Key takeaways
- Heating a closed room without extraction saturates the air and stops the screed from drying.
- The condensation dehumidifier requires an airtight room to capture the released water.
- Intermittent or cross-ventilation evacuates humid air without creating a permanent draught.
- Direct oil-fired heaters release water vapour and rehumidify the closed construction site.
Blind heating saturates the interior volume without drying the screed
Raising the temperature accelerates the migration of capillary water towards the surface of the screed, but this physical step remains ineffective if the ambient air is not dehumidified. When the temperature rises in a hermetically sealed room, the relative humidity may temporarily drop due to thermal expansion, while the absolute humidity remains identical. The water extracted from the screed evaporates into the interior volume until it reaches saturation point. At this stage, the water vapour pressure of the air balances with that of the mortar: moisture transfer stops completely. Without an external dry air supply or mechanical condensation, the room turns into a drying kiln, encouraging nocturnal condensation on cold walls and the reabsorption of water by the material.
SIA 251 strictly regulates the ambient curing and drying conditions for screeds. During the first few days following installation, the cement screed must be protected against premature desiccation to allow the hydration of hydraulic binders. Heating too early or ventilating too abruptly causes differential shrinkage between the surface and the core of the mortar, generating destructive crazing or edge lifting due to the bimetallic effect. Once the minimum curing period has been respected, the supply of heat must only serve to support the air's capacity to transport moisture to a controlled outlet, never to bake the mortar.
| Method | Moisture behaviour | Technical risk | Overall efficiency |
|---|---|---|---|
| Heating only in a closed room | Absolute humidity stagnates, rapid saturation of the air | Condensation on glazing and rehumidification | Null |
| Direct propane heating | Absolute humidity increases through combustion | Surface pollution, water saturation | Negative |
| Continuous ventilation via draughts | Too rapid evacuation at the screed surface | Differential shrinkage, crazing and curling | Dangerous |
| Dehumidification in a closed enclosure | Absolute humidity decreases continuously | None if the initial curing period is complete | Optimal |
Dehumidifiers and cross-ventilation: water evacuation protocols
To lower the mass moisture content of a screed without damaging its crystalline structure, the evaporated water must be physically extracted from the building. Two distinct strategies achieve this result: drying using refrigeration dehumidifiers in an enclosed environment, or intermittent cross-ventilation through air exchange with the outside. The choice of equipment depends on the season, outside weather conditions and the contractual phasing of the finishing work trades.
- Confinement of the volumeHermetically seal all glazed openings, exterior doors and technical shafts. The slightest infiltration of warm, humid exterior air in summer, or uncontrolled parasitic air, unnecessarily overloads the appliance's compressor.
- Positioning of appliances and air mixingPlace the condensation dehumidifiers in the centre of rooms or open areas, elevated on rigid blocks. Combine them with air-mixing fans tilted towards the ceiling to avoid any direct blowing onto the screed while homogenising the boundary layer.
- Connection of gravity drainageIt is essential to connect a continuous drainage pipe to a wastewater drain or temporary siphon. Integrated collection tanks cause machines to stop automatically once full, interrupting drying at night and over weekends.
- Daily control of ambient parametersRecord the temperature and relative humidity daily using a calibrated thermo-hygrometer. The optimal performance of a condensation dehumidifier is between 15 °C and 22 °C; below 10 °C, the unit frosts up and requires thermal assistance.
When dehumidifiers are not used on the construction site, cross-ventilation is the only alternative that complies with trade standards. This process does not consist of leaving windows ajar or in a tilt-and-turn position permanently, which creates localized draught zones responsible for shrinkage cracks along corridors. It requires full, opposite openings for fifteen to twenty minutes, three to four times a day. This aerodynamic shock replaces the indoor air laden with moisture with drier outdoor air without permanently lowering the temperature of the walls or generating a sweeping draught harmful to the screed.
Transfer kinetics and auxiliary heating traps
To extract excess mixing water from a screed without degrading its mineral matrix, raising the ambient temperature is not enough. Surface evaporation obeys saturated vapour pressure gradients between the core of the mortar and the ambient air. According to SIA 251, any temperature rise must be accompanied by strict regulation of the room air's humidity level. If the air is warm but saturated at over 80% relative humidity, transfer stops completely: the partial pressure of water vapour in the room blocks capillary migration. The injected heat energy then runs in a closed loop without drying anything.
Water leaving the screed in gaseous form must be physically extracted from the building. Two technical pathways allow this evacuation: continuous mechanical extraction via a dehumidifier or methodical air renewal via cross-ventilation. During the mechanical dehumidification phase, the building must be completely sealed to avoid drying out the outside air. Conversely, during the natural ventilation phase, openings must be wide and crosswise to expel the moisture-heavy air without permanently cooling the structural masses.
Dehumidification protocols and comparison of evacuation methods
The sizing of a fleet of dehumidifiers is calculated not just on floor area, but on the total volume of the room and the initial water content of the structure. Condensation units are optimal above 15 °C. When temperatures drop below the 10 °C mark in winter, the efficiency of refrigeration compressors collapses due to icing; the installation of adsorption units equipped with a desiccant wheel discharging humid air via an external duct then becomes necessary. Whichever system is chosen, automatic condensate drainage to a connected network drain is mandatory: a full tank that switches the machine off at night results in the loss of the entire day's drying gain.
| Site configuration | Effect on ambient air | Impact on the screed | Water evacuation |
|---|---|---|---|
| Heating only, closed room | Temperature rise, rapid saturation (RH close to 100%) | Interruption of evaporation, risks of condensation and cracking | None: water remains confined within the closed volume |
| Direct gas heating (flueless) | Massive production of combustion water and CO2 | Slowing of drying, degradation of mineral surfaces | Negative: the system adds more water than it extracts |
| Shock cross-ventilation (3 to 4 times a day) | Abrupt lowering of absolute humidity, maintenance of wall energy | Resumption of the evaporation gradient, healthy and steady kinetics | Excellent: direct evacuation to the outside atmosphere |
| Condensation dehumidifier in a sealed room | Relative humidity lowered between 45% and 55% at stable temperature | Gradual extraction without brutal surface desiccation | Continuous: condensates permanently evacuated via flexible hose |
To validate the actual drop in moisture content and prepare for handover according to SIA 251, the site manager must establish daily thermo-hygrometric monitoring. The target equilibrium point for a cement screed is below 70% relative humidity in the ambient air at 20 °C. The classic mistake is to stop appliances prematurely as soon as the surface looks light and dry. Deep down, residual moisture remains trapped if the extraction flow is interrupted. Only the correlation between extracted condensate readings and destructive calcium carbide measurement (CM device) confirms the substrate's actual readiness to receive its final covering.
Emergency management for drying blockages and moisture saturation
On a closed construction site, the appearance of droplets on glazing, a damp film on ceilings or a stagnation of water mass loss indicates a saturated environment. Heating a closed room without renewing the air is a recurring error: heat accelerates the extraction of liquid water from the screed into the ambient atmosphere, but as soon as the air reaches saturation point, transfer stops abruptly. Water does not disappear by magic; it must be captured or driven out of the building envelope.
- Immediately break saturation via thermal shockSimultaneously open opposite openings to create a sharp cross-ventilation for ten to fifteen minutes. This supply of cold, dry outdoor air sweeps away the warm air laden with water vapour without lowering the mass temperature of the floor.
- Install suitable condensation dehumidifiersHermetically close windows and deploy professional electric condensation dehumidifiers. It is essential to connect gravity drainage pipes to a wastewater stack or temporary siphon to prevent tank overflows.
- Record hygrothermal parameters in the logbookMonitor ambient temperature and relative humidity twice a day using a calibrated thermo-hygrometer. SIA 251 sets out the climatic requirements necessary to drive drying down to the prescribed residual rate.
If the client refuses the installation of dehumidifiers or disputes site electricity consumption, the screed layer must immediately exercise their written duty to notify in accordance with the Code of Obligations. Installing a floor covering on a floating screed that has not reached moisture equilibrium directly engages the company's liability if reservations have not been formulated in the required form.
Frequently asked questions
Why is the screed no longer drying despite the continuous operation of construction heaters?
Heating the air increases its absorption capacity, but without renewal, the atmosphere quickly reaches one hundred percent relative humidity. At saturation, the air can no longer absorb water vapour from the mortar. Evaporation stops completely. Thermal energy runs idle and risks damaging the structure through condensation. It is essential to combine condensation dehumidifiers or cross-ventilation sequences to physically evacuate this water out of the interior volume.
Should tilt-and-turn windows be left open permanently with a dehumidifier?
No, this is a major technical error. An air dehumidifier operates in a closed circuit: leaving a window ajar lets in the humidity of the outside air, which the appliance tries in vain to dry without treating the screed's water. To dry efficiently, the room must be hermetically sealed during mechanical dehumidification, or ventilated by short, cross-cutting bursts in the absence of a machine to expel saturated air.
How should the evacuation of condensed water from dehumidifiers be organised on a construction site?
Integrated tanks fill up within a few hours and automatically stop the appliances via a safety float switch, interrupting the process at night or over the weekend. The team must connect a flexible hose to the continuous drainage nipple of each unit and run this flexible pipe to a wastewater drain, floor gully or a fifty-litre container placed in a retention basin regularly checked by the site manager.
Does SIA 251 authorise the use of direct-combustion gas space heaters?
SIA 251 prohibits heat generators without flue gas extraction ducts for drying screeds. The combustion of propane or fuel oil produces approximately one litre of water vapour per kilo of fuel burned. These appliances directly increase the amount of water present in the room instead of drying it, saturate the air with moisture and deposit harmful soot residues on the mortar surface.
Texts and standards cited
- SIA 251Floating screeds and poured floors in buildings: implementation climatic requirements and drying conditions