🧱 CFC 281Substrate, underlays and decouplingChapter 4 of 10 in the section

Edge insulation strip: height, continuity, doors and trimming after pouring

This guide details the installation rules for the perimeter edge insulation strip for floating screeds. You will learn how to guarantee its absolute continuity, treat special points such as service pipe penetrations and door thresholds in accordance with SIA 251, and coordinate trimming to comply with the acoustic requirements of SIA 181.

Key takeaways

  • The perimeter insulation strip completely decouples the mortar from fixed vertical walls and rising columns.
  • A single rigid contact destroys the overall acoustic efficiency of the floating slab for the entire apartment.
  • The integrated polyethylene skirt guarantees laitance-tightness in every internal or external corner of the structural work.
  • Trimming is carried out exclusively after the final installation of the finishing tiles or parquet flooring.

Ensure continuous decoupling to comply with SIA 181

The floating screed rests on thermal or acoustic insulation and must not exhibit any rigid mechanical contact with the load-bearing structure. When pouring a fluid screed or compacting a traditional cement screed, the mortar tends to infiltrate the smallest gaps. The extruded polyethylene foam edge insulation strip acts as a compressible elastic barrier. If a hard spot remains, impact noise energy is transmitted directly to the structural work, ruining the impact sound insulation required by SIA 181.

For floating screeds, perimeter strips must extend above the finished floor level during pouring and exhibit lasting compressibility to ensure free thermal expansion of the work without transmitting mechanical stresses to the walls.

Norme SIA 251

The main risk lies in omitting the strip behind visual obstacles. On the construction site, the crew sometimes bypasses waiting heating pipes or forgets the recess located under a distribution manifold or behind a low radiator. A single missing linear metre puts the screed in direct contact with the masonry or concrete. This localized acoustic bridge degrades the acoustic performance of the entire room, or even the complete apartment, causing non-conformities during final acoustic inspections.

Selection criteria and characteristics of edge insulation strips according to the work
Screed typeMinimum thicknessRequired heightIntegrated accessory
Unbonded cement screed8 mmFinished floor height + 20 mmWithout flap or simple flap
Calcium sulphate fluid screed10 mmFinished floor height + 30 mmPolyethylene flap with adhesive
High-inertia heated screed10 mmFinished floor height + 30 mmWatertight flap and reinforced foot

Installation technique, door thresholds and critical trimming phase

The work begins with careful dedusting of the bottom of the partitions and the slab. The strip is unrolled continuously along the perimeter walls, columns and door frames. Internal corners must be formed without mechanical tension: cut only the horizontal plastic skirt without cutting the compressible foam. In external corners, keep the strip pressed against the wall to prevent the pressure of the liquid mortar from peeling it inward toward the room.

  1. Wall stapling or gluingFix the strip to the partition above the screed level line using staples for plasterboard or adhesive tape for concrete, never piercing the lower waterproofing zone.
  2. Folding down the flapUnfold the waterproof plastic flap over the floor insulation board. Connect it to the floor membrane using wide tape to prevent any liquid laitance leaks.
  3. Continuity of jointsOverlap successive strips by at least 50 mm at each longitudinal joint, ensuring perfect watertightness against mixing water.
  4. Passing door thresholdsInsert a movement joint profile fixed to the continuous edge insulation strip or align two back-to-back strips to separate distinct thermal or acoustic volumes.

At interior doors and sliding bays, the strip ensures the continuity of perimeter insulation. The screed layer must not interrupt the strip under the pretext of a future finishing threshold. If a expansion joint crosses the door, the compressible strip separates the two floating slabs while extending up to the arris of the metal door jambs or wooden frames.

Interface management on the construction site requires rigorous communication. If a finishing work trade prematurely trims the strip to make marking easier, they create a gap where tile adhesive infiltrates down to the structural work. Compliance with SIA 251 recommendations and the delivery of a perfectly watertight substrate protect the company against disputes related to acoustic defects.

Special points and hidden acoustic bridges: radiators, penetrations and door frames

The slightest failure in the continuity of the edge insulation strip destroys the acoustic insulation of a floating screed. According to SIA 181, a single point of rigid contact between the screed and the structure transmits impact sound throughout the building. In multi-family housing, forgetting a linear metre of compressible strip behind a wall radiator fixed before pouring or recessed under a niche creates a direct acoustic short-circuit. The acoustic energy generated by footsteps or impacts no longer encounters the elastic damping of the resilient underlay; it propagates through partitions and slabs, ruining the insulation required by SIA 181.

Treatment of special points according to SIA 251 requirements
Special pointAcoustic short-circuit riskRequired execution by the screed layer
Low wall radiators and nichesPouring mortar against the unprotected raw wall under the hanging bracketsContinuous extension of the compressible edge insulation strip behind the emitter.
Vertical pipe penetrationsInfiltration of laitance forming a rigid ring between the pipe and the screedInstallation of a waterproof compressible foam sleeve taped to the insulation.
Metal door framesMortar backup in the hollow profile and direct contact with steelPrior packing of the door frame and bypassing by the perimeter strip.
Underfloor heating manifoldsTight conduits preventing proper insertion of the compressible stripSufficient spacing of pipes and manual cutting of custom-made foam.

The treatment of door thresholds constitutes another sensitive area governed by SIA 251. At each door opening, the edge insulation strip must not be interrupted but must ensure a seamless junction with the movement or stop profile. This metal profile must rest directly on a resilient strip and remain completely decoupled from the door frame jambs by means of a compressible PE foam shim. This continuity prevents mortar infiltrations under the door frame or against the foot of the frame, maintaining the vibrational and mechanical independence of each room in the apartment.

Trimming protocol, interface coordination and inspection before skirting boards

Trimming the edge insulation strip flush with the mortar immediately after pouring or floating represents a frequent defect on site. This hasty practice violates trade practice and SIA 251 prescriptions. The edge insulation strip must protrude by several centimetres above the upper level of the screed throughout the duration of hardening, drying and heating-up of the underfloor heating. This protrusion protects the peripheral gap against the accidental fall of rubble, plaster or smoothing compound which would fill the mechanical void and create an irreversible acoustic bridge.

  1. Pouring phase and initial settingKeep the edge insulation strip firmly upright against the walls with its plastic flap glued to the underlay. No trimming is permitted during screed pulling.
  2. Initial heat-up protocolKeep the strip intact throughout the thermal cycle to freely absorb the horizontal expansions of the panel and corner uplifting without wall constraint.
  3. Handover to flooring contractorsDeliver the screed with the protruding strip to tilters and parquet layers. Cutting is only carried out once the floor covering is fully installed up to the edges.
  4. Final trimming and installation of skirting boardsTrim the foam with a utility knife at the exact level of the finished covering just before fixing the skirting boards. These must obligatorily be decoupled by a flexible bead.

During acceptance of the work according to SIA 251, the site foreman performs a systematic inspection along the entire perimeter of the rooms. Every internal or external corner, every passage under a radiator and every passing technical conduit must show a visible, continuous and uncrushed compressible strip. If a mortar run has crossed the protective flap, the screed layer must immediately clean out the laitance using a cold chisel to re-establish complete decoupling of the floor. This methodical rigor ensures compliance with the acoustic requirements of SIA 181.

Management of acoustic non-conformities and remediation of rigid connections

When an in situ acoustic measurement reveals non-conformity with SIA 181 requirements for impact sound, the origin frequently stems from a localized hard contact. A single linear metre of edge insulation strip forgotten under a radiator bracket, a mortar run having crossed the flap or a door threshold connected to the structural work is enough to degrade insulation by several decibels across the entire room. Facing this defect, the screed layer must act methodically before final acceptance of the work according to SIA 251.

  1. Non-destructive diagnosis and tracking of the hard bridgeInvestigation begins at critical passages: heating niches, metal door frame bases and door thresholds. Using an electrician's knife or a thin metal blade passed vertically against the masonry, the operator checks the effective continuity of decoupling down to the floor insulation.
  2. Cutting and stress-relieving of the screedAs soon as a rigid contact point is identified, a mechanical groove is cut using a diamond grinder equipped with source dust extraction. The cut line must pass through the entire thickness of the screed to release the blocked element without damaging the underlying acoustic insulation.
  3. Vacuuming and insertion of an expansion jointThe groove is cleared of all laitance or gravel by industrial vacuuming. A closed-cell polyethylene foam joint profile ten millimetres thick is forcibly reinserted to the bottom of the slot, restoring elastic discontinuity before sealing by the flooring installer.

Frequently asked questions

How to treat the edge insulation strip at French doors with waterproofing?

The PE foam perimeter strip must extend up against the frame jamb or waterproofing flap without interruption. At the threshold level, a compressible, rot-proof resilient strip is inserted between the screed and the window sill. This device prevents any direct contact between the mortar and the bottom rail, simultaneously guaranteeing free thermal shrinkage of the paving and insulation against lateral transmission noise.

What thickness of perimeter strip should be installed for a fluid anhydrite screed?

For a calcium sulphate-based fluid screed, SIA 251 requires an edge insulation strip of at least eight millimetres in thickness, equipped with a polyethylene skirt glued to the thermal or acoustic insulation. This waterproof flap, fixed by adhesive tape to the kraft paper or board, prevents infiltrations of liquid grout which would create solid shims after complete drying.

Who is responsible for the final cutting of the edge insulation strip protruding from the screed?

The screed layer delivers the screed with the resilient strip protruding two to three centimetres above the finished floor. Final trimming with a utility knife is exclusively the responsibility of the tradesperson installing the floor covering, whether tiler or parquet layer. This cutting is performed only after applying the covering and just before fixing the wall skirting boards with acoustic decoupling.

How to connect the perimeter strip behind vertical radiator pipes?

Pipes crossing the screed must be individually sheathed with soft closed-cell foam sleeves of at least five millimetres. The wall edge insulation strip must bypass these sleeves by forming a continuous cut without rupture. If the space is less than fifty millimetres, the screed is stopped by a resilient stop to form a flexible protective sleeve around the conduits.

Texts and standards cited

  • SIA 181Sound protection in buildings, requirements for impact and airborne sound transmission
  • SIA 251Floating screeds and resilient underlays in buildings, execution rules and perimeter decoupling