Key takeaways
- The nominal outside diameter never corresponds to the usable clear width between the handrails.
- Only the curved walking line determines the regulatory tread that ensures a stable step.
- The minimum headroom under a stringer or landing requires a rotation set precisely to the storey height.
- The impossibility of carrying up bulky furniture must be notified in writing before workshop production is launched.
Diameter, central column and walking line: calculating the real clear width
In a square or circular stairwell opening of 1400 mm, the available space seems sufficient on the architect's plan. On the construction site, the mechanical bulk of the central column, the tread fixings and the thickness of the perimeter balustrade drastically reduce the space available for the human body. For a column of 114 mm outside diameter and a handrail projecting 40 mm inwards, the gross tread width does not exceed 600 mm. The usable clear width, measured between the inner face of the handrail and the column wall, often falls below 550 mm. This size rules out two people passing each other and forces the user to turn the shoulders on every climb.
- Walking line in a spiral staircase
- Theoretical path taken by the user, drawn by convention at 500 mm from the outer handrail, or in the middle of the flight if the usable width is less than 1000 mm. It is only on this arc of a circle that the tread must comply with the usual step formula.
The geometric trap of the spiral staircase lies in the continuous variation of the support surface. Near the column, the tread is reduced to less than 100 mm, creating a dangerous misstep zone where the foot finds no footing. Towards the outside, the tread widens excessively. If the walking line is not calculated rigorously, taking the real pitch of the helix into account, the staircase becomes unstable and prone to falls on the way down. The metalworker must make sure to keep a constant, comfortable tread along this climbing path, regardless of the overall installation radius.
| Outside diameter | Column diameter | Clear usable width | Tread at the walking line |
|---|---|---|---|
| 1200 mm | 88.9 mm | 480 mm | 190 mm to 210 mm |
| 1400 mm | 114.3 mm | 570 mm | 220 mm to 240 mm |
| 1600 mm | 114.3 mm | 670 mm | 230 mm to 260 mm |
| 1800 mm | 139.7 mm | 750 mm | 240 mm to 280 mm |
Formal notice to the client: the furniture obstacle and the balustrades
A compact helical staircase allows people to move but blocks access for rigid bulky items. Double upholstered bed bases, thick mattresses, assembled wardrobes and corner sofas will pass neither the helical curve nor the narrowing between the column and the underside of the stairwell opening. The client, often attracted by the visual elegance of the steel spiral, discovers this reality on the day the furniture is delivered. He then tries to blame the metalworker's design.
Faced with the risk of claims for defective usability, the structural metalworker has a professional obligation to warn the principal by a clear written notice before starting workshop production. The Code of Obligations requires the client to be informed of any fact liable to compromise the proper execution or the agreed use of the work. If the spiral staircase is the only access point to an attic or a habitable mezzanine, another means of hoisting from outside, through a window or balcony, must absolutely be provided for in the building plans.
- Survey of stairwell opening dimensionsCheck with a laser measure the finished storey height, the finished slab thickness and the axes of the arrivals in order to set the rotation without losing headroom.
- Setting out the walking lineCalculate the layout of the treads on the median circle to balance rise and tread while keeping perfect regularity over the whole spiral.
- Issuing the quote with a written reservationExpressly add a clause stating the net usable width and mentioning the incompatibility of the staircase with the passage of large furniture.
- Formal approval of the opening planHave the workshop drawings countersigned by the client, stressing the position of the first and last tread in relation to the walls.
Head clearance and stairwell opening: the trap of the helical setback
In a helical stairwell, the calculation of the clear height allows no geometric approximation. Unlike a straight flight where the headroom remains constant over the whole length of the stairwell opening, the spiral staircase stacks its treads by axial rotation. As soon as the rotation reaches a full turn, the upper tread is directly above the corresponding lower tread. The vertical distance between these two surfaces corresponds exactly to the height difference covered in three hundred and sixty degrees, less the thickness of the metal tread itself and of the underside stiffeners.
The head clearance problem almost always arises where the stairwell passes the underside of the floor slab. A circular opening cut to the exact outside diameter of the work condemns the user to hit the concrete edge as soon as he goes down the first treads, if the starting angle has not been set with millimetre precision. To guarantee a clear passage of two metres to two metres ten along the walking line, the upper slab edge must be cut back well before the vertical line of the tread concerned. This enlarged cut-out often requires an additional metal trimmer or a specific arrival balustrade, designed according to the strength and containment criteria prescribed by standard SIA 358.
| Opening shape | Diameter or side | Headroom on walking line | Behaviour when passing through |
|---|---|---|---|
| Fitted circular (Ø + 5 cm) | 140 cm | 185 to 195 cm (insufficient) | Systematic head strikes for users of average height on the way down. |
| Open circular with flared edge | 160 cm | 205 to 215 cm (compliant) | Smooth passage, requires a longer curved upper balustrade run. |
| Standard square | 140 x 140 cm | 195 to 200 cm (critical) | The dead corners create lost volumes but allow better headroom at the start of the flight. |
| Comfortable square | 160 x 160 cm | 215 to 225 cm (optimal) | Impeccable head comfort, easy installation of the fixing plates at the edge of the opening. |
Kinematics of rigid volumes and alternatives for furniture
The attractive compactness of a spiral staircase of one metre forty in diameter hides an implacable mechanical reality: the usable passage available for an undeformable object is almost nil. Between the tubular central column of one hundred and fourteen millimetres and the inner handrail fixed to the balusters according to the dimensions of standard SIA 358, the real circulation corridor does not exceed fifty-five to sixty centimetres. To this narrowing is added the permanent helical winding. The swept volume is not a straight prism but a closed left-handed helix.
A rigid bed base of one hundred and forty by two hundred centimetres, a one-piece wardrobe or a simple corner sofa have three-dimensional diagonals incompatible with this turning radius. As soon as the object tilts to follow the theoretical slope determined by the tread measured at the walking line, its ends jam simultaneously against the central column and against the top rail of the perimeter balustrade. Trying to force the passage inevitably results in damage to the powder coatings, distortion of the metal posts or tearing of the furniture.
- Variable tread
- Tread width measured horizontally between two successive nosings, increasing proportionally from the centre towards the periphery. On a helical staircase, its regulatory calculation value is valid only on the walking line, generally located between forty and fifty centimetres from the outer handrail.
- Check for a direct opening in the façade (removable tilt-and-turn window or French window) at the upper level for external hoisting.
- Check the sill height and external accessibility from the road for a cherry picker truck or a removal lift.
- Allow for the added handrail projecting inwards, which reduces the usable passage by a further forty to sixty millimetres.
- Check the free turning radius at the arrival at the top, where a perpendicular partition immediately blocks any long piece.
Delivery disputes and usage blockages: method of recording the facts and fallback solutions
When bulky furniture remains stuck on the ground floor or the client complains of impracticable circulation, the metalworker's liability is decided by the execution file. The first reflex on the construction site is to record the actual dimensions against the approved workshop drawings. Provided the work scrupulously respects the existing stairwell opening and the signed plans, the metal constructor is covered against usage complaints, on condition that he has stated in writing his prior reservations on the physical limits of a helical staircase.
- Joint survey of walking line and headroom dimensionsMeasure to the millimetre the tread at the walking line, conventionally located at the centre of the usable passage or at fifty centimetres from the outer handrail. Note the headroom under the lower edge of the stairwell slab or under the underside of the upper treads. Any difference between the fabrication drawing and the reality of the construction site must be recorded in minutes drawn up according to the principles of standard SIA 118.
- Compliance check according to standard SIA 358Check the regulatory height of the helical railing on the sloping part and on the arrival landing. Check that the gap between the vertical bars or under the bottom rail prevents the passage of a twelve-centimetre sphere. If the client disputes the ergonomics, strict compliance with standard SIA 358 rules out complaints concerning the safety of users.
- Metalwork adaptation for a local wideningIf the blockage is only a few centimetres, modify the handrail fixing in the workshop to make it removable. The metalworker can replace a welded rail with a system of threaded sleeves, tapered pins or countersunk-screw plates, thus freeing between forty and sixty millimetres of lateral clear passage during moves in.
- Validation of substitute access for heavy loadsFaced with a sofa or rigid bedding that cannot be carried up, record in writing the geometric impossibility inherent in the helical turning radius. The technical solution then lies outside the staircase: recommend to the client the temporary removal of a glazing unit in the façade or the use of an external hoist via the terrace.
Frequently asked questions
Can a spiral staircase with a total diameter below one hundred and forty centimetres be installed?
Technically, the workshop can make a diameter of one hundred and twenty centimetres. However, once the ten-centimetre central column and the bulk of the balustrades are deducted, the usable clear width falls below fifty-five centimetres. The tread at the walking line becomes too narrow to place the foot flat. This staircase can only serve as a supplementary secondary access to a non-habitable technical mezzanine.
Where is the theoretical walking line located on a winder tread?
The walking line represents the user's natural path. On a helical tread, it is drawn at about fifty centimetres from the outer handrail for a large staircase, or at the exact centre of the usable width when the usable passage is reduced to less than eighty centimetres. It is on this line that the metalworker must calculate the tread in order to apply the classic step formula.
What is the minimum headroom required on a helical staircase?
The rules of good practice and the safety recommendations require a clear vertical clearance of at least two metres, measured vertically from the tread nosing to the underside of the slab or of the upper tread. If the stairwell opening is too narrow in relation to the pitch of the helix, the headroom quickly decreases and forces the user to bow the head, which is a major non-conformity of the building.
Can the client reject the staircase if his furniture will not go up to the upper floor?
If the staircase complies with the validated execution plans and the prescribed dimensions, the impossibility of carrying up a piece of furniture is not a defect of the work. The metalworker is fully protected if he recorded in writing, before fabrication, a note warning that the geometry of the spiral staircase rules out the carrying of large rigid loads and requires external access for heavy furniture.
Texts and standards cited
- SIA 358Balustrades: geometric characteristics and safety requirements against falls
- SIA 118General conditions for the execution of construction work: notice of defects and acceptance