work. In accordance with art. 41 OTConst, on roofs with a pitch of more than 60°, work must be carried out only from scaffolding or a mobile elevating work platform. At this incline, comparable to the steep lower slopes of Mansard roofs or turrets, it is strictly forbidden to walk on the roof slope or to place one's feet on the battens in order to work. The tradesperson can no longer use the roof structure or the roof covering as a working surface: their body must be fully supported by an independent external structure.
The mobile elevating work platform, commonly called a cherry picker, is a particularly effective solution for maintenance work, localised replacement of sheet-metal flashings or laying courses of tiles in the upper part of a roof. It eliminates the cost and time of erecting heavy scaffolding while guaranteeing a work position protected by a full perimeter guardrail. The operator stands in the basket, has tools at shoulder height and adjusts position without exerting any mechanical pressure on an old or slippery roof covering. However, using this machine requires rigorous logistics on the construction site.
- Ground assessment and positioningCheck the bearing capacity of the ground, keep the machine away from buried services and deploy the outriggers according to the manufacturer's recommendations, using spreader pads.
- Defining the working envelopeCalculate the maximum horizontal outreach needed to reach the ridge or valley without approaching overhead power lines and without exceeding the load limits of the basket.
- Securing the operator and manoeuvresWear a restraint harness with a short lanyard connected to the platform's dedicated anchor point to prevent ejection from a catapult effect during travel movements.
Pitch thresholds and the switch to a ban on standing on the rafter slope
On a roof slope, the physics of the fall risk changes radically with the angle formed with the horizontal. Up to moderate inclines, the friction of safety soles on the battens or underlay still makes it possible to control an occasional loss of balance. By contrast, as soon as the slope steepens, the tangential component of the worker's weight overcomes grip: any misstep instantly becomes an accelerated slide that muscular strength cannot stop. Under art. 41 OTConst, appropriate measures to prevent falls must be taken from a fall height of more than 2 m, in the form of a roofer's catch platform or a perimeter guardrail depending on the roof pitch. But when the incline passes critical values, the protective systems shift from simple perimeter catching to an outright ban on moving directly on the slope.
| Slope pitch | Dynamic behaviour on loss of balance | Collective protection required at the foot of the slope | Permitted way of working on the slope |
|---|---|---|---|
| Up to 25° (approx. 47%) | Slow to moderate slide; spontaneous stop possible on a rough, dry surface. | Perimeter guardrail or catch platform from a 2 m fall height. | Direct movement on foot on the battens or the finished roof covering. |
| From 25° to 60° (47% to 173%) | Accelerated slide unavoidable; violent impact against the eaves protection. | Solid catch wall, net or raised roofer's catch platform. | Roof ladders fixed to service hooks or scaffolding brackets. |
| More than 60° (> 173%) | Almost vertical fall along the surface; immediate tipping of the body. | Independent ground-supported scaffolding or tiered façade platform. | Standing on the slope totally prohibited: work exclusively from platforms. |
Deploying the mobile elevating work platform on steep slopes and steep lower slopes
When ground-supported scaffolding has not been extended over the full height of the slope, or when the duration of the work does not justify erecting a heavy tubular structure on brackets, the mobile elevating work platform (MEWP) is the only compliant solution for pitches above 60°. It removes any direct support of the worker on the roof covering, thus avoiding both mechanical damage to fragile materials (fired tiles, fibre-cement, natural slates) and exposure of the sheet-metal worker to the drop. The basket then serves as a stable, mobile work position, carrying the tradesperson, hand tools and trays of prefabricated parts needed for the waterproofing connection.
- Ground set-up and bearing capacity checksPosition the machine's chassis on a stable base able to take the point loads of the hydraulic outriggers. Spread the pressures using hardwood or high-density polyethylene pads, taking into account buried pipes, vaulted cellars or paved vehicle access.
- Three-dimensional approach to the working areaDeploy the articulated or telescopic boom in accordance with the rated load diagram. The basket's path must clear the eaves, recessed gutters and cornice projections without pushing against any flashing or timber fascia.
- Positioning parallel to the slopeAdjust the orientation of the basket so that the long side of the platform is parallel to the inclined surface being worked on. The basket floor must remain horizontal at all times, and the sheet-metal worker works over the platform's guardrail, never climbing over it or sitting on the top rail.
- Safe handling of roofing elementsSupply materials (courses of tiles, eaves strips, dormer trims) while strictly observing the platform's rated load. Secure sharp or heavy items to prevent any object falling to the ground or onto the glazing below.
Using an elevating work platform on sheet-metal and roofing construction sites requires careful anticipation of weather conditions. Excessive wind load on large-area sheets, or a gust of bise channelled by the building's geometry, can quickly destabilise the crew or trip the boom's overload safety. In addition, the working area on the ground must be cordoned off with a barrier that cannot be crossed, to keep the public and road vehicles out of the swing radius of the counterweight and out from beneath the lifting zone.
Handling critical situations on a steep slope and safe withdrawal
In the field, the real pitch of an attic roof or steep lower slope may exceed the initial measurements. As soon as the incline passes 60 degrees, the roofer can no longer work while supported by the slope, even when wearing a harness or held by an eaves guardrail. Art. 41 OTConst requires appropriate measures to prevent falls from a fall height of more than 2 m, and requires that on roofs with a pitch of more than 60°, work be carried out only from scaffolding or a mobile elevating work platform. If the ground does not allow the platform to be stabilised, or if the boom does not cover the area without a dangerous lean, the team must stop work on the slope.
- Stop the work and secure the machineLower the platform to transport position as soon as anemometers show gusts above the machine's limits, or if any support settles.
- Close off the area below the slopeMark out the swing radius and the area beneath the slope on the ground with rigid barriers to prevent any third-party access, given the risk of tools sliding off.
- Reconfigure the working arrangementAssess with the site management whether to replace the elevating work platform with a full working scaffolding or to change the installation plan.
When access by mobile platform is blocked by obstacles that cannot be overcome, such as overhead cables, an open excavation at the foot of the façade or insufficient asphalt bearing capacity, the foreman reports the blockage and does not attempt any manoeuvre at the limit of the machine's reach. Work on steep slopes requires firm ground, correctly sized support pads and a stable work position. Any change of method must be technically agreed before roofing operations resume.
Frequently asked questions
From what fall height does perimeter protection become mandatory on a pitched roof?
As soon as the potential fall height exceeds 2 m at the roof edge, collective measures must be put in place. On pitched roofs, this protection is provided by either a perimeter guardrail or a roofer's catch platform, depending on the geometry of the slope. Below this threshold, the risk of falling outwards is tolerated without specific collective protection, unless particular hazards or protruding elements at ground level make the situation worse.
Why can the tradesperson no longer stand on the slope above a pitch of 60 degrees?
From an incline of 60 degrees, the grip of footwear on the roof covering or battens becomes almost nil and the precarious balance allows no safe movement. If a foothold is lost, the slide instantly turns into an accelerated free fall along the slope. Protection at the bottom of the roof is no longer enough to dissipate the kinetic energy. The tradesperson must work from a dedicated scaffolding platform or a mobile elevating work platform.
Which weather criteria require a mobile elevating work platform to stop work on a steep slope?
Wind is the main threat when using a mobile elevating work platform near roof slopes. Most manufacturers permit use up to the maximum speeds shown on the manufacturer's plate, generally around 45 km/h. In gusts, storms or ice forming on the controls and the floor, the wind load on the basket destabilises the boom and requires immediate descent to the ground.
What should be done if the ground cannot support the outriggers of a mobile elevating work platform in front of the building?
If the bearing capacity of the ground is uncertain, particularly on recent fill or a hollow pavement, the team must refuse to set up. Certified load-spreading plates are essential, but if the ground strength remains insufficient, the steep roof slope cannot be reached by platform. The erection of working scaffolding anchored to the façade must then be coordinated with the technical office in order to reach the slope.
Texts and standards cited
- OTConst art. 41measures to be taken at roof edges: appropriate measures to prevent falls from a fall height of more than 2 m (roofer's catch platform and/or perimeter guardrail depending on the roof pitch); on roofs with a pitch of more than 60°, work only from scaffolding or a mobile elevating work platform (para. 3)