Key takeaways
- SIA 251 requires the pipes to be kept under pressure during the pouring of the screed.
- The initial pressure gauge reading is carried out jointly with the installer before starting the pump.
- A pressure drop during execution immediately indicates an accidental perforation of the network.
- The joint signature of the joint inspection record before and after the works formally establishes responsibilities.
Manifold check and pressure reading before the first batch
Arriving at the slab before pouring a floating screed over underfloor heating requires a systematic stop in front of the distribution cabinet. The screed layer must never modify the distributor valves, as filling, air bleeding and hydraulic testing fall exclusively within the prerogatives of the heating installer. Conversely, the screed team leader assumes liability as soon as the pumping nozzle pours the mortar. If a cross-linked polyethylene or multilayer pipe is damaged by a tripod, crushed by repeated wheelbarrow traffic or pinched by a screeding rule without pressure monitoring, the fluid will not always escape immediately if the circuit is empty, masking the rupture until final water-filling.
Visual inspection is not enough: the presence of water in the loops offers no guarantee if the network is not under a measurable load. The dial of the pressure gauge connected to the manifold must indicate a stable value, generally between 4 and 6 bar according to the technical guidelines provided by the site management and the heating engineer. The team leader reads the needle to the nearest tenth of a bar, takes a clear photograph of the dial showing the date and the labelling of the manifold corresponding to the room, then records this value on the substrate transfer document.
- Verification of the presence of a calibrated and legible pressure gauge on each distributor concerned by the day's pour.
- Joint static pressure reading with the representative of the building services engineering company.
- Check that the air has been completely bled to prevent false pressure balances in the event of thermal variation.
- Immediate signature of the inspection sheet before connecting the screed mixer discharge hoses.
Continuous monitoring during pouring and end-of-installation report
During pouring, whether it is self-levelling anhydrite mortar or a traditional cement screed pulled with a rule, operators are constantly moving on the mesh or stapled insulation panels. The risk of perforating a coil by a metal peg angle, a displaced reinforcement framework or a protruding nail is permanent. The continuous maintenance of the test pressure during execution acts as an instant warning: any drop in load on the pressure gauge signals a leak that it is still possible to localise before complete immersion under the embedding mass.
- Appointment of a watcherA worker from the team checks the pressure gauge at regular intervals, particularly each time the discharge hoses or distribution boom are moved on the construction site.
- Reaction in the event of a pressure dropImmediate stop of pumping. Water escaping under pressure creates bubbling visible through the fresh screed, making it possible to identify the precise location of the perforated pipe without demolishing sixty square metres of hardened material.
- Intervention of the heating engineerThe repairer from the competent trade sleeves the damaged area in accordance with their professional rules, re-establishes the hydraulic test and authorises the resumption of pouring in writing.
- Final reading after smoothingAs soon as the smoothed or trowelled surface is completed, a second pressure gauge reading is carried out jointly to certify that the work is sealed without damage to the embedded installations.
The joint report finalises the step. This form, drawn up with reference to Swiss building standards of workmanship and the general conditions of the SIA 118 standard, releases the screed company from any liability relating to a subsequent leak if the final pressure is strictly equal to the initial value. In the absence of the installer at the end of the day, the site manager is asked to countersign the reading with timestamped photographic proof.
| Observed situation | Consequence on the construction site | Allocation of costs |
|---|---|---|
| Zero pressure before intervention | Formal refusal to pour the screed | Delay attributable to the heating engineer |
| Pressure drop during pumping | Immediate stop and identification of the leak | Repair costs by the screed layer |
| Stable pressure before and after pouring | Joint signature of the final report | Transfer of custody in accordance with the rules |
Pressure drop during work: immediate stop and demarcation of the area
During the placement of a fluid screed or the pulling of a traditional cement mortar screed, the pressure gauge fixed to the manifold must never be left out of sight. The presence of a worker or the team leader in the immediate vicinity of the manifold makes it possible to detect the slightest depressurization. A flexing needle indicates a clean perforation by a tool, crushing under the passage of a wheelbarrow or the tearing off of a fixing clip having sheared the pipe sheath. Facing this situation, the interruption of pumping must be ordered on the spot: pouring over a damaged pipe turns a twenty-minute local repair into a major claim requiring the demolition of dozens of square metres of hardened screed.
- Stopping the pour and securing the equipmentStop the spraying or pouring of the mortar. Block traffic on the underfloor heating and prohibit any movement of rules, guide hoses or level tripods.
- Visual marking of the progression frontImmediately demarcate with a line or visual markers the exact front of the screed at the precise moment when the pressure drop was observed on the pressure gauge.
- Formal notice to the heating engineer (CFC 241)Alert the person in charge of the heating installations as well as the site management. Only the heating fitter is qualified and authorized to bleed the circuit, cut the concerned loop and sleeve the damaged pipe.
- Check before resuming operationsThe screed can only be resumed after repair validated by a new documented, stabilized and recorded pressure test on the construction site dashboard.
The boundary of services must remain strict. Under no circumstances should the screed layer attempt to repair a broken synthetic or multilayer pipe themselves, even superficially. The use of a fitting not approved by the system under technical approval will engage the full liability of the screed company for all subsequent water damage. The intervention falls exclusively within the remit of the sanitary or heating installer, who applies the crimp sleeves in accordance with the recommendations of the underfloor heating manufacturer.
The jointly signed joint inspection record: legal locking and end of embedding
The SIA 251 standard rigorously prescribes that embedded heating pipes must be maintained under water pressure or air pressure for the entire duration of screed making and until its initial hardening. This provision guarantees the geometric rigidity of the pipes during levelling and allows the immediate detection of a leak. However, physical monitoring only protects the company if it materializes as a written joint inspection record. This document constitutes the absolute legal boundary defining the state of the networks before the arrival of the mixer and after the last smoothing pass.
| Process step | Technical action | Required participants | Documentary validation |
|---|---|---|---|
| Before starting the pour | Visual reading of the pressure on the general pressure gauge and on each floor manifold | Screed foreman and heating installer (or site management) | Signed site opening sheet with transfer of the exact pressure in bar |
| During embedding | Continuous control of the needle during the installation of bridging, pulling and the passage of rules | Screed team leader | Mention in the company's internal work log |
| End of screed placement | Joint check of the final pressure once the surface is smoothed or de-aerated | Screed foreman and representative of the client or heating engineer | Countersignature of the final pouring joint inspection record |
| Setting phase (48 to 72 h) | Maintenance of pressure without operating the valves until sufficient hardening of the screed | Site management / Heating engineer | Transfer sheet for authorization of traffic on the structure |
The report must state with exactness the date, the precise time, the identification of the rooms concerned, the type of test fluid (water or air) as well as the manometric value read to the nearest millibar. If the site management or the heating engineer refuses to sign the record before the start of the first batch, the screed layer must suspend the pour and record their refusal by formal notification in the site log. Without this bilateral trace, the presumption of deterioration rests almost systematically on the screed layer in the event of a defect observed during thermal commissioning tests.
Management of incidents and disputes: stop protocol and responsibilities
When the pressure gauge needle flexes before the start of the work or if the sanitary and heating installer fails to appear to countersign the opening report, pouring must under no circumstances start. Embedding thermal coils without validated control shifts the entire responsibility for defects onto the screed company. In accordance with the requirements of the SIA 251 standard, mortar can only be applied to previously tested hydraulic circuits, maintained under continuous pressure during the entire pour. Ignoring this joint requirement exposes the tradesperson to bearing alone the cost of a leak discovered during heating-up.
- Interruption of pouring and securingStop the screed pump at the slightest pressure loss visible on the manifold pressure gauge. The team interrupts progress to demarcate the freshly pulled area and avoid burying a potentially defective section further.
- Joint summons on the construction siteNotify the site management and bring the heating installer to the foot of the work. The inspection of recent embedding areas must be carried out without delay, before the setting of the binder makes any manual clearance impracticable.
- Drafting a detailed joint noticeRecord on the report the pressures observed, the exact time of the pressure drop, the treated surface and technical reservations. This document must obligatorily be signed by the screed layer and the representative of the site management.
In the event of a persistent dispute or refusal to admit a pre-existing failure, the rules of the Code of Obligations relating to the duty to notify oblige the contractor to formally suspend their service. Without an initial and final reading initialed by both parties, the presumption of mechanical deterioration by beaters, metal rules or the path of discharge hoses will always weigh on the screed layer. This joint inspection record signed before and after pouring remains the sole legal guarantee protecting the company against heavy and unjustified repairs.
Frequently asked questions
Who must be present to read the pressure gauge before pouring?
The screed team leader and the heating fitter or the representative of the site management must jointly observe the value at the manifold. This shared reading certifies that the circuit is under pressure before the mortar touches the floor. The installer records the initial pressure on the follow-up sheet. Without their presence or prior written agreement, the screed layer suspends the start to avoid any subsequent shift of responsibility in the event of failure.
What minimum pressure value must the pressure gauge display during the work?
The test pressure is defined by the heating installer according to the manufacturer's recommendations and professional rules, generally between four and six bar for water. For the screed layer, the absolute value matters less than its perfect stability. The needle must not record any loss of load between the start of the first batch and final trowelling. A sudden drop betrays crushing, perforation or a dislodged connection under the screed.
What to do if the pressure gauge drops while the screed is half-pulled?
The team interrupts the pour and immediately notifies the site management and the heating engineer. The team leader demarcates the damp or freshly embedded area and takes photographs of the dial. The sanitary and heating installer must intervene without delay to locate the seepage and repair the pipe before the final setting of the binder. Pouring over a known pressure drop engages the direct responsibility of the screed company for aggravating the damage.
Can the screed layer reset a pressure gauge themselves or repressurise the circuit?
No. The underfloor heating network falls exclusively within the prerogatives of the heating installer (CFC 241). The screed mission is solely to embed the coils in accordance with the SIA 251 standard. Manipulating drain valves, bleeds or an external test pump engages the screed company outside its contractual scope. Any unauthorized repressurisation distorts the joint inspection record and deprives the screed layer of any means of defense in the event of a leak.
Texts and standards cited
- SIA 251Screeds in construction, installation conditions and embedding of heating pipes
- Code des obligationsGeneral rules of the service contract and duty to notify in the event of a defect compromising the work