Outdoor stairs: standing water, frost, corrosion of connections and drainage holes

This chapter details the design and fabrication rules for external metalwork to prevent standing water in stringers, treads and balustrades. You will be able to locate and size drainage holes from workshop fabrication onwards, coordinate the openings with the galvanizing dip, and durably protect bolting against galvanic corrosion and residual moisture.

Key takeaways

  • Water trapped in a stair tube expands on freezing and irreversibly tears the metal walls.
  • Vent and drainage holes must be drilled before immersion in hot zinc.
  • A badly positioned drainage hole leaves a damp dead end prone to internal blistering and oxidation.
  • Using only suitable stainless steel fasteners prevents contact corrosion on external connection plates.

Residual water in tubular sections: risk of frost and rupture through expansion

On an external metal stair exposed to the weather of the Prealps or the Swiss Plateau, moisture infiltration into metal structures is constant. Whether it comes from driving rain, run-off along the stringers or the daily phenomenon of internal condensation linked to regional temperature swings, water always finds a way in through connection clearances or the residual porosity of fillet welds. When the metalworker uses closed hollow sections with no outlet — such as rectangular tubular steel sections for stringers or square tubes for balustrade posts — this liquid inevitably accumulates by gravity in the lower parts of the metal members.

Frost shattering of a hollow section
Plastic deformation followed by mechanical bursting of the walls of a metal tube, caused by the volumetric expansion pressure of trapped water changing from the liquid to the solid state below zero degrees Celsius.

On turning solid, the volume of water increases by about nine per cent. In a hermetically sealed tube or one without a low outlet, this linear and volumetric expansion develops considerable hydraulic pressures, frequently exceeding one thousand bar. Steel walls two to four millimetres thick cannot absorb such a mechanical stress: the section first shows visible bulging of its flat faces, altering the overall geometry of the stair. When the breaking limit is exceeded, the metal tears violently along the factory weld bead or at mitre joints. The element loses its load-bearing capacity, causing a sudden structural collapse of the flight.

Outside frost periods, prolonged standing water at the bottom of the stringers triggers destructive internal corrosion by differential aeration. The oxygen contained in the water film is rapidly depleted at the bottom of the tube, turning this confined volume into an active electrochemical cell. The metal degrades from the inside outwards, with no trace of rust detectable on external visual inspection, until the bearing flange is completely perforated.

Layout of drainage holes, hot-dip galvanizing and durability of connections

To guarantee the durability of an external stair, water management necessarily begins at the workshop marking-out table, well before dispatch for surface treatment. Hollow sections intended for hot-dip galvanizing must have openings calculated to allow the immediate entry and exit of the chemical pickling fluids and of the molten liquid zinc. These technical openings, essential to avoid any fatal overpressure during dipping in a bath at over four hundred and fifty degrees Celsius, simultaneously form the final gravity drainage system of the metal stair.

  1. Positioning according to the final geometryIdentify the exact inclination of the stair flight in the workshop in order to position the drain holes absolutely flush with the lower plates and mitre cuts, thus avoiding any dead zone of retention.
  2. Sizing of the drilled holesDrill slots or circular holes of appropriate diameter in each closed compartment, located at diagonally opposite ends to ensure air flow and continuous escape of condensate.
  3. Deburring and checking after the bathGrind drilling burrs carefully before treatment to promote the flow of zinc, then systematically rod out each hole after galvanizing to remove drips and menisci likely to block the outlet.

Standing water also threatens the bolted connections located on stringers, brackets and tread nosings. Steel-to-steel contacts create narrow capillary zones that trap ambient moisture and de-icing salts. Combining galvanized parts with ordinary unprotected bolting creates a bimetallic couple that accelerates corrosion of the threads. To preserve the integrity of the connection, the metalworker fits perforated shims leaving a ventilation gap between plates, uses stainless steel fasteners of a suitable grade and prohibits any horizontal assembly without a drainage slope.

During installation, coordination with masons and waterproofers prevents the low drainage holes from being drowned in a landing screed or sealed under an unsuitable silicone joint. The lower opening must discharge in free overhang above the finished floor so that the expelled water drips unimpeded towards the building's drainage points.

Design of vent holes: ensuring zinc drainage, then run-off of condensate

In an external mild steel stair, the choice of closed hollow sections for stringers or balustrade posts often responds to a search for torsional stiffness and a sober appearance. However, turning a rectangular or square tube into a sealed hollow body is a major technical error. During the hot-dip galvanizing bath by immersion, trapped air prevents the pickling liquid and then the molten zinc from penetrating, with a risk of the part bursting in the bath under the effect of overpressure. Once the part is installed outdoors, the absence of a through opening turns the stringer into a reservoir sealed against condensate and rainwater infiltration.

Rainwater inevitably enters hollow sections through the fixing clearances of the balusters, by capillarity around threaded rods or through micro-cracking of fillet welds. If the stringer has no gravity outlet, this water stagnates in the lower part. At the first winter frosts, the transformation of the residual water into ice is accompanied by a volumetric expansion of about 9%. The internal hydrostatic pressure quickly exceeds the elastic limit of the steel: the tube walls first deform into a barrel shape before tearing along the longitudinal weld of the section. Bursting of the section irreparably destroys the stiffness of the stair and ruins the corrosion protection.

  1. Locating the low points according to the slope of the structureDetermine the exact location of the drain openings taking into account the real inclination of the stair once fixed on the brackets or concrete bases. The low point of the inclined stringer never corresponds to the bottom of the straight tube cut square.
  2. Workshop machining before galvanizingDrill oblong slots or circular holes of at least 10 to 12 mm diameter flush with the welded end plates, leaving no inner lip that would create a retention basin.
  3. Checking for zinc blockage after dippingOn return from the galvanizing plant, systematically check that no drop of solidified zinc or dross blocks the purge hole before dispatch for installation.

External bolted connections: neutralizing capillary retention and the galvanic couple

The mechanical junction points between stringers, grating treads and wall brackets are the zones most vulnerable to climatic attack. Run-off water laden with de-icing salts infiltrates by capillarity into the narrow gaps formed by overlapping plates. Without ventilation and a drainage slope, a confined, acidic environment sets in between the contact surfaces. This crevice corrosion phenomenon eats away the protective zinc layer, attacks the base metal and makes the oxides swell, causing warping of the plates and insidious shearing of the threaded rods.

Behaviour of external metal stair connections according to their design
Connection configurationRisk of water accumulationCorrosion resistanceRequired constructional measure
Galvanized steel plates in full direct contact with concrete slabCritical, through rising damp and continuous capillary standing water under the baseRapid degradation of the zinc and blistering of stringer feet in under 5 yearsInstallation on perforated raising shims or anchoring on concrete pads with a run-off slope
Treads screwed against continuously welded internal anglesMedium, localized retention on the horizontal returns of the angleProgressive oxidation of the seating zones through lack of ventilationProvide a gap of at least 5 mm or weld discontinuous seating angles
Electro-galvanized steel bolting on hot-dip galvanized sectionsLow direct geometric influence, but rapid loss of integrityAccelerated bimetallic corrosion of fasteners with undersized coatingMandatory specification of hot-dip galvanized or A4 stainless steel bolts
Balustrade fixed by closed hollow shoes without low drainageVery high, a complete water trap with every rainfallFrost bursting of the shoe or perforating corrosion of the post baseRemove the shoe bottom or provide a bevelled drain opening directed outwards

The management of transverse fixings also demands great rigour in the choice of materials. Direct combination of galvanized steel sections with standard-grade stainless steel fasteners can, in the presence of conductive standing water, cause a galvanic reaction unfavourable to the surrounding zinc. To avoid corrosion under the screw head and preserve the prescribed tightening torque, the metalworker must insert rot-proof synthetic elastomer washers and ensure that air circulates freely around each connection node.

Managing defects: section split by frost, retention and on-site repair

When a tubular stringer or a balustrade post splits under the thrust of ice in winter, the mechanical strength of the stair is directly compromised. Longitudinal rupture along the weld line of the closed section indicates an accumulation of rainwater or condensate, caused by the absence of low drainage openings or the blocking of vents by zinc residues. Faced with this finding, the foreman secures access to the structure, closes off the stair, installs temporary propping if a load-bearing stringer is affected and sends a documented report to the site management in accordance with the rules of standard SIA 118.

  1. Purging and probingMethodically drill an 8-millimetre drain hole at the low point of each suspect closed section that sounds dull when tapped with a hammer. Collect the trapped water to quantify the retention and inspect the interior with a fibrescope to look for corrosion.
  2. Assessing the damageIf the metal wall shows visible bulging or a continuous tear, cut it out cleanly. A section split by frost cannot be rewelded or clamped on site: its mechanical properties and geometric stability are destroyed.
  3. Replacement and protectionMachine a replacement part in the workshop, provided from the cutting stage with vent slots and drainage passages. The assembly is hot-dip galvanized before being connected by a bolted internal sleeve or splice plates with insulating washers.

For bolted connections showing rust runs due to standing water by capillarity between plates, remove the degraded fasteners entirely. The metalworker replaces the fixings with hot-dip galvanized or A4 stainless steel bolts, inserting neoprene washers or draining spacer shims. This arrangement eliminates plane-on-plane contact, guarantees free circulation of run-off water and prevents the formation of a destructive galvanic cell.

Frequently asked questions

Can a galvanizing hole blocked with zinc be cleared directly on the construction site?

Yes, but the operation requires rigorous precautions. Use a twist drill mounted on a slow drill without hammer action, avoiding damage to the inner walls of the tubular section. As soon as drilling is finished, remove the steel and zinc chips with an air blow gun. Then apply a zinc-rich touch-up paint with a brush to the exposed edge, in order to restore the continuity of the anticorrosion film and prevent any rust starting under outdoor moisture.

Why can a closed section not be made completely watertight by welding without a purge hole?

On immersion in the zinc bath at 450 degrees Celsius, the air trapped in a hollow body without a vent suddenly rises in pressure and causes the tube to burst at the galvanizing plant. Moreover, on the construction site, the absolute tightness of a weld bead remains illusory over time: temperature variations create suction through negative pressure. Water infiltrates by capillarity and can no longer escape, leading to rupture at the first winter frosts.

What minimum diameter should be provided for the drainage holes of an external stair?

The metalworker applies a minimum diameter of 8 millimetres, even 10 millimetres on large stringer sections. A hole smaller than 6 millimetres risks becoming blocked instantly when the liquid zinc drains off or through later deposits of pollen and plant debris. The holes must be located precisely at the lowest geometric points, in the lower part of inclined tubes, to avoid any residual retention above the level of the hole.

How can corrosion between the tread plates and the tubular stringer be prevented?

Steel-to-steel contact generates a confined zone where rainwater penetrates by capillarity without drying. Perforated synthetic shims or flat elastomer washers 2 to 3 millimetres thick should be interposed where the bolts pass. This separation leaves a free ventilation slot, breaks the capillary water film and allows the galvanized faces to dry quickly without impairing the tightening torque of the connection.

Texts and standards cited