🧱 CFC 281Substrate, underlays and decouplingChapter 10 of 10 in the section

After casting: ban on traffic, curing time, draughts and direct sunlight

As soon as casting is complete, the fresh screed is extremely vulnerable to mechanical and climatic damage. This chapter guides you on how to set up physical access blocking, formally notify site management of the bans on passage, and control the building's ventilation to prevent any premature drying out of the mortar.

Key takeaways

  • A boot print made during the setting process permanently ruins the surface flatness.
  • The formal notification sent to the other trades relieves the screed layer of sole responsibility.
  • Direct draughts cause harmful differential shrinkage and dusting of the mortar.
  • Light foot traffic requires strict compliance with the prescribed hardening times.

Block access and formally notify the periods when passage is banned

A safety boot print pressed into mortar six hours into its setting time remains engraved for the entire service life of the structure. Rectifying a local depression by sanding or spot patching creates a mechanical discontinuity that is incompatible with the subsequent installation of a bonded floor covering. According to standard SIA 251, the cast surface must be fully protected from all mechanical loads during the initial binder crystallization phase. This principle requires an impassable physical isolation system as soon as the screed pump departs.

The traffic ban cannot rely on a simple verbal instruction given on the landing. Inter-trade coordination requires a written protocol sent to the site management at least forty-eight hours before the work begins. This casting notice specifies the exact location of the treated rooms, the expected completion time of trowelling or running the screeding bar, and the precise date for reopening to pedestrians. In the event of intrusion despite the barriers, this document serves as contractual proof that the damage was caused by a third party.

  1. Distribution of the casting noticeSend the work schedule to the site management for general distribution on the construction site management platform.
  2. Physical obstruction of thresholdsPlace timber cross-members or rigid barriers in front of each access opening to the treated level as soon as the delivery hoses are cleared away.
  3. Installation of prohibition signageStaple standardized notices indicating the type of binder, the risk of damage, and the absolute ban on walking period.
  4. Pedestrian reopening reportCheck the surface hardness at the agreed time before formally approving the resumption of light service traffic.

Controlling the indoor environment: neutralizing draughts and direct radiation

The behaviour of a fresh screed depends directly on the humidity and speed of the ambient air. A passing draught causes accelerated evaporation of the mixing water at the surface, well before the cement or calcium sulphate hydration process is complete. This early drying leads to severe plastic shrinkage, manifested by surface map cracking, matrix dusting, and curling of bay corners due to the moisture gradient between the surface and the underside.

Standard SIA 251 prescribes maintaining a closed and temperate atmosphere during the first few days following installation. External windows and doors must remain closed to prevent any continuous airflow. Similarly, glazing exposed to direct solar radiation during the summer must be obscured using diffusing films or temporary tarpaulins. Direct and asymmetric heat input leads to localized temperature rises that irreparably weaken the binder's crystal lattice.

Eviction periods and ventilation regimes according to the screed binder
Screed typeTraffic banVentilation managementLoad traffic
Cement-based screed (CT)3 to 5 days period depending on temperatureOpenings kept closed for 7 days for curingHeavy loads forbidden before 21 to 28 days
Calcium sulphate screed (CA)24 to 48 hours periodTotal closure for 48 hours, then shock cross-ventilationHeavy loads allowed after complete drying

Initial maturation and setting kinetics: the risk of permanent damage

The period immediately following the screeding and trowelling of a floating screed determines the integrity of the surface structure for the entire service life of the structure. During the first few hours, the binder paste begins its crystallization without having acquired the mechanical cohesion necessary to take a point load. The intrusion of a worker or the movement of a trolley a few hours after installation does not just cause surface dirt: localized crushing shears the nascent crystal lattice, pushes the aggregates downwards and forces the pore water back up the sides of the footprint. This defect becomes completely irreparable without a smoothing compound or local repair, because the locally compacted mortar has a different density and modulus of elasticity from the rest of the bay.

Depending on the type of binder specified and the thermo-hygrometric conditions of the building, the hardening kinetics vary significantly. A calcium sulphate flowing screed reacts differently from a traditional cement mortar leveled with a straightedge. However, simultaneous exposure to uncontrolled draughts worsens the phenomenon: premature evaporation of the mixing water at the surface causes differential plastic shrinkage between the surface crust and the core of the screed, leading to widespread map cracking or early edge curling, even before the minimum flexural tensile strength prescribed by standard SIA 251 is reached.

Indicative periods for non-accessibility and resumption of activity according to the binder
Type of binderAbsolute ban on walkingService foot trafficStorage of distributed light equipment
Traditional cement screed (CT)0 to 72 hoursFrom the 4th day (marking out)After 7 days minimum
Fast-drying cement screed0 to 24 hoursFrom 24 to 48 hoursAfter 3 to 5 days according to technical data sheet
Calcium sulphate flowing screed (CA)0 to 48 hoursFrom 48 hoursAfter 5 to 7 days

Organization of physical barriers and information protocol for trades

To prevent accidental damage by other finishing work trades (electricians, plumbing installers, plasterers-painters), the ban on entering cannot rely on a simple verbal instruction given on the landing. The screed layer must formalize the closure with a rigid physical barrier at each access point: crossed warning tapes at door openings, temporary timber laths fixed in the reveals without piercing the peripheral acoustic insulation, and explicit signs bearing the precise casting date and the exact reopening time.

  • Installation of large-format multilingual posters on site doors, landing doors and stairwells explicitly mentioning the ban on access.
  • Systematic written notification to the site management (screed delivery note, site report or time-stamped email) on the very day of casting.
  • Formal notification of the conditions for keeping windows closed to prevent devastating draughts and flash drying.
  • Reminder of permissible loads upon resumption: absolute ban on placing pallets of plasterboard or heavy toolboxes without load-distribution boarding.

Contractual site management involves establishing proof that instructions have been communicated. By transmitting the practicability schedule to the site management, the screed layer formally transfers responsibility for safeguarding the work. If a third party forces a physical barrier or crosses a boundary marker after written notification, the joint inspection record drawn up immediately will make it possible to attribute repair or surfacing costs to the offending company, releasing the screed applicator from the warranty for appearance defects or cracking caused by premature overloading.

Management of intrusion claims and repair protocols

When a trade enters fresh mortar despite the barriers and notified ban, the boot print permanently alters the material's structure. A few hours into the setting process, the pressure breaks the aggregate skeleton in the middle of crystallization, locally reduces the effective thickness, and creates a hard spot likely to crack during subsequent shrinkage. Such damage can never be erased by simple surface trowelling. The screed layer must record the damage on the same day and refuse any summary intervention that would mask the issue without restoring the expected strength.

  1. Joint inspection record and evidence gatheringSummon the site management to draw up a joint inspection report. Photograph the footprints with a millimetric ruler, note the footprints allowing the offending trade to be identified, and verify the presence of broken or moved physical barriers.
  2. Notice of reservation in accordance with standard SIA 118Issue a formal notice recording the undue intrusion. This letter releases the screed layer from responsibility regarding subsequent mechanical, acoustic or adhesion consequences, while suspending the delivery period for the damaged area.
  3. Diagnosis after hardening in accordance with standard SIA 251Wait for the minimum period prescribed by standard SIA 251 before carrying out mechanical testing. Check the edge hardness with a sclerometer and test the adhesion of the matrix with a hammer to rule out any risk of internal debonding.

If the intrusion or an uncontrolled draught has caused premature desiccation, the remedial measures depend on the surface diagnosis. For surface damage without deep debonding, diamond grinding makes it possible to restore a horizontal plane conforming to execution tolerances. In the case of deep footprints that have reached the reinforcement or heating pipes, straight-line sawing of the damaged area, removal of the unstructured mortar, and casting of a new bay with a bonding resin are mandatory at the exclusive expense of the author of the defect.

Frequently asked questions

What is the minimum period before authorizing other trades to walk on a cement screed?

According to standard SIA 251, a traditional floating cement screed must not receive any foot traffic during the first three days following its installation. This incompressible rest time ensures the initial formation of hydrates without microcracking the paste. Light service traffic may be tolerated after this period, while pallet truck rolling or the storage of pallets from other companies remains prohibited for at least twenty-eight days.

Why are draughts so destructive during the first forty-eight hours?

An airflow accelerates the evaporation of mixing water at the surface well before complete hydration of the binder. This phenomenon causes severe plastic shrinkage, generating a tight network of microcracks or map cracking as well as a loss of cohesion in the surface film. In addition, the difference in drying speed between the top and the base of the screed induces significant curling stresses, which can permanently lift the corners of each panel.

How can access bans be effectively notified to other companies on the site?

Information must be transmitted in writing during site coordination meetings and recorded in the weekly minutes several days before the work. Upon completion of casting, the screed layer sends a formal confirmation to the site management specifying the exact dates for reopening the premises. On site, physically blocking doors with chains, screwed laths and explicit warning signs makes the ban clear to all workers present on site.

Can a deep footprint be repaired without redoing the entire bay?

Repair depends on the extent of the damage and the type of screed. If the footprint remains localized without debonding the coating of the heating pipes, it is possible to rout out the depression, apply a sanded epoxy bonding primer, and then fill it with non-shrink micro-concrete. On the other hand, if the sole has perforated the acoustic insulation or unstructured the reinforcing mesh, complete cutting of the panel between expansion joints remains the only accepted technical solution.

Texts and standards cited

  • SIA 251Floating screeds inside buildings
  • norme SIA 118General conditions for the execution of construction work