🧱 CFC 274Gates, grilles and motorised closuresChapter 6 of 10 in the section

Controlling access: electric strike, intercom, pre-installed cabling and the limits of our package

This chapter defines the technical interface between the locksmith and the electrical installer for access control on a swing or sliding gate. You will be able to prepare the mechanical recesses, integrate the electric strike or motorised lock, size the cable conduits and coordinate commissioning without holding up the construction site or disputing the limits of services.

Key takeaways

  • The locksmith installs the mechanical hardware and provides the internal cable routing up to the connection point.
  • The electrician supplies the low-voltage power, pulls the conductors through the conduits and makes the terminal connections.
  • An articulated cable guide or a recessed loop protects the conductors against shearing when the gate pivots.
  • The joint test of the strike confirms operation under mechanical load before formal acceptance.

Dividing the services between the CFC 274 locksmith and the electrician

On a construction site in French-speaking Switzerland, the installation of a controlled locking system often causes interface conflicts between the metalwork contractor of package CFC 274 and the electricians of packages CFC 232 (power installations) and CFC 238 (telecommunications and security installations). If the gate arrives on site before the cable ducts are installed, or the reverse, the lack of a written agreement on the limit of services exposes the work to destructive drilling in powder-coated profiles. Customary practice assigns to the locksmith the supply and installation of the load-bearing element, the leaf, the electric strike (fail-secure or fail-safe), and the machining of the recesses for the code keypad or badge reader on the technical post.

Usual division of tasks for gate access control
Component or operationLocksmith (CFC 274)Electrician (CFC 232 / 238)
Electric strike or motorised lockSupply, machining of the profile, mechanical fixingElectrical connection of the terminals
Buried conduit to the postIndication of entry points and exit dimensionsSupply, trenching and laying of the corrugated duct
Internal routing through the hollow postPulling the draw wire in the workshop or fitting a cable guidePulling the power and control cable
Articulated cable guide between post and leafSupply and fixing of the mechanical end fittingsThreading the conductors and connecting
Intercom, camera and street-side panelLaser cutting and watertight flush-mounting boxSupply of the device, installation and configuration

The locksmith's work stops strictly at the mechanical fixing of the low-voltage components. Putting a screwdriver to the strike's terminal block, installing the transformer in the main electrical panel or fitting the 12 V or 24 V power supply is exclusively the work of specialists holding the installation authorisation under the ordinance on low-voltage installations. A locksmith who connects a control unit incurs civil and professional liability outside the scope of his cover.

Coordinating pre-installed provisions, duct routing and commissioning tests

To avoid improvised drilling on the construction site, the locksmith sends his approved workshop drawing to the site management before the foundation blocks are poured. This document specifies the exact position of the fixing plate, the position of the duct passage opening in the hollow base and the ground clearance. When the civil engineering contractor pours the concrete base, the corrugated tubes must emerge at the centre of the post footprint with a free excess length of at least 500 mm to allow smooth pulling.

  1. Preparation in the locksmith's workshopMachine the housings for the electric strike, the lock and the control keypad before surface treatment. Drill the wire outlets with careful deburring, fit rubber grommets and slide a rot-proof nylon draw wire into each hollow post.
  2. Installing the structure on the concrete blockThread the pre-installed ducts into the post base during crane lifting or chemical anchoring of the threaded rods. Check that the cables are not pinched under the levelling plate or crushed against the concrete when the post is wedged plumb.
  3. Articulated link to the leafFit a flexible stainless-steel spring cable guide between the pivot post and the leaf if the lock is motorised on the moving upright. Position the spring at the neutral axis of the hinges to eliminate any stretching effect at 90 or 110 degrees of opening.
  4. Joint mechanical testCall the electrician for the connection. Carry out the unlocking tests of the electric strike under manual push, then under the action of a simulated wind, to ensure that the latch bolt does not bind against the adjustable strike.

Commissioning ends with a jointly signed test record in accordance with the rules of standard SIA 118. The electrician certifies the correct polarity, the operating voltage at the terminals and the absence of voltage drop during the control pulse. The locksmith demonstrates manual operation with the key in the event of a power failure and the free articulation of the cables. This coordination ensures the mechanical durability of the equipment and prevents claims relating to an operating defect at acceptance of the work.

Installation sequence and management of cabling provisions

On a fencing or outdoor landscaping construction site, perfect synchronisation between the CFC 274 locksmith and the CFC 232 electrical installer is often a matter of theory. Two scenarios dictate the method: either the metal gate is anchored before the lines are pulled, or the control and power cables emerge from the concrete blocks before the leaves arrive. To avoid destructive rework in powder-coated profiles or finished masonry, the metalworker applies strict provisioning rules from workshop fabrication onwards.

When the gate arrives on the construction site before the cables are pulled, the metal structure itself serves as a watertight cable route. The locksmith incorporates into his tubular uprights smooth conduits or continuous internal guides, with no machining burrs or sharp edges from mitre cuts or welds. A rot-proof polyamide draw wire is slid in at the workshop between the base of the technical post and the housing of the electric strike or the intercom panel. The base of the hollow post has an oblong passage opening, aligned with the provision tube embedded in the ground beam by the mason. This passage ensures that the electrician's pulling needle runs freely without catching on an anchor weld.

If the electrician's cable already emerges from the concrete base when the post is installed, the main risk is pinching or shearing of the conductor when the anchor studs are tightened. The installer must thread the strand directly into the metal upright during the lifting phase. The cable is coiled inside the post and temporarily sealed at the top with a plug that is watertight against rain infiltration and cement laitance runoff. Installing the gate must in no case force the cable insulation against the base plate or under the levelling shims.

Locksmith-electrician interface, strike and joint tests

The limit of services between the trades must be clear-cut to prevent disputes at acceptance of the work under standard SIA 118. The locksmith supplies, adjusts and fixes the mechanical elements: the leaf, the closing post, the mortise lock, the electric strike matched to the profile, the armoured flexible stainless-steel cable guide at the hinge if the device is on the leaf, and the laser-cut intercom support. The electrician takes charge of the low-voltage supply, the modular transformer at the panel, the access control module and the physical connection to the strike's terminal block.

Division of tasks between the CFC 274 locksmith and the CFC 232 electrician
Access componentLocksmith (CFC 274)Electrician (CFC 232)
Electric strike (12/24 V)Supply, mortising, mechanical installation and alignment of the latchConnection to the terminal block, power supply and interlocking
Stainless-steel spring cable guideMechanical installation on leaf and frame with deburringThreading the flexible multi-conductor cable
Intercom post or panelMetal support, mechanical fixings and cut-outsSupply of the device, bus cabling and configuration
Buried conduit to postCoordination of the base exit templateLaying the bent tube, pulling the power cable

The type of strike selected requires particular care during installation. A fail-secure strike (releasing on an electrical pulse) releases the latch bolt on the electrical pulse and keeps the gate locked in the event of a mains power cut. A fail-safe strike (releasing on loss of current) unlocks the access as soon as power is cut, meeting emergency evacuation requirements. The locksmith must set the rebate clearance between three and five millimetres: a smaller clearance jams the latch bolt against the faceplate under summer thermal expansion, while a larger clearance prevents the bolt from activating the signalling contact.

  1. Mechanical alignment check without voltageCheck that the gate closes smoothly under the action of the door closer or by hand. The latch bolt must enter the centre of the strike's receptacle without vertical metal-on-metal friction or lateral stress on the pivoting jaw.
  2. Unlocking test under residual pushSimulate manual pressure against the leaf equivalent to a gust of wind and command the electrical opening. The strike must release without mechanical blockage under this preload.
  3. Joint verification at commissioningCarry out the full functional test in the presence of the electrician: intercom call, triggering of the opening delay, automatic relocking after passage and operation of the emergency mechanical cylinder.

Managing interface disputes and fallback protocols on the construction site

On construction sites in French-speaking Switzerland, the recurring conflict arises when the screeds or outdoor asphalt surfacing are completed without the control cable emerging in the technical post, or conversely when the locksmith installs his tubular upright before pouring, crushing the CFC 232 provision. If the cable has not been pulled when the gate is installed, the locksmith fitter must in no case permanently seal the technical covers or inject resin without having checked the free passage with a pulling needle and a nylon draw wire left in place.

  1. Joint inspection record of the obstructionAs soon as a conduit proves to be blocked, kinked or severed under the concrete base, immediately send a notice of interruption to the site manager of the site management. Clearing it with a heavy rod or reopening the civil engineering work is not the responsibility of the locksmith package.
  2. Mechanical discharge test of the strikeIn the absence of the final power supply from the electrician, test the mechanism with a portable 12 V or 24 V source according to the coil specifications. Record in writing the correct operation of the latch bolt and of the pulse in order to clear the locksmith's liability.
  3. Recording of the pre-installed loopsIsolate the control wires of the electric lock in a temporary watertight box housed in the post, mark the terminal diagram and require a signature on the installation slip before withdrawing from the site.

Standard SIA 118 governs the acceptance of concealed parts of the work. When the pedestrian gate incorporates a magnetic lock or an electromechanical strike, the joint test with the electrical fitter constitutes the formal hold point. If the intercom is not installed, the validation of the low-voltage live line and the mechanical closing of the leaf are the subject of a separate test record, avoiding unjustified late-completion penalties.

Frequently asked questions

Who supplies the articulated cable guide between the fixed post and the moving leaf?

The supply and mechanical installation of the flexible stainless-steel cable guide are the locksmith's responsibility (CFC 274), because they require workshop drilling protected against corrosion and adjustment to the opening radius. The electrician then takes over to thread his flexible multi-conductor cable inside the flexible guide and make the end connections on the electric lock's terminal block and the main power supply.

How do you test the electric strike if the electrician has not yet installed the power supply?

The locksmith foreman uses an autonomous 12 V or 24 V DC backup battery connected directly to the strike terminals. A brief pulse is applied to check that the latch bolt retracts under the mechanical preload of the leaf. This confirms that the strike works perfectly and that the leaf exerts no abnormal stress before the electrician's control cable is finally installed.

What should you do if the pre-installed conduit exits 15 cm from the actual axis of the metal upright?

Never grind the fixing plate or force the upright onto the duct, at the risk of pinching it. Record the deviation in the daily report intended for the site management. The adaptation requires either a low junction box at the post base installed by the electrician, or a corrective core drilling approved by the mason before the gate is finally anchored.

Who is responsible for water tightness at the point where the cable enters the tubular profile?

The locksmith prepares the drilling with a tapped thread or a smooth deburred hole in the workshop. The electrician supplies and tightens the metric cable gland suited to the outer diameter of the cable when pulling it. Rainwater penetration into the tubular profile or the control box is the responsibility of the connecting contractor if the cable gland is missing or incorrectly sized.

Texts and standards cited

  • norme SIA 118General conditions for the execution of construction work, acceptance of the work and handling of notices of defects.