🧱 CFC 281Drying, heat-up and moisture measurementsChapter 3 of 10 in the section

The protocol: step-by-step rise, maximum step, cooling down and signed logbook

This chapter details the rigorous management of the thermal protocol on floating screeds prior to flooring installation. You will learn how to specify the heating steps, set the maximum permissible temperature according to the binder type, coordinate the controlled cooling down, and demand the flawless maintenance of the heating logbook countersigned by the construction site stakeholders.

Key takeaways

  • Heating up releases mechanical stresses before any moisture extraction of the binder is attempted.
  • Compliance with initial curing times is strictly required before the first thermal start-up.
  • Daily progression through moderate steps protects the pipe embedding against premature cracking.
  • The signed heating logbook formally releases the screed layer's liability for the subsequent work.

Orchestrating thermal steps without confusing stabilisation with forced drying

On a floating screed incorporating underfloor heating, the initial heating-up performs a very specific structural function: it causes the thermal expansion of the mortar to reveal and release internal shrinkage stresses before the floor finish is applied. Too often wrongly perceived as an accelerated drying operation driven by tight schedules, this temperature increase must under no circumstances be rushed to remove excess water. Early or brutal thermal stress impairs binder hydration, weakens surface mechanical strength, and generates destructive micro-cracks around the embedding pipes.

The cycle must obligatorily begin at low temperature with a flow water temperature set to 25 °C, or a setpoint matched to the ambient temperature if lower, maintained for three full days. The load increase is then carried out in regular increments of 5 °C per 24 hours up to the maximum operating temperature prescribed by the site management, without ever exceeding the material's permissible ceiling. This maximum temperature must be maintained continuously for several days to stabilise the movements of the substrate, before starting a symmetrical cooling phase in descending steps of 5 °C per day.

Indicative heating-up steps according to screed type (SIA 251 standard)
Heating parameterCement screed (CT)Calcium sulphate screed (CA)
Waiting time before heating21 days minimum7 days minimum
Initial flow temperature20 °C to 25 °C (3 days)20 °C to 25 °C (3 days)
Daily increments+5 °C every 24 h+5 °C every 24 h
Maximum step temperature45 °C to 50 °C at flow45 °C to 50 °C at flow
Holding at maximum step4 consecutive days minimum4 consecutive days minimum
Cooling steps-5 °C every 24 h-5 °C every 24 h

Recording operating data in the official heating-up logbook

Screed compliance does not rely solely on execution actions on the construction site: it requires irrefutable documentary evidence. The heating-up logbook is the cornerstone of the as-built record file for the screed layer. This document certifies that the work has undergone the thermomechanical test without defects and clearly defines the responsibilities between the heating engineer, who adjusts the control system, the site management, which coordinates the trades, and the future floor covering installers. The absence of this document invalidates the works warranty in the event of subsequent lifting or cracking.

  1. Initial record and parameter loggingRecord the screed pouring date, the exact type of binder, the average thicknesses observed, and the initial filling date of the heating pipe network on the official document.
  2. Daily temperature recordingNote daily the flow and return temperatures at the manifold, the room ambient temperature, and the window opening status to ensure continuous cross-ventilation without direct drafts.
  3. Visual inspection of the work at maximum stepMethodically inspect expansion joints, protruding corners, and doorway thresholds during the peak temperature phase to record the absence of random cracking or spalling.
  4. Joint inspection record closure and signaturesHave the logbook countersigned by the heating installer for compliance with water temperature guidelines, by the site management to certify monitoring, and keep a certified copy for the execution file.

Throughout the duration of the protocol, room ventilation must be strictly controlled. Moisture-laden air must be allowed to escape through controlled room ventilation, strictly avoiding wide-open windows that would create heterogeneous cold zones on the same heating loop. As soon as the cooling phase is completed, the underfloor heating is returned to its operating temperature or switched off according to climatic requirements to allow residual moisture measurements to be carried out using the carbide bomb method.

Elevation steps, maximum step, and regulation of thermal cooling

The thermal protocol defined by the SIA 251 standard requires progressive stressing of the screed structure. This is by no means an accelerated drying phase through overheating, but rather putting the structure under controlled mechanical stress. Internal stresses caused by the expansion of the hydraulic coils must be released in an orderly manner through expansion and movement joints. Any premature thermal increase, prior to sufficient hydration of the binder matrix, irreparably destroys the crystal lattice and lowers the flexural tensile strength of the mortar.

Indicative parameters of the thermal cycle according to binder type in accordance with the SIA 251 standard
Control parameterCement floating screedCalcium sulphate screed
Minimum age before heating starts21 full days (28 days recommended)7 days after pouring
Temperature increase ramp+5 °C per 24 h period+5 °C per 24 h period
Maximum setpoint step45 °C to 50 °C for 4 days minimum45 °C to 50 °C for 3 to 5 days
Thermal cooling ramp-5 °C per 24 h period-5 °C per 24 h period
Ambient ventilation managementModerate ventilation without draftsRegular and brief cross-ventilation

The maximum step temperature corresponds to the design temperature of the floor heating system, generally between 45 °C and 50 °C at the manifold flow, without exceeding the permissible limit for the binder used. Maintaining this step for several consecutive days ensures complete thermal expansion of the screed panel and reveals any incipient cracks under stress. The cooling phase requires the same metrological rigor: lowering the setpoint by more than 5 °C per day exposes the surface to sudden contraction relative to the core of the slab, generating severe cupping phenomena or shear along edges.

Joint inspection record closure of the heating-up logbook and transition to CM measurement

The heating-up logbook constitutes the main contractual document certifying that the floating screed has completed its test cycles without structural damage. The SIA 251 standard makes the acceptance of the substrate and the authorization of covering work conditional upon the presentation of this exhaustive daily record. Each trade acts within the strict limits of its responsibilities: the CFC 241 heating installer manages the regulation of the thermal source and records the flow and return temperatures read at the manifold, while the CFC 281 screed layer checks the mechanical behavior of the mortar, the absence of spalling on joints, and the effective play of edge insulation strips.

  1. Daily time-stamped recordNote every morning the programmed flow temperature, the actual flow temperature measured with a contact thermometer on the manifold, as well as the ambient air temperature and humidity.
  2. Joint inspection visual recordExamine surfaces at the end of the cooling phase, check the operation of movement joints, and ensure the absence of random cracks or abnormal lifting at room corners.
  3. Tripartite signature of the logbookThe official heating-up logbook form is initialed and signed jointly by the site management, the heating installer, and the screed layer to validate the end of the thermal test.
  4. Release of CM measurement zonesLocate on the as-built drawings the reserved areas devoid of heating pipes to immediately proceed with material sampling using the carbide bomb.

Once the screed has returned to a stabilised temperature of around 15 °C to 20 °C, the thermal protocol is considered complete. This return to cold is essential: carrying out a residual moisture measurement on a still-warm screed skews evaporation balances and makes the carbide bomb results unusable for the flooring contractor.

Heating incidents, defects, and management of logbook non-conformities

A heating-up process does not always follow the ideal theoretical curve. The most frequent site incidents remain the unexpected interruption of the mobile boiler, the sudden exceeding of the maximum step temperature, or the pure and simple absence of daily recording. According to the SIA 251 standard, the protocol aims to release thermal-origin mechanical stresses in the screed prior to flooring installation. If the process is flawed, liability for the integrity of the assembly relies on the traceability of the anomalies.

In the event of a power outage or thermal failure occurring during the heating or maximum steps, the reaction depends on the duration of the interruption. If the stoppage lasts less than twenty-four hours, the CFC 241 heating installer must resume the setpoint at the step preceding the interruption before continuing the elevation. If the screed has completely cooled down for several days, the entire heating cycle must be restarted from the initial flow temperature. This measure prevents a violent thermal shock that would cause mortar shearing around the underfloor heating pipes.

When the heating-up logbook is not kept on a daily basis, or if it is presented a posteriori without effective signatures from the heating engineer and site management, the screed layer must issue a notice of non-conformity in accordance with the rules of the SIA 118 standard. The absence of a signed logbook prohibits the commencement of floor covering work. Without this contractual document, proof that the work has undergone the required thermal test does not exist, transferring the entire risk of subsequent defects onto the company accepting the substrate.

Frequently asked questions

What to do in the event of a heating failure occurring during the temperature increase phase?

If the thermal interruption is short, the CFC 241 heating engineer resumes the interrupted temperature step after circuit stabilisation. Conversely, if the screed has cooled down to the building's ambient temperature, the thermal protocol must obligatorily be restarted from the initial 25 °C step. This incident, its duration, and the decision to resume must be recorded jointly on the site heating-up logbook.

Why can the heating-up never begin before twenty-one days on a cement screed?

The SIA 251 standard prescribes a minimum period of twenty-one days after pouring for a traditional cement screed. This time ensures that the hydraulic matrix has developed sufficient mechanical strength to withstand thermal expansions without bursting. Premature temperature increase blocks binder hydration, degrades internal mortar cohesion, and destroys heating pipe embedding through premature shock.

Does the signed heating-up logbook authorize the immediate installation of tiling or parquet?

No. The heating-up logbook only certifies the relief of internal screed stresses through controlled expansion. It in no way prejudges the actual residual moisture of the mortar. Once the cooling phase is completed and the circuit is brought back to shutdown temperature, the flooring contractor must obligatorily carry out the calcium carbide moisture measurement (CM device) at the reserved sampling points before starting their work.

Who must obligatorily sign the heating-up logbook for it to be legally valid?

The heating-up logbook must obligatorily bear the signature of the CFC 241 heating installer, who controls the generator's flow temperatures, and that of the site management, which oversees the site schedule. The CFC 281 screed layer initials the document to record compliance with the steps prescribed by the SIA 251 standard. Without these joint signatures, the document loses all value as a joint discharge record.

Texts and standards cited

  • SIA 251Floating screeds and underlays in buildings, execution specifications and heating-up protocol.
  • SIA 118General conditions for the execution of construction work, notification duties and non-conformity management.