🧱 CFC 274Metal stairs and handrailsChapter 7 of 10 in the section

Installing the staircase: bearings, slab tolerance, levelling shim and impact noise

Installing a steel staircase on concrete requires anticipating the dimensional deviations of the structural work. This guide details the level survey, the use of compensating levelling shims, the application of a non-shrink grouting mortar and the installation of acoustic elastomer interlayers to comply with standard SIA 358 and eliminate impact noise transmission.

Key takeaways

  • The concrete slab has execution tolerances that the rigid steel staircase can never compensate for on its own.
  • The level survey from the general datum line determines the sizing of the bearing shims.
  • Placing an elastomer under the base plates ensures acoustic decoupling against impact noise.
  • Non-shrink mortar grouting under the base plate provides the final mechanical seating after the adjustments.

Absorbing concrete slab tolerances from the design stage of the base plates

On a building construction site, a raw reinforced concrete slab never corresponds exactly to the theoretical level shown on the execution drawings. The flatness and level tolerances permitted for structural work frequently create offsets of ten to twenty millimetres, both in height and in local out-of-plumb. By contrast, the steel staircase prefabricated in the workshop is a non-deformable assembly with millimetre tolerances. Attempting to clamp a steel stringer directly onto a domed or hollowed slab causes visible deformation of the treads, internal twisting and abnormal pull-out stresses on the mechanical anchors.

The conformity of the work is assessed against standard SIA 358 on the safety of guardrails and staircases. This standard notably prescribes strict regularity of riser heights and going depths over the entire flight. If the ground bearing of the first step has a level difference of fifteen millimetres relative to the planned finished level, the entire walking line becomes non-compliant and dangerous for the user. The metalworker must therefore control the finished height, including the screed, the floor insulation and the final floor covering.

Deviations found on raw slabs and adjustment solutions in metalwork
Finding on the slabTypical measured deviationConsequence for the stringerTechnical solution in workshop and on installation
Floor arrival too low-10 mm to -20 mmFirst step too high, landing out of levelBase plate with integrated jacking screws and metal shimming
Floor arrival too high+10 mm to +15 mmLast step squashed, landing raisedStringer cantilevered with vertical slotted holes
Transverse cross-level error of the bearing surface3 mm to 8 mm across the widthTwisting of the flight and non-horizontal treadsStack of serrated stainless steel wedge shims
Central deflection of the slab5 mm to 12 mm over the spanIncomplete bearing capacity under the intermediate base platesPacking with non-shrink grouting mortar under the shim

Anticipation starts with the measurement survey on site. The team leader must transfer the official datum line marked at one metre by the mason. This mark serves as the single reference for measuring the exact distance to the raw lower and upper slab. In the workshop, the foot and arrival base plates must be drawn with a theoretical installation clearance of fifteen to twenty millimetres. Slotted holes allow three-dimensional adjustment without having to resort to destructive cutting or thermal grinding on the construction site.

Organising the seating shimming, the non-shrink grouting and the acoustic break

The steel staircase is adjusted by means of calibrated levelling shims inserted under the bearing base plates before the anchors are tightened. Offcuts of untreated raw sheet metal or wooden shims, which may rot or rust under the effect of the residual moisture of the concrete, are strictly prohibited. Installers use galvanised steel shims, stainless steel shims or synthetic polyamide shims of high mechanical strength, capable of carrying the dead weight of the structure and the service loads without differential crushing.

  1. Placing on shims and checking the walking linePosition the staircase on temporary shims at the foot and at the upper landing. Check the transverse horizontality of the treads with a precision spirit level and check the conformity of the overall slope against the general datum line of the landing.
  2. Interposition of the resilient acoustic layerSlide a high-density elastomer strip (EPDM or cellular polyurethane with a compressed thickness of five to ten millimetres) under the base plate. Place elastomer washers under the steel washers of the anchor rods to cut any solid acoustic bridge through the fixings.
  3. Controlled tightening of the anchor boltsTighten the fixings to the prescribed torque with a torque wrench to compress the elastomer without crushing it beyond its elastic deformation limit, thus avoiding direct metal-to-concrete contact.
  4. Injection and packing of the non-shrink mortarFill the remaining space under the base plate with a thixotropic non-shrink cementitious grouting mortar. The mortar must fully encase the bearing shims to ensure uniform transmission of the bearing loads to the slab.

Acoustic interposition at the bearings meets the indoor comfort requirements of modern housing. Without effective decoupling, heels striking a steel step make the stairwell resonate and transmit a vibrational shock wave directly into the concrete slab. This vibration spreads as impact noise into the adjoining apartments. To avoid the acoustic short-circuit effect, the threaded fixing rod must pass through the steel base plate via a flexible elastomer sleeve, completely isolating the steel of the rod from the side of the through-hole.

Datum line survey and millimetre shimming of the stringers

On a building construction site, the structural work rarely delivers a perfectly flat raw slab or one rigorously set to the theoretical finished level. Between formwork-removal deflections, the bulging at mid-span and surface-finishing irregularities, the level deviations found commonly reach ten to fifteen millimetres relative to the general datum line transferred at one metre above the finished floor. For the metalworker, installing a staircase stringer without checking the overall setting out inevitably leads to distorting the first or the last riser height, in direct breach of the accessibility and comfort requirements of standard SIA 358.

The first operation on site consists of setting out the axis with a chalk line and checking the height under the arrival slab as well as the level of the lower bearing zone using a rotating laser level. The thickness of the future build-up, comprising the thermal or acoustic insulation, the floating screed and the final floor covering, is marked out in order to position the stringer's seating within its adjustment window. The temporary erection shims, in bevelled steel or high-density polyamide, make it possible to raise or lower the metal element while checking plumb and the regular pitch of the steps.

Behaviour and installation of the shims under the stringer base plate
Type of shimMaterialMain roleKeeping in place
Bevelled levelling shimsBlack or galvanised steelFine level adjustment of the structure under jack or hoistMust be removed before pouring the final grouting mortar
Stackable seating platesReinforced polyamide or polyethyleneStable pre-adjustment of the seating without risk of contact oxidationMay be left embedded if they do not reduce the required bearing surface
Angled anchor washersGalvanised steel 8.8Compensation of the angle under the nut head in case of a tilted base platePermanently tightened under the anchor bolt

Acoustic decoupling and seating grouting

The transmission of footstep noise in reinforced concrete is the most frequent dispute on interior steel staircases. Bare steel clamped directly against a slab acts like a tuning fork, sending the vibrational energy of impacts into the entire structure of the building. To meet the requirements for noise protection in buildings, the staircase must be installed on a resilient interposition device that ensures complete decoupling without compromising the mechanical stability required by standard SIA 358.

  1. Installing the resilient stripPosition under the steel base plate an elastomer pad made of polyurethane or synthetic rubber, about ten millimetres thick, cut to measure to the dimensions of the seating plate.
  2. Isolating the anchor boltsInsert flexible plastic sleeves into the holes of the base plate so that the bolt or grouted threaded rod never touches the side of the steel, then place an elastomer washer under the metal tightening washer.
  3. Controlled torque tighteningTighten the fixings with a torque wrench to the value prescribed by the anchor manufacturer and the elastomer data sheet, in order to compress the material without crushing its damping capacity.
  4. Packing with non-shrink mortarWhere the configuration requires a lost steel shim or rigid shimming with an acoustic pad at the head of the landing, carry out the under-grouting with a fine thixotropic expanding non-shrink mortar, taking care not to create a parasitic rigid connection bypassing the elastomer.

At the head of the staircase, fixing to the slab edge requires the same vigilance: fixing angles with slotted holes to allow natural thermal expansion, a resilient gasket between the concrete slab and the steel bracket, and insulating washers under the nuts. The mechanical assembly decoupled in this way ensures optimal absorption of impact noise while ensuring that the whole remains non-deformable under service load.

Managing major deviations, acoustic bridges and bearing rework

On the construction site, the gap between the actual structural work and the opening drawings frequently exceeds the planned margins. When the level of the concrete slab exceeds the capacity of the slotted holes or of the adjusting bolts, the first or the last riser height ends up modified. Such a variation contravenes the requirements of standard SIA 358 on user safety, which prohibits irregular breaks in the walking pattern. The metalworker must never compensate a level defect of more than fifteen millimetres with an unstable stack of flat shims without the formal agreement of the site management.

As soon as a slab level tolerance not in conformity with the execution drawings is found, the contractor issues a written notice of anomaly to the client in accordance with the Code of Obligations (CO) and standard SIA 118. Work is suspended before final drilling. Two technical solutions are available: require the mason to carry out a fast-setting fibre-reinforced structural levelling after chipping out the seating area, or fabricate in the workshop a bevelled welded counter-plate, hot-dip galvanised, to compensate the actual slope of the concrete without stressing the shanks of the anchors.

Analysis of defects at staircase bearings and corrective measures
Defect foundOrigin on the construction siteImmediate corrective measure
Slab too low (> 15 mm)Hollow or raw level outside toleranceWelded steel packing piece or non-shrink mortar under the base plate
Slab too highConcrete top surface above the datum lineChipping of the opening by the structural work trade or rework of the stringer
Residual acoustic bridgeAnchor rod touching the steel base plateReplacement with an elastomer sleeve and washer
Short-circuit of the resilient layerMortar overflowing onto the bearing sidesClearing with a flat chisel and flexible polyurethane joint

The second recurring defect concerns the acoustic bridge. Acoustic interposition at the bearings loses all effectiveness if the grouting mortar spills against the stringers or if the threaded rod touches the edge of the steel hole. The transmission of footstep noise to the concrete structure then violates the insulation values required by standard SIA 181. To remedy the defect, the anchor must be decoupled by means of flexible sleeves, any rigid mortar in lateral contact must be ground off, and the perimeter must be sealed with a permanently flexible elastomer sealant.

Frequently asked questions

How can the transmission of footstep noise through the steel anchor rods be avoided?

The resilient pad under the base plate is not enough if the metal rod passes through the steel without insulation. Direct contact creates an acoustic bridge to the concrete. The installer must drill a larger hole in the base plate to insert a tubular elastomer bush around the bolt, backed by a steel washer on a flexible washer under the nut, in order to fully decouple the mechanical clamping in accordance with standard SIA 181.

What should be done when the finished screed swallows up the first step of the steel staircase?

If the finished level exceeds the design level, the first riser height decreases and breaches standard SIA 358 on regularity of goings. The metalworker suspends the fixing and issues a written notice in accordance with standard SIA 118. Rework requires either modifying the base plates in the workshop to raise the staircase, or coordinating with the screed layer a local recess in front of the stringer's seating to maintain the regulatory height.

Which mortar should be used for grouting under the base plate after millimetre adjustment on shims?

Temporary shimming on wedge shims or erection jacks leaves a void under the steel base plate. The space must be filled with a high mechanical strength non-shrink grouting mortar. The product is poured or tamped under pressure to avoid air pockets. The original steel shims are left embedded only if they create no rigid contact short-circuiting the prescribed acoustic resilient layer.

What concrete slab level tolerance must a metalworker accept without refusing the substrate?

According to the usual rules of structural work and standard SIA 414/1, the permitted deviations commonly reach ten to fifteen millimetres on a raw landing. The metalworker anticipates this variation by providing, from fabrication, vertical slotted holes and a free space of at least ten millimetres under the base plate for the resilient layer and the shimming. Any larger deviation justifies a formal notification before installation.

Texts and standards cited

  • SIA 358Guardrails and access ramps, user safety and regularity of staircase steps
  • SIA 118General conditions for the execution of construction work, duty to notify and management of defects
  • SIA 181Noise protection in buildings, acoustic requirements for impact noise
  • SIA 414/1Dimensional tolerances in building construction for structural work and finishing work elements