Key takeaways
- The hot work permit formalises the clearance and the extinguishing means before any arc is struck.
- Glowing grinding particles fly up to ten metres and burn through ordinary plastic protection.
- Certified spark screens must tightly seal all gaps leading to the thermal insulation layers.
- Deferred monitoring remains the critical clause for detecting smouldering fires several hours after work has stopped.
Preparing the hot zone: hot work permit, clearance and protective screens
On Swiss construction sites, fitting or tack-welding balustrades, handrails and light grilles on site exposes the structure to major fire risks. The Ordinance on Construction Work requires strict safety planning before hazardous tasks are carried out. Before connecting a welding set or using an angle grinder to adapt a fixing bracket on a stair stringer, the metalworker must obtain a hot work permit validated by site management or the site safety officer.
- Inspection and signing of the hot work permitThe team leader inspects the work location with the site manager, lists the adjacent flammable materials and sets the strict schedule for the hot operations.
- Mechanical clearing of the perimeterAll movable combustible items within a minimum radius of five metres around the hot spot are removed, in particular cardboard, pallets, solvents and packaging.
- Setting up first-response meansTwo suitable, serviceable fire extinguishers and a bucket of water or a fire blanket are placed within immediate reach of the operator.
- Sealing and installing spark screensFloor gaps, expansion joints, open sleeves and insulated façades are covered with non-combustible thermal fabrics made of glass fibre or silicate.
Confinement tolerates no compromise: protective fabrics must be firmly secured with metal clamps so that the blast from the grinder or draughts in the stairwell do not expose the adjacent surfaces. The OTConst requires workstations to be protected against projections. When grinding a chamfer or dressing a weld on a balustrade fixed against a ventilated façade or a render on insulation, the operator sets up a rigid spark screen or a fireproof sheet weighted at the base to catch the direct flow.
Neutralising the risk of smouldering fire: the post-work monitoring protocol
Stopping the electric arc or disconnecting the grinder never ends the installer's hot operation. In metal finishing work, the fire almost always breaks out after the workers have left. A stray spark that has gone through a gap in a technical floor or lodged against an expanded polystyrene insulation board can smoulder slowly for two to four hours with no flame and no immediate smoke, before igniting under the effect of an air draught.
| Time after stopping | Check action | Equipment or method |
|---|---|---|
| Immediate (0 min) | Direct visual check and preventive wetting of inert surroundings | Touch inspection, water mist sprayer |
| After 30 minutes | First general round and check of the seals | Checking for suspicious smells, inspecting rear faces |
| After 1 hour | Temperature measurement of walls and penetration joints | Thermal camera or contactless infrared thermometer |
| After 2 hours | Thorough check of lower levels and service shafts | Checking the areas where sparks may have fallen |
| End of the fire watch | Final joint inspection and written closure of the permit | Joint signature with site management |
Deferred monitoring is the central legal and technical clause of the hot work permit. It requires the continuous presence of a dedicated watch person during the activity, followed by regular checks at the workstation and in adjacent or underlying rooms. Swiss fire protection requirements and Suva guidelines remind us that organising emergency response and checking rooms after hot work is the joint responsibility of the parties involved. As long as the period set by the permit has not elapsed and the thermal camera has not confirmed that all exposed surfaces have returned to ambient temperature, the metalworker does not leave the construction site.
Spark trajectory and sealing of insulation cavities
When installing or fitting light metalwork such as balcony balustrades or stair stringers, using an angle grinder or a welding set produces a stream of glowing particles whose range far exceeds the immediate work zone. Grinding sparks, thrown at over a thousand degrees, do not go out instantly in the air. Carried by the peripheral speed of the disc, they bounce off raw slabs, cross the gaps under thresholds and can travel up to about ten metres from the point of impact, finding refuge in the gaps of linings or ventilated façades.
The main risk for the metalworker is not the ignition of a solid object, but the intrusion of these metal beads into combustible thermal insulation or mineral wool mats soiled with site residue. The presence of polyurethane, expanded polystyrene at the slab edge or open vapour barrier membranes creates heat traps where an ember smoulders without any visible flame for several hours. Before the first cut with the disc or the striking of an arc, mechanical clearance and the installation of tight physical screens are an operational obligation under the Ordinance on Construction Work.
| Configuration of the work | Critical penetration point | Required confinement measure |
|---|---|---|
| Balustrade on balcony with compact façade | Insulation connection joint, drip edge, gap under rail | Glass-fibre fabric sheet classified as non-combustible, weighted on the ground with no gaps |
| Handrail in concrete stair opening | Service shafts passing through, core-drilling openings | Temporary sealing with a fire-stop cushion or a protective metal plate |
| Stair plates on technical floor | Gaps between removable slabs, cable passages | Rigid curved spark screen surrounding the grinding zone through 360 degrees |
| External ventilation grille in a basement light well | Light well with accumulated leaves and dust | Complete prior cleaning and full cover with a solid steel sheet |
The spark screen must have no gap at its base. Fabrics made of silica fibre or aluminised glass must be pressed to the ground using steel profiles or non-combustible weights. The use of simple plywood panels or plastic painter's sheeting is strictly prohibited, as these materials ignite or melt on prolonged contact with molten steel shot.
Deferred thermal monitoring and closing the hot work permit
Stopping the welding arc or the cutting saw marks the start of the most critical phase of the metalwork construction site. Slow combustion in organic insulation or a bituminous complex gives off almost no visible smoke at first. The temperature rise stays confined inside the wall or under a floating screed, reaching general ignition well after the workers have left. The post-work monitoring required by the hot work permit and the OTConst requires an organised and documented human presence.
- Extinction and first immediate visual inspectionAs soon as the hot operation ends, light preventive wetting if the substrate allows it, removal of the spark screens and checking for smells or incipient smoke at skirting boards and joints.
- Thermographic scan at thirty minutesCheck, using a thermal camera or an infrared pyrometer, all contact points, balustrade anchor slots and insulated walls located within the spark cone.
- Staggered intermediate roundsSystematic check every hour that there is no hot spot. The safety watch also monitors the floor below and adjoining rooms if the anchor has passed through a slab or a partition wall.
- Final check and joint closure of the permitFinal inspection with the site safety officer or site management, joint signature of the closing document recording the official end of the monitoring.
The required watch duration is determined by the nature of the surrounding materials and the AEAI requirements. It typically extends over two to four hours after the hot spots have actually stopped. This time must be built into the planning of the work from the outset: any welding or heavy cutting operation in metalwork must be stopped early enough in the afternoon to allow the protocol to be carried out in full before the construction site accesses are finally closed.
Action to take in case of a smouldering fire and emergency lifting of the watch
During metalwork involving balustrade grinding or tack-welding adjustments, grinding sparks expel glowing metal particles over eight metres. Despite the installation of a fireproof spark screen, a particle can pass through an unsealed gap and get into a lining, a combustible insulation or a service shaft. This smouldering fire phenomenon develops without a visible flame for several hours, under a slow oxidation regime, before suddenly breaking out into general ignition once the construction site is deserted.
- Immediate stop and alertAs soon as an abnormal smell of pyrolysis, a thin bluish smoke or a hot spot detected with the infrared thermometer appears, stop the welding set immediately. Disconnect the energy supplies and raise the alarm on the construction site at once by sounding the audible alarm. Call the fire brigade emergency number without delay.
- Targeted primary attackIf the fire remains accessible on the surface without endangering the operator, use the water-mist extinguisher with additive or the ABC powder extinguisher prescribed by the hot work permit. Do not spray pressurised water into a closed duct with no visibility, as this risks spreading the embers into neighbouring cavities of the building.
- Making safe and evacuation guideEvacuate the work zone, closing the fire doors to limit the flow of combustion air. In accordance with the OTConst, the organisation of first aid and evacuation must be operational at every workstation. Send a colleague wearing a high-visibility vest to the site entrance to guide the emergency vehicles.
After the emergency services have intervened, no return to work is allowed without a formal inspection. Site management, the safety officer and the metalworker draw up a joint inspection record. The hot work permit is suspended automatically. The employer must review the risk analysis and record the event before considering any new authorisation for hot work on the building.
Frequently asked questions
How long must deferred monitoring compulsorily last after welding?
Monitoring after extinction is not limited to a simple glance while packing up. According to the AEAI fire protection guidelines and the terms of the hot work permit, an active watch on site must be maintained for at least two to four hours after the last arc or grinder cut. This physical presence makes it possible to detect the gradual temperature rise of a hidden insulation or dust.
What should you do if site management refuses to sign the hot work permit on the construction site?
The metalwork fitter must never start any spark-generating operation without this initialled document. If site management refuses to sign, welding, cutting and grinding operations are suspended on the spot. Report in writing to your foreman that the task cannot be carried out. The OTConst requires strict planning of safety measures: working without a permit makes the executing company directly liable.
Why is an ordinary site sheet prohibited as a spark screen?
Standard polyethylene or PVC sheets melt instantly on contact with slag thrown at high temperature. When burning, they themselves spread the fire through burning droplets onto the coverings below. Only treated glass-fibre or silicate fabrics, classified as non-combustible according to the AEAI requirements and fitted with weighted hems to seal floor gaps, ensure effective retention of machining particles on site.
How do you effectively check a technical void suspected of having received sparks?
Simple visual examination is insufficient to probe a hollow partition or compacted insulation. You must use a thermal camera or an optical pyrometer to scan the surfaces adjacent to the weld bead. Any abnormal temperature difference requires local removal of the lining to check that there is no internal ignition. In case of a persistent temperature rise without flame, moisten the area moderately and maintain a reinforced watch post.
Texts and standards cited
- OTConstWork planning, organisation of occupational safety and emergency measures to prevent harm to the health of workers on construction sites.
- Directives de protection incendie AEAISwiss requirements governing operational and preventive measures against fire risks during hot work.
