On-site welding, corrosion protection and safety: the execution reference framework
This section is intended for metalwork fitters, team leaders and site managers dealing with welding, grinding and corrosion-treatment operations on the construction site. It covers the practical measures for carrying out arc work without starting a fire, controlling toxic fumes, ensuring the strength of light metalwork weld beads and durably protecting galvanised or powder-coated steel during fit-up adjustments, in strict compliance with Swiss safety directives.
- 10chapters
- 22 000words
- 6sections in the training course
- 60chapters in total
Key values to remember 4
19 to 21 %
Minimum and maximum oxygen content in the ambient air at workstations
100 cm
Minimum height of the top edge of the top rail of a temporary guardrail
2 m
Free-fall height from which edge protection is mandatory
15 cm
Minimum height of the toe board at floor level on scaffolding or floor openings
Scope of light metalwork and limits of intervention
The work of the building metalworker on the construction site requires rigorous control of hot-work operations. On-site assembly of secondary elements such as guardrails, handrails, light metal staircases, ventilation grilles or small gates requires making sound welds without damaging the built environment or compromising people's safety. The metalworker often works in partially occupied rooms or close to flammable insulation, which demands strict discipline from the moment the welding set is switched on until the equipment is packed away.
This section sets out the operational requirements for work falling exclusively under finishing-work metalwork (CFC 274). It covers management of the hot-work permit, flame-proof screens, extraction of toxic fumes when working stainless steel or zinc-coated steel, visual assessment of weld beads, and the methodical restoration of corrosion protection after drilling or trimming cuts. It also addresses the safe handling of angle grinders and the manipulation of bulky bars or frames.
The employer is required to guarantee compliant workplaces, in particular within the meaning of OPA, by implementing the technical and organisational measures dictated by the state of the art and occupational medicine. Work on the construction site tolerates no compromise on assembly sequence, ventilation or personal protection suited to radiation and spatter.
Operational structure and sequence of the section's chapters
The ten chapters of this section are arranged to follow the chronology of an intervention on the construction site, from the administrative authorisation to start hot work through to acceptance of the work by the client and the authority issuing the occupancy permit. They make it possible to anticipate the major technical pitfalls of finishing-work metalwork.
- Thermal control and management of immediate risks (Q6-01 to Q6-03): formalising the hot-work permit, neutralising combustible materials, setting up active fire watch, capturing metal oxides at source and personal protection against the ultraviolet radiation of the electric arc.
- Mechanical integrity and chemical durability of connections (Q6-04 to Q6-06): diagnosis of undercut, porosity and lack of penetration according to recognised rules, design of gas vents for hot-dip galvanising and immediate reconditioning of bare edges after sawing or core drilling.
- Safe execution, logistics and recovery (Q6-07 to Q6-09): safe fitting of abrasive discs, trajectory of the spark stream, carrying heavy sections while avoiding cuts from sharp edges, and management of workshop offcuts with strict separation of scrap iron, stainless steel and aluminium offcuts in accordance with the waste ordinance.
- Final regulatory compliance (Q6-10): handling geometric or mechanical non-conformities found during compliance inspections for the occupancy permit, deciding on rework and contractual responsibilities.
Air management at the welding station is a critical health issue, governed by art. 33 OTConst. Fumes laden with zinc, ozone or hexavalent chromium must be captured at source or removed by forced mechanical ventilation in order to guarantee at all times a healthy working atmosphere that complies with federal requirements.
📘 Chapters in this section 10
Welding on site: hot work permit, screen, clearance and monitoring after stopping work
Secure every hot spot with the hot-work permit and organise the mandatory thermal patrol.
On-site welding, corrosion protection and safetyFumes: extraction at source, stainless steel welding, and rooms without ventilation
Eliminate toxic stainless steel and zinc fumes by adapting the mobile extraction to your workspace.
On-site welding, corrosion protection and safetyThe arc burns: arc eye, protecting the eyes, the skin and the people nearby
Prevent retinal and skin burns with optical shielding suited to neighbouring workstations.
On-site welding, corrosion protection and safetyAssessing a weld: undercut, lack of penetration, porosity and rework
Identify internal or surface defects immediately to guarantee the strength of the weld beads.
On-site welding, corrosion protection and safetyGalvanising: inlet and outlet holes, distortion in the bath and touch-up after welding
Position the dipping vents correctly to prevent bursting and distortion in the zinc bath.
On-site welding, corrosion protection and safetyEvery cut opens the door to corrosion: touch-up after drilling, bare edge and compatible product
Restore the corrosion barrier as soon as the cut is made to avoid premature degradation of the sections.
On-site welding, corrosion protection and safetyThe angle grinder: disc failure, guard, direction of projection and clothing catching fire
Check the guard orientation and the peripheral speed to rule out the risk of the disc bursting.
On-site welding, corrosion protection and safetyCarrying steel: weight, sharp edges, gloves and slinging a long piece
Master the slinging of long bars and neutralise sharp edges to protect your teams.
On-site welding, corrosion protection and safetyOffcuts: sorting by metal, buy-back value and pickling bath
Organise the construction-site skip to separate alloys and properly recover each cut metal.
On-site welding, corrosion protection and safetyRejected balustrade: findings, remedial solution and cost allocation
Correct a guardrail rejected at inspection without delay to secure the occupancy permit.