🧱 CFC 281Screed on underfloor heating and floor coveringChapter 9 of 10 in the section

Document before pouring: photo of the heating coil, joint plan and drilling depth

At the end of this chapter, you will know how to compile the complete as-built documentation before pouring the screed: organise the photographic report with metric rods, mark the exact location of control joints and formally record the permissible drilling depth for handover to the client.

Key takeaways

  • Photograph all heating coils with a graduated rod placed on the reference axes.
  • Mark control joints on the plan in accordance with door openings and thresholds.
  • Record the concrete/mortar cover thickness in writing to set the maximum authorised drilling depth.
  • Hand over the complete documentation to the client before the flooring contractors intervene.

The metric photographic campaign before the arrival of the truck mixer

As soon as the truck mixer or the screed pump is in position, access to the substrate is permanently lost. Anything that has not been visually recorded before pumping begins becomes invisible to the other trades. The tradesperson who comes to install a door stop, fit light partition rails or anchor a fitted cabinet will have to drill into the mortar thickness without damaging the heating installer's heating pipes. Producing a complete and standardised photographic file is the responsibility of the screed layer during the acceptance of the heated substrate, just before pouring the screed.

As-built plan of a heated screed
Contractual documentary package including georeferenced condition-survey photographs or photographs referenced to raw walls, the diagram of the embedded underfloor heating circuits, the precise layout plan of the shrinkage joints and the indication of the nominal cover thickness above the pipes.

A simple overview taken from the entrance of a room has no future operational value. Without a scale reference, the perspective effect of a wide-angle lens prevents any reliable retrospective measurement. For each room, the procedure requires placing a graduated rule or folding rule directly onto the insulation or mesh, deployed perpendicularly to an identifiable raw masonry structure. Sensitive areas require close-up framing: door openings, service duct crossings, narrow partition areas and the immediate vicinity of sanitary and heating manifolds.

  1. Setting up metric reference markersPlace two two-metre rules on the floor: the first pressed against the finished raw masonry or door frame, the second perpendicular along the heating coil layout.
  2. Axial shooting of passagewaysPhotograph vertically, plumb with the door thresholds, the protective sleeves shielding the pipes where they cross future movement joints.
  3. Framing the distribution headersRecord close-ups of the loop departures at the distribution cabinet, with visible labelling of the rooms served and pipe spacing.
  4. Timestamped digital archivingImmediately name each photograph according to the project nomenclature (floor, flat number, room) before injecting the fluid or traditional binder.

Joint plan, cover calculation and handover protocol to the client

The plan for control and expansion joints must strictly match the layout of the heating coils. According to good trade practice for screed layers and the guidelines of the SIA 251 standard, a control joint must never cut an unprotected heating pipe; crossing connections must be sleeved for a minimum length on either side of the cut. The as-built plan indicates the precise location of synthetic or metal joint profiles inserted into the fresh screed or sawn after initial hardening.

Cover parameters and drilling limits according to the binder
Type of fluid or traditional screedMinimum cover thickness above the pipeOn-site execution safety marginMaximum permissible depth for plugging/anchoring
Traditional cement screed on insulation45 mm10 mm35 mm from the finished mortar surface
Calcium sulphate (anhydrite) based fluid screed30 mm5 mm25 mm from the finished mortar surface
Special self-levelling cement screed35 mm5 mm30 mm from the finished mortar surface

Determining the permissible drilling depth stems directly from the cover thickness recorded during pre-pouring rod checks. This dimension must be stated in millimetres on the screed work completion report. If the floor receives tiles or bonded parquet, the usable drilling depth for subsequent trades will increase by the thickness of the finished covering, but the baseline value certified by the screed layer strictly concerns only the mass of screed located above the upper generator of the pipe.

The position of control joints and expansion joints must be coordinated between the planner, the heating installer and the screed layer. Heating pipes crossing a joint must be protected by deformable sleeves.

Norme SIA 251

The finalised as-built documentation is officially handed over to the site management and to the client in the forms provided for by the SIA 118 standard and the company's contractual clauses. This binder, whether physical or digital, includes the dimensioned plan of the actual joints, the captioned photographs of the loops before closure, the thickness checking reports and the drilling warning sheet. This traceability releases the screed contractor from any presumption of fault if a third party were to perforate a hydraulic pipe when fixing finishing work elements.

Determining the permissible drilling depth and locating sensitive areas

The cover over underfloor heating pipes forms a thin physical barrier between the thermal installation and the finished surface. As soon as secondary trades intervene — light partition installers, joiners for door stops, rail installers for fitted wardrobes — the screed is subjected to mechanical drilling stresses. If the documentation does not specify the available anchorage reserve, the risk of nicking a manifold or a pressurized pipe becomes immediate. The safety dimension calculation is established from the total thickness poured, minus the height of the pipe, its stapling system and the flatness tolerance permitted by the SIA 251 standard.

Safety margins for mechanical fixings according to the screed assembly
Type of screedCover thickness above the pipesPermissible drilling depthRecommended fixing method for accessories
Traditional cement screed (CT)45 mm nominal (local tolerance ± 5 mm)25 mm maximum with mechanical drill bit stopShort plug/anchor or polymer bonding for light stops
Calcium sulphate based fluid screed (CA)35 mm nominal (local tolerance ± 3 mm)15 to 20 mm maximum with depth guideSystematic structural bonding of stops and profiles
High-performance thin cement screed30 mm nominal (local tolerance ± 2 mm)Total prohibition of mechanical drillingExclusive chemical bonding on compatible primer
Dense passage areas (thresholds and duct surroundings)Variable depending on sleeve overlapTotal prohibition of mechanical drillingWall mounting or technical skirting board fixing

To prevent accidental drilling, the screed layer must report on the summary document the thickness measured in situ during execution, expressly mentioning the net reserve above the upper generator of the sleeves. This value takes into account any high points in the floor insulation or irregularities in the load-bearing slab not compensated by the levelling layer.

Compilation of the as-built documentation and transfer to finishing work contractors

The as-built plan of a floating screed is not limited to a theoretical execution diagram; it compiles the actual data recorded before pumping the mortar. This technical file legally protects the screed company by establishing the condition of the heating network under its immediate responsibility for covering, in accordance with the duty of care obligations of the Code of Obligations and the rules for acceptance of the work according to the SIA 118 standard. All documents must be filed in such a way that a tradesperson intervening several months after drying can unambiguously identify the concealed layouts.

  • Metric photographic sheets: orthogonal photographs with a graduated scale placed on the floor, incorporating door frames or raw masonry corners as invariant zero points.
  • Location plan for control and expansion joints: precise indication of clean screed cuts and the layout of decoupling profiles.
  • Diagram of sleeve crossings: identification of insulated pipes crossing the movement joints of the substrate.
  • Survey of actual thicknesses: recording book for laser levelling rods distributed over the entire surface.
  • Drilling instruction sheet: explicit instructions given to site management prohibiting the use of heavy percussion tools and defining limit depths.

Rigorous archiving of this file within the screed company serves as a means of proof in the event of a post-delivery dispute. If a hydraulic leak occurs following the installation of interior equipment, comparing the damage point with the photographic sheet makes it immediately possible to establish whether the contractor drilled outside the indicated tolerances or without consulting the network layout.

Disputes, accidental perforation and use of the as-built documentation

The accidental piercing of a heating pipe by the skirting board installer, the door stop installer or the joiner fitting out furniture constitutes the classic finishing work claim. When water under pressure gushes out or the pressure drop reveals a hidden perforation, the immediate shut-off of the water circulation is required. The site management then systematically requests the supporting documents to determine the technical and financial responsibilities for the damage.

The screed layer disclaims liability as soon as they produce the complete file countersigned upon delivery of the work. This file demonstrates the conformity of the cover thickness above the upper generators of the pipes and recalls the permissible drilling depth transmitted in writing. If the drilling exceeded the stipulated residual clearance or occurred directly plumb with a passage line indicated on the metric photographs, the fault lies with the tradesperson who perforated the floor without consulting the as-built file.

  1. Immediate joint inspection recordLocate the precise impact point, record the tool used, measure the actual depth of the drill bit and record the dimension in relation to the finished walls with the site management.
  2. Comparison with metric imagerySuperimpose the measurements of the incident onto the photographs of the heating coil taken before pouring and onto the control joint plan to identify the damaged circuit.
  3. Surgical opening and repairClear the screed using a light breaker hammer without striking neighbouring coils, have the heating installer crimp a certified sleeve, then rebuild the cover with a shrinkage-compensated mortar.

The formal transmission of the as-built documentation to the client via the acceptance report according to the SIA 118 standard closes the risk phase for the screed layer. It transfers to the site management the obligation to communicate these tolerances to subsequent trades.

Frequently asked questions

Who is responsible if a tradesperson drills into a pipe even though the cover dimension was respected?

Liability lies with the company carrying out the drilling. The as-built file handed over to the site management specifies the maximum permissible clearance, generally limited to twenty millimetres below the surface. If the tradesperson drilled beyond this tolerance or without consulting the heating coil plan handed over to the client according to the SIA 118 standard, the screed layer and the heating installer are entirely cleared of liability.

How to properly repair a screed after crimping a pierced pipe?

Following the heating installer's intervention and successful pressure test, the excavation must be thoroughly dusted. A sanded epoxy bonding primer is applied to the edges of the existing screed. Filling is carried out using a technical shrinkage-free mortar, compatible with underfloor heating according to the SIA 251 standard. The repaired area must dry completely before any reheating or installation of flooring.

What should be done if the heating installer's theoretical installation plan does not match the photos taken before pouring?

Reality on site always takes precedence over the theoretical execution plan. During pouring, the heating coil may have been diverted to bypass an obstacle or a joint. The metric photographs with a graduated rod are authentic. The screed layer immediately records these deviations on their as-built plan and has this document signed off by the site management before pouring the mortar.

What plugging/anchoring depth should be authorised for tradespeople intervening after the screed has been poured?

On fluid or traditional screed with incorporated heating according to the SIA 251 standard, the maximum safe clearance never exceeds fifteen to twenty millimetres, adhesive and tiling included. Beyond this, the risk of perforating a pipe or crushing the sleeve is certain. To fix heavy elements, it is imperative to use short chemical anchors or require structural bonding without drilling.

Texts and standards cited

  • norme SIA 118General conditions for the execution of construction work and acceptance of the work
  • norme SIA 251Floating screeds, execution rules, cover thicknesses and requirements on underfloor heating