Key takeaways
- Systematic measurement of the diagonals avoids the pitfall of a masonry opening that is out of square.
- The official level line guarantees the exact setting out of the landings and the height of the steps.
- Suitable slinging compensates for the asymmetric centre of gravity of a steel flight throughout the whole manoeuvre.
- Strict application of the OTConst requires a total ban on access beneath a moving suspended load.
Surveying the opening and checking the diagonals before fabrication
In building metalwork, fabricating a straight or winder flight tolerates no geometric approximation. Reinforced concrete walls or masonry frequently show out-of-plumb faces, setbacks or parallelogram shapes. Taking only the length and width of the opening at floor level exposes the metalworker to delivering a steel assembly that cannot be lowered between the slabs. The survey must cover the entire volume of the passage, systematically measuring the horizontal diagonals at the slab corners and the spatial diagonals crossing the shaft.
- Locating the level lineLocate the official level line marked one metre above the finished floor on the concrete walls, set out by the masons or the surveyor. Transfer this reference to the upper and lower floors to deduce the actual thicknesses of the screed and floor finish build-ups.
- Measuring the floor edges and diagonalsUse a laser distance meter to measure the four sides of the opening at the face of the raw concrete. It is essential to measure both opposite horizontal diagonals. If the lengths differ, the opening is not square: the edge stringer risks jamming against the wall during lowering.
- Checking plumb and headroomCheck the verticality of the perimeter walls over the full storey height. Measure the three-dimensional diagonal linking the nosing of the upper opening to the walking line at the lower arrival point in order to guarantee the required headroom.
- Defining the installation clearancesDeduct from the raw dimensions a minimum perimeter assembly clearance, generally between 15 and 20 millimetres per side, needed to absorb the tolerances of the structural work and to manoeuvre the piece without damaging contact.
| Element measured | Common deviation found | Consequence for the staircase | Workshop corrective action |
|---|---|---|---|
| Opening diagonals | Difference greater than 15 mm | Stringer jammed diagonally | Adjust the overall width or use an adaptation false stringer |
| Batter of a concrete wall | Bulge greater than 10 mm | Clearance conflict during lifting | Increase the lateral assembly clearances with adjustable brackets |
| Raw slab level | Unforeseen screed level difference | Incorrect first or last step | Modify the starting base plate or the arrival nosing |
Lifting plan, slinging kinematics and exclusion zone
Introducing a one-piece steel staircase into an interior opening is a critical finishing work assembly operation. The mass distribution of a flight is strongly asymmetric: the centre of gravity is frequently located outside the geometric median axis of the stringers. The operation requires detailed planning of the manoeuvres, selection of equipment compliant with the machinery safety ordinance and exemplary coordination with the crane operator or lifting supervisor.
- Prior determination of the theoretical centre of gravity by the metalwork technical office.
- Fitting short-fibre textile slings with reinforced corner protectors to protect the steel edges and the powder-coated finishes.
- Use of an adjustable spreader beam or chain slings with shortening hooks to adjust the inclination angle of the staircase to the exact slope of the shaft from the moment it is taken on the hook.
- Systematic attachment of two synthetic guide ropes of sufficient length to control the orientation of the load without ever placing hands on the moving structure.
Under the ordinance on construction work, protecting workstations and traffic routes against falling objects or the collapse of suspended loads requires absolute physical sectorisation. Throughout the approach, tilting and lowering phase into the opening, the entire footprint below and the immediate surroundings of the intermediate levels must be neutralised.
- Clearing and marking outProhibit access beneath the opening on the lower level and the floors crossed. Install suspended-load warning signs and lock off access to the landings.
- Hooking on and trial liftPosition the bow shackles marked with the WLL on the welded lifting lugs or on the protected slings. Lift the piece 10 centimetres above the transport wedges to validate its attitude and the integrity of the rigging.
- Tilting and insertionGuide the piece using the restraining ropes to align its slope with that of the shaft. Feed the staircase into the opening while constantly monitoring the safety distances from the concrete walls.
- Setting down on supports and temporary fasteningSet the staircase on its steel bearing wedges at the lower landing and immediately clamp the upper anchorage before any release from the crane or hoist.
Lowering into the opening: rope guidance and temporary anchors
As soon as the stringer clears the upper floor, the margin for error disappears. Introducing a one-piece steel staircase into a closed shaft requires a precisely controlled downward path, often combined with a helical pivoting movement to avoid beam downstands or out-of-plumb concrete. During this critical phase, the metalworker never touches the steel piece directly with their hands: orientation and damping of the swing are carried out exclusively by means of restraining ropes attached to the lower ends of the flight. These braided polyamide textile lines allow the fitters to guide the mass from a distance, remaining outside the potential fall path and outside the void of the opening.
| Stage of passage | Material and human risk | Device and method of execution |
|---|---|---|
| Clearing the upper concrete edge | Sudden slipping of the sling, damage to the slab nosing or the workshop paint | Fit textile protective sleeves on the slings and sacrificial planks on the concrete edge. |
| Angle tilt to pass beneath a landing | Asymmetric shear force on the rigging, twisting of the stringer-rack | Use of a secondary chain hoist to shift the centre of gravity under controlled tension. |
| Approaching the raw masonry walls | Jamming of the work due to out-of-plumb structural work, crushed hands | Hold exclusively by ten-metre guide ropes, check clearances by laser without approaching directly. |
| Arrival at the level of the anchor brackets | Lateral impact on the starter bars, sudden destabilisation of the flight | Slow lowering by centimetres, guided by two operators positioned back on secured floors. |
The flight reaching the floor does not mark the end of the mechanical hazard. Before allowing an operator to approach to present the fixing plates, the staircase must be immobilised on propping stands or heavy metalworker's props fitted with non-slip pads. These temporary supports are sized to carry the full self-weight of the steel structure in the event of instantaneous failure of the lifting appliance. Fine adjustment is then carried out using heel bars and hydraulic compaction jacks, prohibiting any presence of limbs or tools beneath the unstabilised bearing shoes.
Levelling, anchoring to the landings and reinstating collective protection
Fixing of the steel staircase must start with the upper landing to guarantee the exact elevation relative to the reference finished floor level, indicated by the official level line marked on the concrete. The metalworker checks with a tape measure and laser level the height of the first riser relative to the future screed. Adjustment shims in stainless steel or high-strength polyamide are slid under the steel brackets to absorb the flatness irregularities of the masonry. Drilling for the anchor studs or fitting the concrete screws is carried out without imposing any twist on the steel structure, so as not to generate residual stresses that would cause creaking or deformation of the shaft.
- Docking and securing the attitudeRest the staircase on its lower temporary supports and temporarily lock the top of the stringer with high-power metalworker's clamps tightened on the starter corbels.
- Upper drilling and mechanical anchoringDrill the recesses in the concrete wall according to the setting-out plan, vacuum up the drilling dust and insert the mechanical fixings without releasing the tension of the safety sling.
- Alignment check and lower tighteningCheck the step level with a two-metre aluminium straightedge and fix the anchorage at the foot of the flight on the lower landing, inserting the required thickness compensation shims.
- Unloading under controlled loadGradually slacken the lifting rigging while watching the deformation indicators, check there is no settlement at the supports, then unhook the textile slings using a release pole.
As soon as the lifting appliance is disengaged, securing the residual voids becomes the absolute priority of the installation team. The ordinance on construction work requires closing the openings in floors without delay or installing temporary guardrails as soon as the fall height exceeds two metres. If the final guardrails of the metalwork package are not welded or assembled in the same work sequence, compliant temporary construction site barriers, consisting of a fifteen-centimetre toe board, a top rail at one metre and an intermediate mid-rail, must be fitted on the stringer or fixed to the adjacent openings before the safety zone is withdrawn.
Unforeseen assembly problems: jamming in the opening, out-of-plumb and secure withdrawal
When a stringer jams against a slab edge or a rotation stops halfway in the shaft, forcing with the winch is absolutely prohibited. Forcing on a jammed sling induces uncontrollable dynamic overloads, twists the steel stringer and risks shearing the suspension points. The assembly foreman stops the manoeuvre immediately and stabilises the load.
Jamming almost always comes from formwork batter on the concrete wall or from an out-of-square opening not identified in the initial survey. An opening measured only along its orthogonal axes often hides a diagonal shortened by a pouring bulge. If the deviation exceeds the planned assembly clearances (generally 15 to 20 mm on each side), two options apply: local chiselling of the concrete if the site management and the civil engineer authorise it, or removal of the staircase.
- Making safe and proppingRest the flight on solid workshop wedges at the starting landing level or lower it back to the ground if the lifting cable allows it without rubbing.
- Joint inspection recordMeasure the actual overall dimensions by laser in the presence of the site management and give notice of the dimensional deviation in accordance with the SIA 118 standard.
- Rework in the workshopReturn the staircase to the workshop to recut the plates, narrow the protruding step nosings or modify the clearance radius rather than improvise weakening grinding on site.
In accordance with the requirements of the ordinance on construction work, as soon as a lifting operation is aborted, the perimeter protection of the opening must be reinstated before any other intervention. The opening must never remain gaping without temporary guardrails or fixed decking.
Frequently asked questions
What should I do if the measured opening diagonal is 20 mm shorter than the execution drawings?
Stop fabrication of the staircase. A deviation on a diagonal reveals a parallelogram opening or a pouring bulge on the concrete wall. Send a formal notice to the site management in accordance with the SIA 118 standard. The structural work contractor must either correct the concrete by bush-hammering, or you must adapt the width of the flights and stringers in the workshop to keep a minimum perimeter clearance of 15 mm.
How do I secure the opening if the staircase cannot be installed on the planned day?
It is strictly prohibited to leave an opening unattended. Under the ordinance on construction work, you must immediately close the opening with thick formwork panels firmly plugged to the floor to prevent any movement, or reinstall a temporary guardrail comprising a top rail, an intermediate rail and a toe board. The marking out of the lower zone must also be maintained until work resumes.
Can a stringer be ground or notched on site to force it through the slab?
No. Modifying a load-bearing stringer with a grinder on the construction site weakens its resisting cross-section, voids the manufacturing warranty and destroys the anti-corrosion treatment or powder coating. If a fixing bracket or anchor plate rubs, only a minor touch-up without structural impact may be considered, with the written agreement of the technical manager. Otherwise, the piece goes back to the metalwork workshop for clean modification, qualified welding and reapplication of the surface treatment.
Who bears the cost of crane standby in the event of an opening error?
If the metalworker carried out a prior joint survey showing that the work complies with the validated dimensions and that the jamming comes from out-of-plumb concrete exceeding the accepted tolerances, the cost of the additional crane work falls on the structural work contractor or the client in accordance with the SIA 118 standard. Conversely, if the metalworker fabricated without checking the actual diagonals, the additional costs remain entirely at their expense.
Texts and standards cited
- OTConstOccupational safety requirements, fall protection and securing of floor openings during construction work.
- norme SIA 118General conditions for the execution of construction work, notice of defects in the substrate and handling of extras for unforeseen conditions.