🧱 CFC 281Cement or anhydrite screed: selection and executionChapter 9 of 10 in the section

Pumping on upper floors: pipe length, blockage, cleaning and truck access

Pumping fluid or traditional screed to upper floors leaves no room for logistical improvisation. This chapter guides you through positioning the truck mixer, securing delivery lines according to the Construction Work Ordinance (OTConst), anticipating hydraulic head losses, clearing a pressurized pipeline without risk of bodily injury, and disposing of rinsing residues in accordance with environmental regulations.

Key takeaways

  • Positioning the truck mixer requires a load-bearing roadway and signage compliant with the OTConst.
  • Every metre of vertical head creates a pressure drop equivalent to three horizontal metres.
  • Rigorous priming with grout prevents mortar de-aeration and the immediate formation of blockages.
  • Total manometric depressurisation is mandatory before opening any quick-release clamp.

Pump positioning, line setup and head management

Delivering fluid screed or cement mortar begins well before the mixer is started. The truck mixer-pump or worm pump requires a flat, compacted and secure parking area. A loaded mixer truck routinely exceeds a total weight of 32 to 40 tonnes: unpropped basements, hastily backfilled utility trenches or fragile curbs present a major risk of subsidence. In accordance with the principles of the Construction Work Ordinance, the working perimeter around the hopper and stabilizers must be rigorously demarcated with construction site barriers and appropriate road signs if the footprint encroaches on public land.

Calculating the delivery line directly determines the pump's discharge rate. Head losses depend on the internal nominal diameter of the pipes (generally DN50 or DN65 for liquid screeds), internal friction and the static head of the fluid. As a general rule, one metre of vertical rise is equivalent to three metres of horizontal piping in terms of hydraulic resistance, while a 90-degree bend generates a resistance equivalent to two straight linear metres.

Head loss equivalencies and practical pumping limits
Line configurationPhysical lengthHorizontal equivalenceRequired pressure
Horizontal straight line (DN50)100 m100 m20 to 35 bar depending on consistency
Façade rise 4th floor (DN50)15 vertical m45 equivalent m30 to 45 bar
Façade rise 8th floor (DN65)28 vertical m84 equivalent m45 to 60 bar
90° steel bend (per unit)0.5 m2.0 equivalent mLocal increase in friction

To limit pressure at the rotor outlet, prioritize a straight layout avoiding bottlenecks, loose loops and pinching through window openings. Conical diameter reducers must only be used immediately at the machine outlet, never at the end of the line, to avoid creating a compression point that causes instant aggregate blockage.

Line priming, dealing with blockages and residue treatment

Starting the pump into a dry line guarantees a mechanical blockage in less than twenty metres. The inner wall of the pipe absorbs the mix water from the leading mortar, causing screed de-aeration and the formation of a dry plug of sand or binder. To lubricate the entire circuit, pre-inject a specific priming grout or a very liquid pure cement slurry (two to three bags mixed in the hopper) immediately before pouring the cement or anhydrite screed. This guiding fluid coats the wall and stabilizes the flow pressure.

  1. Early detection of blockageContinuously monitor the pumping unit's pressure gauge. A sudden pressure rise above 40 bar accompanied by a drop in flow rate at the tripod signals an imminent blockage.
  2. Stop and reverse rotationImmediately stop mechanical feed. Engage reverse gear for a few turns to depressurize the pipe and push the compressed material back toward the hopper.
  3. Location and physical depressurisationLocate the blocked section by tapping the flexible hose with a rubber mallet (the sound becomes dull and solid). Before dismantling any quick-release lever coupling, check that the pressure gauge reads zero absolute bar to prevent violent jets of pressurized mortar.
  4. Mechanical clearance of the sectionDisconnect the affected section while protecting workers with safety glasses and full face shields. Manually empty the segregated material plug before reassembling the line.

At the end of pumping, cleaning is carried out by pushing a dense foam sponge ball, driven by clean water pumped through the system. Rinsing water management represents a strict environmental challenge. Cement-laden water has a very basic pH that can exceed 12, while anhydrite residues contain high concentrations of sulphates. It is strictly forbidden to discharge this water into storm drains or municipal sewers. Effluents must be collected at the bottom of the column in watertight settling tanks or geotextile filtering skips. After settling and clarification, the dried solid sludge is sent to an approved mineral recovery facility, and the neutralized water is directed to the wastewater network with the municipality's agreement.

Organization of delivery access, line anchoring and compliance according to the OTConst

Pumping fluid or traditional screed over long distances requires rigorous planning of the parking area. A truck mixer-pump or screw pump combined with a mixer truck involves heavy equipment whose mass can exceed thirty-two tonnes on three or four axles. Site access, platform load-bearing capacity and turning radius must be validated with site management before the first mix. The subsidence of a stabilization outrigger or a stuck truck on an evacuation route paralyzes the logistics chain, leaving the mortar to set in the pipes.

The Construction Work Ordinance strictly regulates traffic and work near transport machinery. Delivery hoses must never obstruct emergency access routes or cross pedestrian pathways without stable, crossable pedestrian bridges. On façades as well as in stairwells, the weight of a loaded vertical column imposes considerable mechanical forces: a pipe filled with mortar weighs approximately fifteen kilogrammes per linear metre for an internal diameter of sixty-five millimetres. Each floor crossed increases the downward gravitational thrust and raises the manometric pressure required at the rotor level.

Delivery constraints according to the pumping line configuration
Line configurationEstimated pressure forceMain site riskPreventive installation measure
Horizontal line 100 m on the ground15 to 25 barCrushing under machinery wheels, water hammerHeavy bridging ramps, straight layout without kinks
Rising column 25 m (7th floor)30 to 45 barTraction on couplings, pipe bucklingClamps on load-bearing structure at each level
Mixed façade with 3 90° bends35 to 55 barSegregation in bends, abrasive wearLarge-radius steel bends, textile retaining slings
Downward line in basement10 to 20 barMortar downflow, formation of air pocketsBack-pressure valve or restriction at discharge

Line rinsing, material recovery and disposal of contaminated water

As soon as pouring stops, the mortar still present in the piping must be flushed out without delay to prevent the irreversible setting of the resin or binder. Over one hundred metres of pipe, the trapped volume represents a significant fraction of the order. Two expulsion options exist: water pushing or compressed air pushing. Compressed air presents extreme danger: the elasticity of the air stores energy capable of turning the cleaning ball into a deadly projectile at the pipe exit. Water remains the recommended method to control the continuous evacuation of the paste plug.

  1. Final drainage and separator installationStop pumping at the signal from the applicator on the upper floor. Disconnect the pouring lance, insert a high-density water-soaked foam ball into the line head, and lock a secure receiving basket at the outlet.
  2. Hydraulic line pushingInject clean water at a regulated flow rate from the machine at the base of the building. Check with the pressure gauge that the pressure does not exceed the pipe's operating limits while pushing the remaining high-grade mortar toward the pouring area.
  3. Ball interception and depressurisationWatch for the arrival of the ball in the collection basket. Immediately stop the water supply as soon as the first traces of cloudy liquid appear, open the air purge valve and unlock the unpressurized line.
  4. Evacuation of pasty residuesDirect the last litres of washed-out mortar into a watertight construction site skip reserved for inert mineral residues, prohibiting any dispersion on bare ground.

Good logistical management always provides a retention basin of at least five hundred litres at the foot of the mixer to collect water from washing the hopper, mixer and short pipes. Residual additives, plasticizers and accelerators contained in the slurry must not enter open soils. Sorting and disposal of flushing sludge falls under the executing company's duty of cleanliness, recorded in the operations logbook before final equipment withdrawal.

Emergency procedure for major blockage and residue management

When the pump pressure gauge shoots up and flow stops at the pouring tripod, the logistics chain switches to high alert. In an upper-floor pumping setup with around one hundred metres of piping, an unresolved blockage in less than twenty minutes causes the binder to set inside the hoses and condemns the entire batch waiting in the truck mixer. Managing this crisis on site requires an immediate shutdown protocol to secure equipment, protect workers in accordance with the Construction Work Ordinance, and dispose of residues according to Swiss environmental standards.

  1. Depressurisation and cycle reversalCut injection and engage pump reverse gear to relieve overpressure in the circuit. Carefully monitor the pressure gauge until zero hydraulic pressure is reached. Never unlock a lever coupling under stress: water hammer and laitance splashes present a severe bodily hazard to operators stationed along the column.
  2. Acoustic sounding and removal of the clogged sectionMethodically sound the line with a rubber mallet to locate the aggregate agglomerate separated from its mix water. Once the area is located, lay down waterproof tarpaulins to protect walkways, loosen the safety clamps and manually evacuate the compacted blockage into a watertight skip or outside.
  3. Sponge ball push and residue collectionInsert the sponge cleaning ball into the upstream coupling and push it slowly with water toward the outlet equipped with a regulated catch basket. Collect all milky effluents and purge sludge in a watertight settling tank. The waste ordinance strictly prohibits the disposal of these liquid sludges into storm or wastewater drains.

Frequently asked questions

How to secure the opening of a pipe coupling during a blockage?

Before touching any coupling clamp, engage the pump reversal and check that the discharge pressure gauge reads zero bar. Systematically wrap the joint with a tarpaulin or thick geotextile when manually unlocking the cams to contain any potential projection of residual grout. Wear a helmet with an integrated visor and protective gloves complying with OTConst safety requirements to prevent any skin or eye contact with the alkaline binder.

What happens to the batch in the mixer truck if the line remains blocked for more than half an hour?

As soon as pouring stops exceed thirty minutes, the stiffening of the cement or anhydrite paste compromises the fluidity required for placement. The truck mixer driver must keep the drum rotating slowly without adding water, which would destroy final strengths. If the line cannot be quickly restored, refuse unloading and send the mixer truck back to the plant for recycling or disposal at an approved treatment area.

How to dispose of contaminated rinsing water without breaking the law?

Rinsing milk from fluid mortars has a strongly basic pH and contains suspended solids harmful to the environment. This sludge must be directed to a watertight sedimentation basin or filtering skip installed on the site. Once the particles have settled, the clarified water is neutralized if necessary before discharge, while the dehydrated solid residues are sorted and disposed of in accordance with waste ordinance requirements.

Why does the vertical rising column promote separation and blockages?

In a vertical pipe, the mortar column experiences reverse gravitational thrust during pumping interruptions. This local pressure drop promotes rapid sedimentation of heavy grains and separation of the lubricating slurry film. To prevent this critical de-priming, install a shut-off valve or retention bend at the foot of the rising column to prevent paste reflux between pouring phases.

Texts and standards cited

  • OTConstOccupational safety and health protection for workers in construction work
  • OLEDRegulations on sorting construction waste and disposing of polluting sludge