Key takeaways
- The horizontal handrail extension measures at least thirty centimetres without creating a protruding obstacle.
- The return closed against the wall or the floor protects visually impaired users against the risk of snagging.
- Stair nosings require a contrasting strip of at least forty millimetres, visible when descending.
- A tactile warning zone must precede the first descending step on access landings.
Designing the horizontal extension and the tactile markers of the handrail
For the metalworker, staircase accessibility is not limited to adding a standard handrail. The grip must be uninterrupted over the whole flight, including at intermediate landings. At the start and end of the flight, the metal handrail must extend horizontally by at least thirty centimetres beyond the going line of the first and last step. This arrangement allows a visually impaired person or a person with reduced mobility to steady their balance before taking the step or after having crossed the change in level.
The free end of a metal tube is a dangerous trap when it stops abruptly in mid-air. The terminal return must always be formed by bending or by welding a prefabricated short-radius elbow, then ground free of any roughness before surface treatment. In public settings or in shared circulation areas, the metalworker prefers a loop that returns down to the stringer or a ninety-degree corner return directed towards the masonry wall with a residual gap not exceeding fifty millimetres. This geometry prevents a bag strap or a white cane from becoming caught under the steel.
- Recommended round tubular handrail section: outside diameter of forty to forty-five millimetres for a fully ergonomic grip.
- Tolerated rectangular sections: forty by thirty millimetre profile with chamfered edges or edges rounded to a minimum radius of two millimetres.
- Clearance to the wall: minimum distance of fifty millimetres between the inner face of the handrail and the plaster to avoid scraping the fingers.
- Tactile floor marking: embossed engravings or machined metal rings on the underside of the tube to announce the level.
Treating the visual contrast of nosings and installing the tactile warning marker
Visual marking of the steps prevents falls on the level, particularly when descending, where the perception of the drop requires an immediate distinction between the tread and the riser. On a metal staircase made of folded sheet steel treads, pressed grating or pans intended to receive a screed, the front edge must be treated with a high luminance contrast against the rest of the step. This contrast must be present over a width of between forty and fifty millimetres from the outer edge of the nosing.
| Type of metal support | Recommended metalwork method | Non-slip hold and contrast |
|---|---|---|
| Powder-coated or bare folded sheet | Contrasting anodised aluminium profile screwed from below or riveted | Sanded resin insert or integrated non-slip mineral strip |
| Electroforged steel grating | Specific perforated nosing angle welded in the workshop before galvanising | Contrasting chequer plate mechanically fixed to the front edge |
| Metal pan with thin infill | Brushed stainless steel corner edge profile with visual offset | Through-tinted polymer insert sealed in the rebate of the profile |
- Setting out and aligning the tactile landing markerPosition the tactile warning surface on the arrival or departure landing, parallel to the nosing of the first descending step. According to accepted practice and the SIA 500 standard, the installation generally starts fifty centimetres from the stair nosing in order to leave a full step of deceleration for the user guided by a cane.
- Mechanical fixing of studs or guidance stripsOn a metal landing, drill the structural plate to install stainless steel or brass tactile studs by threaded stud fixing or certified structural bonding. Do not use thin adhesives on the inside for external areas exposed to frost.
- Installing the contrasting stair nosingsApply the nosing profiles over the whole usable width of the metal staircase. Check that the added edge does not create a vertical step of more than two millimetres, which could cause a trip when going up.
Workshop fabrication and assembly of metal sub-assemblies
Workshop fabrication of an accessible handrail compliant with the SIA 358 standard requires constant geometric rigour. To guarantee smooth guidance along the flight, carbon steel or stainless steel tubes of forty to forty-five millimetres in diameter are mitre-cut then bent without crushing the section. The horizontal extension at both ends of the staircase ends in a closed return, folded back towards the wall or the stringer. This geometry removes the risk of personal belongings snagging while signalling the end of the route to the cane or the palm. TIG welds are carefully dressed flush then blended with a fine abrasive to form a smooth continuity, without excess thickness or metal burr. On powder-coated parts, a chamfer softens sharp edges to prevent local thinning of the protective powder coating.
| Metal sub-assembly | Workshop assembly method | Surface finish | Tactile and visual compliance |
|---|---|---|---|
| End return | TIG weld with internal sleeve | Satin or fine brushed polish | No step under the palm |
| Tactile marker ring | Plug weld or concealed pinning | Micro-bead blasting before powder coating | Clean relief without sharp edge |
| Cranked wall bracket | Tapped plate welded under the tube | Continuous anti-corrosion treatment | Free clearance for the fingers to slide |
| Added nosing profile | Mechanical fixing with countersunk stainless steel screw | Contrasting hard anodising | Directly flush with no tripping risk |
The contrasting nosing on folded sheet, chequer plate or grating requires careful preparation of the supporting metal. On hot-dip galvanised steel, the holes for mechanical fixing are made in the workshop before dipping in order to preserve the integrity of the zinc coating. When resin, mineral or heat-bonded strips are applied, the metalworker carries out complete solvent degreasing followed by mechanical brushing of the substrate to ensure excellent adhesion under repeated foot traffic.
On-site installation, assembly tolerances and acceptance of the work
Fixing the handrails and the floor markers requires methodical prior coordination with the structural work and the screed applicators. The metalworker must set his markers to the metric level line established by the site management. Any variation in the thickness of the floor build-up changes the usage height of the rail, which must remain between eighty-five and ninety centimetres above the edge of the steps and on the landings. For their part, the tactile warning slabs placed at the head of a descending flight are installed parallel to the finished stair nosing, with a precise setback guaranteeing adequate tactile reaction time before crossing the first step.
- Surveying levels and setting out anchoragesCheck the metric reference on the concrete walls and check the planned thickness of the floor finishes. Mark out the axes of the plates, including the horizontal extension of thirty centimetres beyond the end riser.
- Drilling and fixing the wall bracketsDrill the masonry walls or tap the staircase members according to the execution centres. Install approved metal anchors and tighten to the required torque, with plumb shimming using thin stainless steel shims.
- Connecting the rail sectionsPresent the metal sub-assemblies, fit the internal adjustment sleeves and check the alignment with an optical line. Lock the connections with set screws or discreet tack welding, then brush the joint areas.
- Installing the tactile warning on the floorPosition the tactile strips or studs upstream of the first descending step. Fix the elements by mechanical anchoring or two-component resin on a levelled screed that is perfectly dust-free and dry.
- Measuring contrast and tactile verificationVisually assess the colour differentiation between the stair nosing and the steps under service lighting. Check by hand the absence of injurious edges, the continuity of grip and the free clearance of fifty millimetres from the wall.
Acceptance of the work is based on the provisions of the SIA 118 standard. The record notes the static resistance tests prescribed by the SIA 358 standard as well as the consistency of the contrast across all the metal steps. The metalworker notifies in writing any straightness defects in the masonry likely to alter the path of the handrail. An exemplary accessible installation combines a continuous grip along the stringers, ends secured by neat returns and effective tactile marking for all users.
Accessibility non-conformities: arbitration and on-site rework
On a metal staircase, accessibility non-conformities frequently appear in the final phase, when the floor finishes are laid or during the compliance inspection. The three determining elements — the visual contrast of the stair nosings, the horizontal extension of the handrail and the tactile marker at the start and end of the flight — require absolute geometric rigour. When the horizontal extension of the handrail conflicts with the opening of a landing door or creates a protruding obstacle prohibited by the SIA 358 standard, the metalworker must never cut the tube arbitrarily. Such shortening destroys the accessibility of the work and leads to immediate refusal of acceptance by the client.
Visually, deficient contrast between the stair nosing and the metal step cannot be corrected with a simple coat of paint. On chequer plates, gratings or folded treads, applying a non-adhesive coating quickly flakes off under mechanical stress and weather. The technical rework involves dismantling or machining on site to insert high-adhesion powder-coated added profiles or mechanically anchored mineral inserts. For the tactile marker, often neglected at the junction of metal stringers, its omission requires the careful addition of a raised marker (welded sleeve, machined ring or brazed metal ball under the bar) perfectly detectable by hand without presenting any sharp edge.
- Record the alignment defect or the spatial interference jointly with the site management before any modification of the metal.
- Notify in writing the geometric constraints arising from the SIA 358 standard and the remedial solutions compliant with universal use.
- Prefer a modification by sleeving, TIG-welded and ground in the workshop, rather than thermal improvisation on the construction site that damages the galvanising or the powder coating.
- Record the accessibility inspection sheet with measurements of the contrasts and of the horizontal lengths when signing the acceptance record.
Frequently asked questions
What exact length of horizontal handrail extension must be respected?
The horizontal extension must measure at least thirty centimetres beyond the nosing of the first and last step, at both the upper and lower landing. This straight section must remain in line with the going line and at the same height as the staircase handrail. It allows the user to anticipate the change of level before taking the first step and to steady their posture at the end of the flight.
How should the visual contrast of the stair nosings be treated on an external metal staircase?
On an exposed metal staircase, visual contrast is ideally obtained by a contrasting powder coating of a suitable class or by the mechanical insertion of a heat-bonded or riveted non-slip flat over a width of forty to fifty millimetres. The luminance contrast relative to the step must be clearly perceptible in all weathers. Simple signage adhesives are prohibited outdoors because they peel off under the effect of frost, moisture and high-pressure cleaning.
Where should the tactile marker be located on the metal handrail?
The tactile marker is placed on the underside or side of the handrail, exactly in line with the first and last stair nosing. Made as a soft relief, a collar or a specific milling, it warns the visually impaired person by touch of the start of the slope without any risk of injury. It complements the horizontal extension of thirty centimetres by serving as an indelible tactile beacon for understanding the flight.
What should be done if the handrail extension obstructs a free passage?
When the thirty-centimetre extension encroaches on a passageway or the swing path of a door, it must never be removed. The construction rule is to bend the end of the tube towards the supporting wall or towards the stringer, or to make a square return towards the floor. This arrangement removes dangerous sharp angles while respecting the spirit of the SIA 358 standard and the requirements for continuous guidance for users.
Texts and standards cited
- norme SIA 358Guardrails