Key takeaways
- The intervention window requires an area completely cleared of any finishing work trade.
- The formal prohibition on walking on the work lasts for a minimum of forty-eight to seventy-two hours.
- Physical barricading at access points with dated signage prevents destructive trampling by other trades.
- The choice of installing partitions before or after the screed determines the overall acoustic insulation.
Negotiating the pouring window and securing the floor
Pouring a screed allows zero coactivity. When the mobile batching plant or mixer truck sets up at the foot of the building, the delivery hoses pass through stairwells or facade shafts. Throughout the entire phase of pumping, raking and passing the levelling bar for a fluid screed, or tamping and trowelling for a traditional cement screed, the space must be entirely empty. The site manager must secure this time slot in the general construction site schedule several weeks in advance.
For a slab of four hundred to six hundred square metres, the actual pouring window requires a full day. However, the immobilisation of the area extends well beyond the placement of the mortar. The binder needs rest to initiate its chemical setting without undergoing vibrations or mechanical deformations. Site management regularly underestimates this rest period and attempts to introduce electricians or painters as early as the day after pouring, which exposes the work to irreversible damage: premature cracking, surface indentation or crushing of insulating underlays under point loads.
| Type of mortar or fluid | Foot traffic prohibited | Light foot traffic | Heavy load storage |
|---|---|---|---|
| Calcium sulphate fluid screed | Minimum 24 to 48 hours | From 48 to 72 hours | After complete drying validated by CM |
| Traditional cement screed | Minimum 72 hours | After 7 full days | After 28 days of hardening |
| Fast-setting screed (special binder) | Minimum 12 to 24 hours | From 24 hours | According to manufacturer's technical datasheet |
In parallel with the physical obstacle, the written information protocol is essential to release the trade's liability. A formal notice is sent by email or via the project management platform to the site management at least ten working days before the start, then confirmed forty-eight hours before the arrival of the trucks. This document recalls the direct consequences of premature entry: refusal to cover footpaths, deterioration of flatness according to the tolerances of standard SIA 251 and deferral of warranty to the identified culprit.
Arbitrating the execution sequence between light partitions and screed
The articulation between the assembly of partition walls and the pouring of the floating screed determines the acoustic comfort and mechanical durability of the premises. In Western Switzerland, two approaches contrast depending on the requirements of the architectural project. The chosen option dictates the preparation requirements for the screed layer, in particular the installation of the peripheral edge insulation and the treatment of movement joints.
- Option 1: Light partitions installed before the screedPlasterboards on metal framing are installed directly on the raw load-bearing slab, with a resilient base strip. The screed layer then intervenes in each compartmentalised room. This method offers maximum lateral acoustic insulation between adjoining apartments or offices, because the screed is physically interrupted under the partition.
- Option 2: Continuous screed poured before partitionsThe mortar is poured over the entire open floor slab, free of wall obstacles. The plasterer subsequently erects light structures directly on the hardened screed. This approach greatly accelerates the screed layer's pouring pace but degrades overall acoustic performance through transmission of footsteps from one room to another.
In cases where the screed is poured first, the screed layer must obtain a precise layout plan of the future partitions in order to match its stop or shrinkage joints. Executing an angle grinder cut in a heated floating screed without knowing the routing of integrated heating coils exposes the construction site to the perforation of hydraulic circuits. Technical consultation between the finishing work drywaller, the heating engineer and the screed layer is therefore mandatory before validating any pouring phase.
Restriction device and access prohibition signage
Upon completion of the pouring or grading of a daily step, access to the surface must be physically impossible. Fresh screed, whether it is calcium sulphate fluid screed or traditional cement screed, tolerates no point loads during its initial setting phase. The accidental entry of a worker or third party causes immediate structural defects: level deformations, indentation of the mesh or tearing of edge strips, not to mention the crushing of pressurized underfloor heating tubes. The prohibition of access is not a simple site courtesy, but an essential technical measure to preserve the flatness and internal cohesion of the mortar. Any compromise on this point jeopardises the durability of the finished work.
The signage must be visual, explicit and difficult to move. Notices must be affixed to each potential crossing point, drafted with standardised pictograms of formal entry prohibition. This signage mentions the date and time of the end of pouring, the exact date from which light pedestrian passage is authorised, as well as the name and telephone number of the screed foreman. Any intrusion prior to the formal lifting of the ban engages the liability of the offending company for repair work or reconstruction of the damaged bay.
- Neutralisation of lift and hoistway landing controls for the concerned floor.
- Installation of wooden laths screwed across stair landing access points.
- Posting a notice prohibiting movement on each apartment door, landing shaft and French window.
- Complete closure and locking of windows to avoid violent drafts causing premature surface desiccation.
Contractual notification and trade intervention schedule
Securing a floor cannot be improvised the day before pumping. It is part of a written information protocol managed with the site management and communicated during weekly site coordination meetings. The screed layer transmits their pouring notice at least ten working days before the first implementation. This written notification sets the detailed schedule: installation day for the mixing plant or silo, pouring days by sector, total closure period and return date of the floor for work without heavy loads. Other trades must evacuate materials, stepladders and waste before taking possession of the level.
| Type of screed | Absolute access prohibition | Pedestrian trafficability | Heavy load traffic |
|---|---|---|---|
| Calcium sulphate fluid screed | 48 hours | After 48 to 72 hours | After 7 full days |
| Traditional cement screed | 72 hours | After 3 to 4 days | After 14 to 21 days |
| Fast-drying screed | 24 hours | After 24 to 48 hours | After 3 to 5 days according to technical datasheet |
The articulation between the execution of the screed and the installation of light partitions on metal framing requires an arbitration recorded in the site minutes. When distribution partitions are mounted on the screed for acoustic imperatives, the plasterer only starts their framing after the pedestrian trafficability period. Rolling scaffolding loaded with boards and storing tile pallets mid-span remain excluded until hardening has reached its nominal strength. The written information reminds site management of these load limits to prevent any premature sagging of the insulating complex under the screed.
In the event of unauthorised intrusion despite warning signs, the screed foreman establishes a joint inspection record as soon as the damage is discovered. A detailed formal notice is notified in writing to the site management, accompanied by dated photographs attesting to the state of broken barriers and the depth of footprints. This document releases the screed company from its warranty regarding final flatness and allows repair or fibre-reinforced levelling costs to be passed on to the offending trade, in accordance with the general execution rules of standard SIA 118.
Management of access infractions and contractual claims
Despite door chains, ribbons and warning signs, illicit entries onto fresh screed remain frequent. As soon as a party forces passage during the hardening phase, the screed layer must act according to a strict procedure to release their liability and preserve financial rights facing site management.
- Immediate inspection and securing of evidencePhotograph footprints, scaffolding wheel tracks or floor indentations. Frame fractured access points or torn warning tapes with a metric reference. Note the day, exact time and identity of the company present in the room.
- Formal notice to site managementTransmit a written notice of defects the same day to the site management and client according to standard SIA 118. Explicitly mention that the warranty for flatness, surface cohesion and cracking is suspended on degraded surfaces.
- Establishment of the joint protocolConvene the site manager and the responsible person of the offending trade on site. Record the extent of damage on a signed joint report: deteriorated square metres, depth of hollows and debonding of insulation under the screed.
- Refusal of makeshift repairsRefuse any cosmetic levelling applied hastily. Rework requires a clean cut with an angle grinder down to the insulation or heavy mechanical sanding, the costs of which fall exclusively on the author of the infraction.
If the conflict blocks the continuation of the work, the screed layer records the interruption in the site logbook. Delays induced by the repair of a crushed bay entitle the contractor to an extension of execution times and compensation for team remobilisation costs.
Frequently asked questions
What to do if the drywaller refuses to install their rails before our pour?
Formally remind the site management of the acoustic requirements of standard SIA 251. Installing light partitions directly on the floating screed creates major acoustic bridges between rooms and restricts shrinkage movements. If management nevertheless imposes this inverted execution sequence, issue a formal written notice declining all responsibility regarding corner cracks and lateral acoustic transmissions.
Who pays for repairs if an unidentified worker walks on the fresh mortar?
If the screed layer correctly restricted access and notified prohibition dates in writing, the custody of the work lies with the site management. In the absence of a designated culprit among the trades, the rework of the screed must be ordered by a work order or an addendum signed by the client before any hacking intervention.
Can other workers be authorised to pass after 48 hours on cement screed?
A traditional cement screed is trafficable for light walking and without load after two to three days depending on ambient temperature. On the other hand, storing tile pallets, rolling scaffolding or erecting partitions remain strictly excluded for at least seven days. Any early access must be the subject of a written agreement strictly limiting the floor load.
How to legally materialise the official unblocking of the floor?
The screed layer submits a written access release notice to site management, indicating the exact opening date and permissible load limits. This notice specifies that the floor remains in the drying phase and prohibits any water projection or airtight storage. Prohibition signs are only removed from doors after the site manager formally signs this document.
Texts and standards cited
- norme SIA 118General conditions for the execution of construction work, management of notice of defects, work interruption and contractor's rights.
- norme SIA 251Technical specifications, execution rules, decoupling and protection periods for floating screeds in buildings.