🧱 CFC 274On-site welding, corrosion protection and safetyChapter 2 of 10 in the section

Fumes: extraction at source, stainless steel welding, and rooms without ventilation

This chapter gives you the method for neutralising toxic fumes when welding stainless steel components on a construction site. You will learn how to size extraction at source, why simply stirring the air is prohibited, and how to make your fitting or balustrade-fixing work safe in windowless or confined rooms in line with Swiss requirements.

Key takeaways

  • Stainless steel fumes contain hexavalent chromium and nickel, highly carcinogenic substances.
  • A simple fan spreads the toxic particles throughout the room without ever removing them.
  • Extraction at source captures pollutants directly at the nozzle before they spread into the breathing zone.
  • In a windowless room, forced ventilation must always be added to capture at source of the fumes.

Hazardous compounds in stainless steel and the legal obligation to capture as close as possible

When installing balustrades, handrails or gates in stainless steel, occasional TIG or flux-cored wire welding operations generate a thermal plume loaded with persistent pollutants. Arc temperatures vaporise the metals, which then condense into respirable aerosols of micrometre size. Unlike structural steel or ordinary metalwork steel, stainless steel releases chromium and nickel derivatives whose inhalation represents a major risk of serious lung damage and tumour development.

Hexavalent chromium (Cr VI)
Highly oxidised metallic compound formed during arc welding of stainless and chromium-alloyed steels, recognised as a carcinogenic and mutagenic substance for the respiratory tract.

Hexavalent chromium crosses the bronchial barrier and penetrates deep into lung tissue. Combined with dusts of nickel oxides and manganese and residual gases such as ozone or nitrogen oxides, it exposes the metalworker in the short term to metal fume fever or bronchial oedema, and in the medium term to bronchopulmonary cancers. The Ordinance on the Prevention of Accidents (OPA) requires the employer to take all prevention measures called for by experience and the state of the art, which makes any stainless steel welding work inseparable from an effective filtration or extraction system.

Main toxic compounds emitted when welding stainless alloys in metalwork
Substance emittedMain origin of formationIdentified clinical effectsPriority technical measure
Hexavalent chromiumOxidation of chromium under the arc energyProven carcinogen, nasal ulcerationExtraction torch or nozzle within 15 cm
Nickel oxidesVaporisation of austenitic stainless gradesSuspected carcinogen, skin sensitisationClass H very-high-efficiency filter
Manganese oxidesFiller metal and stainless steel matrixDamage to the central nervous systemRemoval of effluents from the work volume
Ozone and nitrogen oxidesUltraviolet radiation ionising the ambient airAcute irritation of the respiratory tractCapture of the thermal plume before dilution

Mobile capture set-up and ventilation of a room without openings

The effectiveness of an extraction installation rests on the capture velocity at the point of emission. To neutralise stainless steel compounds, the air velocity at the arc must be sufficient to draw off the thermal plume without blowing away the inert shielding gas (argon or argon-helium mixture). On a metalwork construction site, using mobile filtration units fitted with an articulated arm or extraction torches is the technical solution consistent with the occupational health rules recognised in Switzerland.

  1. Geometric positioning of the nozzlePlace the capture hood upstream of the natural drift of the fume, at a distance never exceeding one times the nozzle diameter (typically between 10 and 20 centimetres from the weld bead area).
  2. Checking the filtration classCheck that the mobile unit includes an absolute filtration stage for toxic and carcinogenic dusts, with discharge outside the building if the room allows it.
  3. Adjusting the flow rate to the processAdjust the extraction to avoid drawing off the TIG shielding gas while maintaining constant negative pressure in front of the weld pool.
  4. Supplementary respiratory protectionWear an individual supplied-air respirator or a half-mask fitted with a filter against toxic solid and gaseous aerosols whenever the operator welds in a confined position.

When stainless stair strings or rails are assembled in a room without windows, a windowless technical room or the basement of a commercial building, the Ordinance on Construction Work (OTConst) requires a healthy atmosphere to be maintained and pollutants to be diluted. Extraction at source is no longer sufficient if the extracted air is discharged back into the room: a temporary mechanical sweeping flow must always be created. An extraction duct carrying the contaminated air to the open air is installed, together with a compensating fresh-air supply, to guarantee volumetric air renewal without creating dangerous negative pressure.

Positioning of the capture and discharge of air in a cramped space

On a finishing work construction site, connecting stainless steel rails or fixing base plates in a windowless stairwell, a service shaft or a basement demands strict airflow discipline. The classic mistake is to place an air stirrer or an axial site fan in an attempt to disperse the visible plume. This only dilutes the fine particles of hexavalent chromium and nickel throughout the work volume, exposing all trades present to highly toxic respirable aerosols. The Ordinance on the Prevention of Accidents prescribes the implementation of recognised technical measures to neutralise the risk at its very source.

To be truly effective, the air velocity at the point of emission must overcome stray draughts without blowing away the shielding gas under the diffuser of the TIG or MIG torch. A funnel fitted with a magnetic holder or a telescopic tripod is placed upstream of the natural thermal flow, at a distance never exceeding one and a half times the diameter of the extraction nozzle. If the metalwork configuration prevents an articulated arm from being brought close, the metalworker uses the high-flow extraction torch, which draws off the fumes directly at the nozzle without disturbing the argon curtain.

Behaviour of airflows according to the ventilation device in a closed room
Equipment usedMovement of welding fumesLevel of capture of chromium oxidesCompliance on site
Standard blowing fanDisorderly turbulence, dispersion throughout the roomNone (complete dispersion of pollutants)Non-compliant with safety rules
Mobile extraction arm with HEPA H13 filterLaminar capture at 20 cm from the weld beadVery high (over 99% of raw fumes)Compliant with discharge or certified filtration
Torch with integrated extractionImmediate capture at the gooseneck without diffusionOptimal on continuous linear passesCompliant subject to flow rate calibration
Extraction duct with discharge outsideContinuous negative pressure in the room and direct removalTotal (no air recycling in the zone)Priority solution in confined environments

Discharge of the contaminated air is the second critical point. In a windowless room, extracting is not enough: the extracted air must be channelled to the outside of the building using sealed spiral ducts made of fire-retardant technical fabric. If the distance to the façade or to an external opening prevents this direct discharge, the mobile capture unit must include an automatic filter-cleaning system and an absolute filter for toxic and carcinogenic dusts. The ordinance on the safety and health protection of workers in construction work requires care to be taken to maintain a healthy, renewed atmosphere at the workstation.

Airflow coordination, respiratory protection and residue management

In building metalwork, on-site welding often takes place during the finishing phase, among other trades such as painters or electricians. The general ventilation of the room must operate with air compensation: extraction at source creates a volumetric deficit that must be offset by a supply of clean fresh air, otherwise the flow rate of the mobile unit will drop due to pressure losses. The installation supervisor ensures that the outside discharge point is not located in the immediate vicinity of an air intake of the building's air-handling unit or of an office window.

  1. Preliminary check of the roomCheck that no combustible materials are stored nearby and ensure access to an air outlet to the outside for the extraction duct.
  2. Setting up negative pressure and connectionDeploy the flexible discharge hose, position the motor unit outside the confined zone if the layout allows, and connect it to the site power supply.
  3. Airflow setting of the nozzleSet the funnel 20 centimetres above the balustrade or handrail bead, orienting the capture so as not to draw off the protective inert gas flow.
  4. Safe removal of filtration residuesAt the end of the day, clean the filter unit according to the procedures provided for waste contaminated with heavy metal dusts, without dispersal into the air.

Maintenance of the mobile filtration units is an integral part of safety. The metal dusts retained on the cartridges contain concentrations of metal oxides that call for precautions when changing the filter. This operation is carried out wearing a disposable overall and a suitable respirator, the used filter being enclosed in a sealed bag. The ordinance on the prevention of accidents recalls the employer's responsibility for keeping the technical protection installations and equipment intended to preserve staff health on construction sites in perfect working order.

Shutdown procedure and emergency measures in the event of ventilation failure on site

During metalwork in enclosed or poorly ventilated spaces, welding stainless steel components generates particularly toxic compounds, notably hexavalent chromium and nickel, both classified as proven carcinogens. The ordinance on the prevention of accidents requires the employer to implement the technical measures needed to eliminate any risk to health. If the mobile capture device breaks down, if the nozzle cannot be positioned in the immediate vicinity of the bead or if the extraction flow weakens, the welding arc must be stopped without delay.

  1. Cutting the arc and evacuating the polluted zoneAs soon as a fault appears on the mobile extraction unit, the metalworker switches off the power supply of the welding generator, warns neighbouring workers of the danger and leaves the unventilated room to avoid any inhalation.
  2. Checking the capture unit and the filter mediumThe team checks that the flexible duct is not crushed, the saturation state of the filters for dusts and particles of the appropriate class, and the correct operation of the extraction motor outside the polluted room.
  3. Setting up substitute forced ventilationBefore any resumption of work in a closed room, a temporary mechanical supply or extraction system is deployed towards the outside to clean the ambient air, in accordance with the requirements of the ordinance on construction work.
  4. Wearing supplementary assisted respiratory protectionIf on-site welding of a handrail or balustrade has to be completed in a confined corner that rules out the articulated arm, the welder must wear a sealed ventilated hood with active particle filtration.

Work may resume only with the agreement of the site manager after verifying that capture as close as possible to the source has actually been restored. Traceability of extraction incidents and documented replacement of filter cartridges ensure compliance with Swiss occupational health directives.

Frequently asked questions

Why is a standard fan prohibited when welding stainless steel?

An ordinary fan neither captures nor filters pollutants; it merely creates an air current that disperses the carcinogenic particles of hexavalent chromium and nickel throughout the room. This uncontrolled dilution endangers the welder and all the other trades present on the construction site, in breach of the provisions of the ordinance on the prevention of accidents.

How far from the weld pool should the extraction nozzle be placed?

To guarantee airflow effectiveness without disturbing the gas shielding of the bead, the extraction nozzle or funnel must be between fifteen and twenty centimetres from the welding zone. If the nozzle is too far away, the toxic fumes escape into the worker's breathing air; too close, it draws off the shielding gas and causes inclusion defects in the stainless steel.

How do you ensure safety when welding stainless steel in a windowless basement?

In the absence of natural ventilation, the set-up requires extraction at source coupled with a general air extractor discharging the polluted flows outside the building. The fresh outside air supply must be sized to maintain an oxygen content compliant with the requirements of the ordinance on construction work, while requiring the installer to wear a supplied-air ventilated hood or a suitable filter.

What should be done with clogged filters containing stainless steel welding dust?

The residues of stainless steel welding fumes contain heavy metal compounds that are hazardous to health and the environment. Used cartridges must be sealed in airtight bags as soon as they are removed from the extraction unit, identified as special waste and handed over to an approved recovery or technical disposal channel, and never thrown into the construction site skips for general waste.

Texts and standards cited

  • OPAGeneral obligation of the employer to take technical and medical prevention measures against health damage.
  • OTConstRequirements relating to ambient air quality, the removal of pollutants and the ventilation of closed rooms on construction sites.