🧱 CFC 281Movement joints and layoutChapter 10 of 10 in the section

Accepting the screed: flatness, level, joints, sounding and complete inspection report

As soon as a floor covering seals the floor, the screed escapes any direct visual inspection. This chapter guides you through conducting the five mandatory checks on the raw structure, recording the results in a single joint inspection report in accordance with standard SIA 118, and setting deadlines for lifting localised reservations prior to the intervention of subsequent trades.

Key takeaways

  • Joint acceptance of the screed must take place strictly before any floor covering is laid.
  • The check verifies flatness, level, joints, surface cohesion and moisture.
  • Any reservation entered in the inspection report requires exact location and a deadline for remedial work.
  • Joint signature of the document transfers the risk in accordance with the provisions of standard SIA 118.

Perform the five technical checks on the screed before any covering is applied

Once covered with tiles or parquet, a bonded or floating screed becomes inaccessible without destructive demolition. Formal acceptance therefore permits no postponement: it is carried out on a bare, clean and swept substrate, in the presence of the site management and, ideally, the floor layer. In accordance with standard SIA 251, compliance checking is based on a series of rigorous physical steps designed to validate the geometrical tolerances and mechanical soundness of the mortar.

  1. Surface flatness checkPlace a 2-metre metal straightedge without added load and measure residual gaps using a tapered measuring wedge or graduated gauge. Inspect the central areas, diagonals and particularly the immediate vicinity of doorways.
  2. Level verificationCheck the finished height of the screed against the general reference level mark drawn at one metre on the walls. Verify the required thickness reservation for the future adhesive and floor assembly.
  3. Inspection of control joints and separation jointsCheck the cleanliness, verticality and clear release of the edge insulation strips. Ensure that the sawn or profiled control joints pass through the prescribed thickness without being filled with hard laitance.
  4. Compacting and surface cohesion soundingTest the screed with a screed hammer or impact ball to identify any delamination or hollow areas. Carry out a scratch-test sclerometer grid to assess surface hardness.
  5. Reconciliation of moisture and heating dataIntegrate the results of the calcium carbide measurements at the labelled locations and verify the complete execution of the initial heating-up protocol for underfloor heating.
Technical checklist for bare screed in accordance with standard SIA 251
CheckMeasuring toolReference requirementCommon non-conformity
Overall flatnessRigid 2 m straightedge and graduated wedgeGap compliant with standard SIA 251 tolerancesSag or bump in the centre of the span
Local flatnessRigid 20 cm rulerMaximum deviation under the ruler according to the required classTrowelling marks or ridges
Reservation heightTape measure below reference lineAltitude tolerance compatible with the coveringScreed too high blocking door clearance
Edge jointsSpatula and visual checkContinuous flexible strip without rigid acoustic bridgeMortar spilled over the edge strip
Surface cohesionScribe point and hammerAbsence of dusting, cracking or hollow soundFriable un-sanded laitance or surface crust

Draft the acceptance inspection report and manage the lifting of reservations

The acceptance inspection report is the legal document that concludes the work of the screed-laying company and triggers the start of the warranty period provided for under standard SIA 118. Drawn up on the construction site following the joint inspection, this document records an unequivocal overall assessment: acceptance without reservations, acceptance with reservations, or postponement of acceptance if major defects preclude any use of the floor. The Code of Obligations and standard SIA 118 require that any shortcomings observed are clearly and detailedly flagged.

  • Complete identification of the lot, building, floor and inspected rooms with attached plans.
  • Recording of ambient data during the visit: surface temperature, air temperature and relative humidity.
  • Explicit recording of defects in the form of localised reservations with marking on sketches.
  • Setting of a precise schedule including the deadline for carrying out remedial work for each defect.
  • Designation of the approved remediation method (planing, sanding, stitching resin or self-levelling compound).
  • Joint and immediate signature by the screed layer and the site management representing the client.

Transfer of custody and liability regimes in accordance with standard SIA 118

Signing the acceptance inspection report marks the contractual completion of the work carried out by the screed layer. Within the framework defined by standard SIA 118, this bilateral legal act records in writing the condition of the screed at a specific date, in the presence of the site management and the contractor. From the moment the inspection report is initialled without reservation or the reservations issued are the subject of an acceptance agreement, custody of the work is transferred to the client. This transfer releases the screed layer from daily monitoring of the surface and transfers the presumption of conformity for all elements that have been directly checked, namely flatness, level of the top edge, geometric location of control joints and residual moisture recorded by calcium carbide.

On a building site, the floating screed becomes the working plane for multiple finishing work trades as soon as it hardens. Plasterers, painters, electricians or sanitary installers move across it daily with mobile scaffolding, stepladders, concentrated loads and heavy tools. Without a proper acceptance inspection report drawn up prior to these interventions, any subsequent alteration, such as a deep scratch, chipping from a point impact, plaster contamination or a chipped joint edge, risks being wrongly blamed on the screed layer. The inspection report draws up the exact inventory of flatness and mechanical integrity, freezing the situation before the subsequent trades intervene.

Acceptance opens the claim period provided for by standard SIA 118, during which the client retains the right to assert hidden defects in the screed. A hidden defect in a floating screed may consist of internal disintegration of the mortar due to a lack of binder, late shrinkage cracking occurring under thermal stress that was not detectable upon handover, or unforeseen differential settlement of the underlying acoustic insulation. The existence of a complete inspection report makes it possible to demonstrate that these defects do not stem from an initial failure to execute the installation requirements set by standard SIA 251, but arise from external stresses or movements specific to the load-bearing structure.

Technical treatment of reservations and covering visa

When departures from trade practice are identified during the joint visit, they must be formulated as written, precise reservations geolocated on the floor plan. Each reservation entered in the inspection report requires a technical remediation measure adapted to the criteria of standard SIA 251. It is essential to distinguish surface non-conformities from structural mortar instabilities. Localised flatness defects are corrected by diamond-disc planing on the screed ridges or by applying a smoothing compound compatible with the binder present. Parasitic cracks, on the other hand, require rigid stitching to restore monolithism prior to laying sensitive floor coverings.

Screed reservation remediation protocols in accordance with the requirements of standard SIA 251
Recorded defectSIA 251 normative criterionRemediation methodLifting validation
Excessive gap under straightedgeTolerance exceeded under 2 m straightedgeDiamond sanding or self-levelling screedChecking with bevelled straightedge and gauge
Random through-crackContinuity broken outside control jointMetal staples and epoxy groutHammer sounding and inspection
Joint lip offsetContinuity on either sideMechanical planing of raised edgesControlled flushness with ruler
Excessive moisture contentExceeding the allowable thresholdRegulated heating and forced ventilationNew sample and CM measurement

The deadline granted for lifting reservations must be set by mutual agreement with the site management, taking into account the setting times inherent to bridging resins or levelling mortars. Once the corrective work has been carried out, a joint counter-expertise visit is conducted to validate the remediation. This process leads to the signing of the reservation lifting form, a document which authorises the start of the final floor covering work. According to Swiss building trade rules, the craftsman who undertakes installation on a screed presenting open reservations without a lifting visa assumes full responsibility for subsequent bonding failure or detachment issues.

  • Joint signing of the lifting inspection report by the site management and the screed layer.
  • Formal handover of the final calcium carbide moisture measurement protocol.
  • Transmission to the tiler or parquet layer of the layout plan for control joints and stitched areas.

Dispute management: refusal to sign, major defects and unauthorised covering

When the site management refuses to sign the acceptance inspection report or the floor layer starts work without consultation, the screed layer must immediately secure their technical and contractual position. Standard SIA 118 regulates the work verification procedure and the notification of defects. As soon as a disagreement arises regarding compliance with the flatness tolerances defined by standard SIA 251, an altimetry deviation or the alignment of a control joint, the absence of a joint inspection casts doubt on the screed, even though structural deformations or site overloads may be the real cause of the defect.

In the presence of a localised technical reservation — gap exceeding tolerances under the 2 m straightedge, finished level non-compliant with the reference line or offset at a joint crossing — the screed layer must never let a third party carry out self-levelling or grinding without written agreement. Any uncontrolled mechanical intervention risks reducing the minimum covering thickness above the underfloor heating pipes or altering the compactness of the mortar. The contractor records the anomaly, proposes the appropriate remediation method in accordance with standard SIA 251, sets a realistic lifting deadline and organises a formal follow-up visit. If the site management orders work to be carried out officially without proper warning in accordance with the rules of standard SIA 118, the costs cannot be passed on to them.

In the event of a persistent dispute regarding flatness or cracking, immediate recourse to a joint technical expertise makes it possible to settle the matter before the floor assembly is laid. The neutral expert measures gaps using the calibrated measuring wedge, examines surface cohesion using a grid or sclerometer test, and checks for the absence of peripheral acoustic bridges. This joint technical report constitutes the sole probative document to preserve the craftsman's rights under the Code of Obligations, before the final covering permanently conceals the floor structure.

Frequently asked questions

What should you do if the site management refuses to sign the screed acceptance inspection report?

In the event of a refusal to sign, the screed layer immediately records their own measurements of flatness, level and moisture, accompanied by dated photos. They forward the complete document to the site management by registered mail, setting a formal deadline for taking a position in accordance with standard SIA 118. Without a reasoned dispute within the allotted time, the work is considered accepted without reservation by the client.

Can a tiler plane or grind a screed without notifying the screed layer?

No mechanical modification of the substrate must be undertaken without the written consent of the screed layer. Uncoordinated planing risks weakening the minimum embedment of the underfloor heating coils or destroying the surface film of a fluid screed. If the tiler intervenes without prior notice, they assume full responsibility for structural defects, induced cracking and subsequent loss of adhesion on the floor assembly.

What tolerances are allowed if the inspection report does not specify any particular requirement?

In the absence of stricter contractual requirements in the specifications, the standard requirements of standard SIA 251 apply automatically. For a screed intended to receive a standard bonded covering, the maximum permissible gap under the 2 m straightedge is 4 mm. If the screed remains bare or receives a thin resin, increased requirements must have been expressly agreed in writing prior to pouring.

How to formalise the lifting of a reservation after correcting a joint offset?

After carrying out the localised smoothing or corrective sawing, the screed layer summons the site management for a joint inspection visit. The parties check the local flatness under the 2 m straightedge and ensure the continuity of the peripheral separation layer. The lifting is recorded by signing an addendum to the initial inspection report, mentioning the intervention date and formally authorising covering by the layer.

Texts and standards cited

  • norme SIA 118General conditions for the execution of construction work, verification of the work, notice of defects and guarantees
  • norme SIA 251Floating screeds and underlays in buildings, flatness tolerances, execution rules and joint treatment