Cement or anhydrite screed: selection and execution: the execution reference guide

Intended for team leaders, foremen and site managers, this section covers the decisive choice between cement binder and calcium sulphate, as well as on-site execution rules. It provides practical benchmarks for sizing the nominal thickness, controlling mixing water, managing fluid or traditional pouring, and accepting a substrate that complies with tile or parquet flooring requirements in accordance with SIA 251.

  • 10chapters
  • 22 000words
  • 6sections in the training course
  • 60chapters in total

Key values to remember 4

Norme SIA 251

35 mm

Minimum embedment of a calcium sulphate fluid screed on compressible insulation in residential premises

Norme SIA 251

45 mm

Minimum thickness of an unheated floating cement screed for standard distributed loads

Norme SIA 251

30 mm

Minimum cover above the top of underfloor heating pipes with cement mortar

Norme SIA 251

5 °C

Ambient and substrate temperature below which pouring is prohibited without special measures

Technical scope of the screed layer: binders, implementation and interfaces

The choice of binder determines the entire interior floor physics. This section covers the fundamental trade-off between traditional cement mortar and calcium sulphate-based fluid screed, commonly known as anhydrite. For the site manager and foreman, this trade-off involves the room's residual moisture tolerance, drying kinetics, dimensional shrinkage behaviour and direct chemical compatibility with the flooring adhesive specified in the tender.

The screed layer's responsibility begins on the blinding layer or on the laid thermal and acoustic insulation layer. It includes the rigorous installation of the perimeter uncoupling edge strip, thickness adjustment at the thinnest point, preparation or acceptance of the mixed mortar, vertical pumping, mechanical compaction or de-aeration, and ends with the required surface preparation before the finishing trades intervene. Checking mechanical strengths by taking standardized test specimens confirms the compliance of the delivered work.

Also excluded from this scope of work are the supply and installation of final floor coverings. Tiling, waterproofing under tiles and the treatment of flexible joints belong to the tiler. The glued or floating installation of parquet, wood sanding and skirting boards are the responsibility of the parquet installer. Finally, fine self-levelling smoothing compounds, floor paints and decorative or industrial resins are applied by their respective applicators, based on the inspection reports issued by the screed layer.

The nominal thickness of the screed must be respected over the entire surface. Execution tolerances of the raw slab can under no circumstances justify a reduction in the minimum thickness required above insulation or heating pipes.

Norme SIA 251

Progress method: from design choices to work acceptance

Organizing a screed construction site requires anticipating drying, load and supply logistics constraints well before the arrival of the mixer truck or mobile batching plant. To ensure smooth progress and prevent structural defects, the study of the technical chapters must follow a rigorous sequential logic, dictated by the requirements of SIA 251 and Swiss codes of practice.

  1. Qualify the binder and the geometry of the workWe begin systematically with the comparison between cement and calcium sulphate according to the intended use of the rooms, followed by the calculation of the nominal thickness at the high point of the structural work, in order to prevent any punching failure.
  2. Master formulation and mechanical behaviorWe then analyze the specificities of self-levelling fluid mortars, the direct influence of the water-cement ratio on compressive strength and the exact usefulness of reinforcement meshes or fibres with respect to plastic shrinkage.
  3. Manage implementation and surface treatmentWe examine the methods for adjusting flatness using a straightedge, the techniques for floating or sanding the anhydrite surface laitance to guarantee the mechanical adhesion of future adhesives.
  4. Secure site conditions and contradictory inspectionsWe finish with thermal protection during the winter period, the layout planning for vertical façade pumping, and the mortar prism crushing protocol to settle any strength disputes.

This methodological structure provides site management with an operational reading grid. Each chapter provides a direct dimensional or prescriptive response, which can be mobilized immediately when drafting tenders, checking plans or coordinating technically with other finishing trades.

📘 Chapters in this section 10

Cement or anhydrite screed: selection and execution

Cement or anhydrite: room humidity, drying, shrinkage and planned floor covering

Select the perfect binder to secure drying and prevent any subsequent tile detachment.

Cement or anhydrite screed: selection and execution

Thickness: minimum according to binder and load, with the thinnest point being decisive

Calculate the nominal thickness at the high point of the substrate to prevent failure under operational load.

Cement or anhydrite screed: selection and execution

Liquid screed: formwork sealing, de-aeration, and leaks through pipe penetrations

Seal pipe penetrations securely and master de-aeration without causing detrimental settlement.

Cement or anhydrite screed: selection and execution

Water: excess water, lost strength, increased shrinkage and chalking surface

Adjust the mixing water volume to eliminate surface dusting and maximize internal compactness.

Cement or anhydrite screed: selection and execution

Reinforcing the screed: mesh, fibres, what it prevents and what it does not prevent

Distinguish the real effectiveness of synthetic fibres versus welded wire mesh for managing crack opening.

Cement or anhydrite screed: selection and execution

Flatness: tolerance by class, measurement with a straightedge, and what the tiler will demand

Check deflections under the two-metre straightedge to deliver the work required by the tiler.

Cement or anhydrite screed: selection and execution

The surface: smoothing, anhydrite laitance to be sanded, and bonding of the covering

Thoroughly remove the superficial laitance film to guarantee a lasting adhesion bridge for floor coverings.

Cement or anhydrite screed: selection and execution

In winter: room and substrate temperature, freezing before setting, and lost screed

Organize auxiliary heating and monitor morning frost to preserve the initial hydration of the mortar.

Cement or anhydrite screed: selection and execution

Pumping on upper floors: pipe length, blockage, cleaning and truck access

Optimize the routing of vertical delivery columns to prevent the onset of blockages on upper floors.

Cement or anhydrite screed: selection and execution

Checking strength: test specimens, sampling, and the dispute they resolve

Sample and store test prisms according to codes of practice to close any contradictory debate.