🧱 CFC 281Drying, heat-up and moisture measurementsChapter 4 of 10 in the section

How long: thickness, binder, room ventilation and misleading rule of thumb

This chapter teaches you how to rigorously assess the drying time of a liquid or traditional screed. You will learn why the formula of one week per centimetre misleads construction sites beyond four centimetres, how the choice of binder changes evaporation, and which aeration parameters guarantee the evacuation of residual water without degrading the mineral matrix.

Key takeaways

  • The rule of one week per centimetre becomes completely false as soon as the thickness exceeds four centimetres.
  • The evaporation of free water follows a quadratic law linked to the internal diffusion path of the mortar.
  • The nature of the binder determines the chemically combined water proportion and the residual capillary porosity.
  • Controlled cross-ventilation directly conditions the moisture gradient between the screed and the indoor environment.

The empirical rule of one week per centimetre versus physical reality

On construction sites in French-speaking Switzerland, the adage attributing seven days of drying per centimetre of thickness remains stubborn among many planners. This simplification works acceptably for leveling screeds or thin layers up to 30 or 40 millimetres under a temperate indoor climate. Beyond this dimension, the transport of excess water no longer follows a simple arithmetic progression. The interstitial water located at the core of the section must cross an increasingly dense and tortuous capillary network to reach the exchange surface.

Drying kinetics actually respond to a quadratic function of mass transfer: the time required to evacuate free water is proportional to the square of the structure's thickness. Thus, doubling the thickness of a screed does not double its drying time, but quadruples it under strictly identical thermo-hygrometric conditions. A 70-millimetre cement screed laid on acoustic insulation will not take seven weeks, but commonly twelve to sixteen weeks to reach its equilibrium point without forced thermal input.

Indicative natural evaporation times according to thickness under standard conditions (20 °C and 50% RH)
Nominal thicknessEmpirical rule estimateObserved physical time (cement)Observed physical time (calcium sulphate)
40 mm4 weeks4 to 6 weeks3 to 5 weeks
50 mm5 weeks7 to 10 weeks5 to 8 weeks
60 mm6 weeks11 to 15 weeks8 to 12 weeks
70 mm7 weeks16 to 22 weeks12 to 18 weeks
Quadratic diffusion law
Physical principle governing fluid transfer through an unsaturated porous medium, where the travel time of a water molecule increases with the square of the distance separating the bottom of the screed from the free surface.

Binders, capillary kinetics and management of air renewal

SIA 251 states that a screed's suitability to receive its floor covering depends exclusively on its measured residual moisture content, and under no circumstances on a theoretical calendar. Two parameters determine this deadline: the mineral binder formulation and the ambient air evacuation potential. Between a Portland cement screed and a calcium sulphate (anhydrite) liquid screed, water retention and release mechanisms differ fundamentally.

  • Traditional cement screed: a significant fraction of the mixing water is used for silicate hydration, with the surplus having to extract itself through a fine capillary network that slows down deep migration.
  • Calcium sulphate screed: rapid crystallization into gypsum consumes a defined stoichiometric share, leaving an open and permeable porous structure that accelerates evacuation as soon as heating is commissioned.
  • Ternary binder or quick-drying screed: the incorporation of aluminous cements chemically traps a large part of the free water in the form of ettringite, reducing evaporable residual water to a minimal fraction.

Stagnant air in direct contact with the floor immediately saturates with moisture, creating a micro boundary layer that completely interrupts any vapour transfer. To maintain the vapour pressure gradient essential for drying, the room must benefit from regular air renewal without creating destructive turbulence. During the first 48 hours for cement, and 24 hours for calcium sulphate, any draft is prohibited to protect the screed against premature surface desiccation and plastic shrinkage cracking.

As soon as the initial curing period ends, the thermal and aeraulic protocol takes over. Pulsed ventilation, consisting of opening transom windows or opposite windows wide three times a day for twenty minutes, surpasses permanent transom opening in winter. It replaces water-laden warm air with drier cold air without cooling the mass of the structural work. The use of condensation or adsorption dehumidifiers becomes essential in windowless or underground rooms, otherwise drying will be blocked indefinitely due to ambient saturation.

Non-linearity beyond 40 millimetres: time drift according to the binder

On site, the most frequent planning error consists in extrapolating the drying time of a thin screed to a heavy-section structure. Below 40 millimetres, the evacuation of free water still responds to a relatively direct moisture gradient between the core of the screed and the exchange surface. Beyond this critical threshold, kinetics become strictly non-linear. The capillary path that residual water must travel to reach the surface lengthens, while the porous structure densifies as hydration progresses. Water no longer evaporates at a proportional rate: the time required for evacuation increases quadratically with thickness.

This non-linearity varies considerably from one binder to another. Calcium sulphate (anhydrite) screed has a continuous and open porous structure, promoting a more regular thermal and hydric progression. Conversely, it exhibits extreme sensitivity to water: any trapped moisture within a thickness of 60 to 70 millimetres deteriorates mechanical strength if drying stagnates. For a traditional cement screed, the formation of a dense hydrate mat on the surface during the first few weeks drastically reduces vapour permeability. Internal moisture is held back in the bottom last centimetres, extending the waiting period by months if no heating or dehumidification is initiated.

Orders of magnitude for natural drying times according to binder and thickness (standardised environment at 20 °C and 50% relative humidity)
Screed mortar typeNominal thicknessBasic estimate (rule of thumb)Actual duration observed in natural dryingSchedule time deviation
Conventional cement40 mm4 weeks4 to 6 weeksLow divergence
Conventional cement60 mm6 weeks10 to 14 weeksDelay greater than 100 %
Conventional cement80 mm8 weeks18 to 26 weeksDelay greater than 200 %
Fluid calcium sulphate40 mm4 weeks3 to 5 weeksGlobal equivalence
Fluid calcium sulphate60 mm6 weeks8 to 11 weeksSignificant delay without heating

Site aeraulics: organising air renewal without degrading the structure

Water evaporation speed does not depend solely on thickness and the chemical nature of the binder. It is governed by the partial water vapour pressure prevailing flush with the mortar. If the room air reaches a saturation state greater than 70% relative humidity, diffusion stops almost completely, regardless of internal porosity. Conversely, brutal air circulation during the initial hydration phase causes rapid surface desiccation, generating premature differential shrinkage and irreversible curling of the edges.

  • Closed maturation phase (days 1 to 3 for cement, days 1 to 2 for calcium sulphate): rooms kept closed, without cross-drafts, to preserve the water necessary for crystalline reactions and avoid early cracking.
  • Active aeration phase (from the 4th day): timed impulse opening or mechanical ventilation to lower indoor air saturation, promoting capillary transfer.
  • Controlled dehumidification phase : introduction of closed-circuit condensation absorbers if the outdoor atmosphere displays an unfavourable dew point (autumn fog or continuous rain).

To meet SIA 251 requirements on substrate maturity prior to installation, air renewal must be measured and permanent. In enclosed construction sites equipped with airtight joinery without a functional mechanical ventilation system, evaporation stops spontaneously after a few days for lack of evacuation of the saturated volume. The trapped humidity then rises to 85-90% in the interior volume. In this context, a 50-millimetre cement screed will take more than twenty weeks to drop below the acceptance threshold without appropriate mechanical intervention.

Managing drying drifts and site arbitration

When the installation deadline approaches and carbide bomb measurements reveal residual moisture outside tolerances, the reflex of invoking a simple calendar delay is not enough. Unanticipated excess thickness or insufficient air renewal block deep evaporation. According to SIA 251, the screed layer must track substrate evolution and document the room's hygrometric state. If the air remains saturated, the water imprisoned at the core of the matrix can no longer migrate to the surface.

As soon as kinetic drift is observed on a fluid calcium sulphate screed or a traditional mortar, the site manager and construction management must be formally alerted in writing, in accordance with the duty to notify recalled in SIA 118 and the Code of Obligations. The screed layer's liability stops at the delivery of work conforming to trade rules; they cannot validate floor covering installation until the normative threshold is reached.

  • Systematically measure air temperature and dew point before any mechanical drying decision.
  • Log contradictory hygrometric readings in the site logbook to prove the absence of natural ventilation.
  • Demand the maintenance of regular cross-ventilation if dehumidification equipment is not provided by the client.
  • Formally refuse in writing the authorisation to cover the floor as long as the calcium carbide test does not conform.

Frequently asked questions

Why does the rule of one week per centimetre fail on 70 millimetres?

Water diffusion in the porous network obeys quadratic kinetics linked to thickness. Up to 40 millimetres, drying takes place almost linearly. Beyond that, the capillary path lengthens considerably and slows down vapour evacuation. For 70 millimetres of cement mortar without specific admixture, the actual time easily reaches twelve to sixteen weeks instead of the seven weeks predicted by this erroneous empirical estimate.

What is the difference in drying between cement screed and calcium sulphate screed?

Cement screed consumes a fraction of its water through chemical hydration, but retains slow evaporation and a high risk of hydraulic shrinkage. Calcium sulphate screed requires the evacuation of virtually all its mixing water by evaporation. Although its structure allows more uniform drying without curling, its residual moisture threshold required for watertight installation is much stricter according to SIA 251.

How to effectively ventilate a floor without damaging the fresh screed?

During the first few days, the room must be kept closed to prevent premature desiccation of the binder and plastic cracking. Once setting is complete, cross-ventilation must be established through shocks of fifteen to twenty minutes several times a day. Windows left in permanent transom position should be avoided as they create localized draft zones, generating asymmetrical drying and mechanical stresses.

Who bears the financial cost of installing dehumidifiers in case of delay?

If the delay stems from a screed thickness greater than ordered to make up for structural work level errors, or from non-compliant site climate maintained by the client, technical drying constitutes an additional service at their expense. The screed layer disclaims liability by notifying in writing the impossibility of natural drying under the ambient conditions observed on site.

Texts and standards cited

  • SIA 251Floating screeds and insulating underlays in buildings - Execution prescriptions and acceptance criteria.
  • SIA 118General conditions for the execution of construction work - Duty to notify and management of notices of defects.