Key takeaways
- The written protocol formally certifies that the screed has reached its permissible residual moisture content.
- Each calcium carbide measurement must be geolocated and linked to a specific room.
- The transmission of the report to site management transfers the custody of the finished work.
- The flooring contractor validates the acceptance of the substrate by signing the joint inspection record.
Essential technical data of the survey in accordance with SIA 251
The document authorising the installation of a floor covering is not merely a figure scribbled on the corner of a plan. It constitutes the technical act by which the screed layer demonstrates that their work has reached the required state of equilibrium to receive the upper assembly. In accordance with trade practice and the requirements of SIA 251, this report records a series of objective parameters taken at the precise moment of the calcium carbide bomb test. The absence of even one of these details exposes the company to immediate dispute in the event of subsequent damage through detachment, blistering or mould beneath parquet flooring.
- Installation authorisation protocol
- Joint inspection record drawn up by the screed layer recording the residual moisture content measured using the calcium carbide (CM) method, confirming the suitability of the substrate to receive the planned covering.
The survey must detail the exact nature of the mortar used, as the admissibility threshold varies threefold depending on whether it is a cement-based screed or a calcium sulphate (anhydrite) flowing screed. The document also specifies whether the substrate incorporates underfloor heating and confirms the complete completion of the heating-up protocol. Each destructive test must correspond to a sampling area predetermined during casting, marked by markers or layout sheets, to certify that the sampling was carried out across the full thickness without perforating the heating pipes.
| Document section | Recorded technical parameter | Legal and technical utility |
|---|---|---|
| Construction site identification | Level, apartment number, room use | Defines the exact scope covered by the release of the floor. |
| Nature of the mortar | Type of binder (cement or calcium sulphate), average thickness | Sets the applicable residual moisture limit value. |
| Thermal history | Dates of heating-up and maximum plateau | Proves the dimensional stabilisation of the heated screed. |
| Ambient conditions | Air temperature (°C) and relative humidity (%) | Justifies the absence of risk of condensation during measurement. |
| CM measurement per room | Sample weight, manometric pressure, value in % CM | Constitutes material proof of the dryness of the substrate. |
It is imperative to attach a location plan to the report indicating the exact position of each control point. For a four-room apartment, the screed layer shall carry out at least one measurement per homogeneous zone or per surface increment prescribed by SIA 251. Simply entering a general average for the entire floor constitutes a methodological error: as moisture is never perfectly uniform due to drafts or shaded areas, each room must have a separate recording line indicating the measured value.
The transfer of custody and the joint inspection signature mechanism
From the moment the protocol certifies that the screed has reached its critical moisture level and the document is handed over to the parties involved, the transfer of risks takes place. Until this stage, the screed layer retains full and complete responsibility for the drying of their work. The handover of the certificate shifts this burden to site management and to the tradesperson responsible for installing the tiling, resin or parquet flooring. If a construction site delay occurs after transmission without the room being closed, the accidental rewetting of the screed by weather or plastering work henceforth falls under the supervision of the client.
- Joint verificationThe screed foreman invites the flooring contractor or site management to witness the crushing of the sample and the reading of the carbide pressure gauge.
- Signing of the protocolThe parties record the date, exact time and affix their signatures at the bottom of the form containing the raw values and the sampling plan.
- Formal notificationThe original document or its certified electronic copy is formally transmitted to site management with a copy to the designated flooring subcontractor.
- Recording of reservationsIf the flooring contractor rejects the substrate due to a value not being met, the exact reason and the date of a re-inspection are recorded on the spot.
The flooring contractor has a duty to examine the substrate before commencing work. By countersigning the measurement protocol provided by the screed layer, the flooring tradesperson expressly acknowledges that the substrate exhibits the physical conditions suitable for their adhesives or acoustic insulation. If the parquet layer begins installation without demanding this document, they bear full responsibility for damage caused by substrate moisture. The role of the screed site manager is to formalise this dispatch without delay by e-mail or construction management platform, archiving proof of dispatch in the handover file.
Suitability to receive the covering must be ascertained before the start of installation work. The moisture control must be the subject of a written report transmitted to site management.
norme SIA 251
Finally, when several weeks elapse between the release measurement and the actual start of flooring installation, the screed layer's liability cannot be re-engaged if external water ingress has occurred during this waiting period. The certified date of the survey constitutes the clear dividing line between the screed execution phase and the subsequent management of the building's indoor climate by the other trades.
Methodical survey per room and mapping of control measurements
The installation authorisation cannot be based on a global assessment of the building. The drying of a flowing or traditional screed varies considerably from one room to another depending on exposure to drafts, sunlight through large bay windows and the lengths of underfloor heating pipes. The release document therefore requires rigorous and individualised recording of moisture values for each room or distinct expansion joint zone. Each zone must include at least one representative sampling point, imperatively located outside the zones of direct influence of exterior doors or hot service ducts.
| Location / Room | Screed binder | Underfloor heating | Measured value (CM-%) | Permissible threshold (waterproof or wood covering) | Suitability opinion |
|---|---|---|---|---|---|
| Living room / Dining room (Lot A) | Calcium sulphate (anhydrite) | Yes (in operation) | 0.3 CM-% | ≤ 0.3 CM-% (bonded parquet) | Conform for installation |
| North Bedroom 1 (Lot A) | Calcium sulphate (anhydrite) | Yes (in operation) | 0.5 CM-% | ≤ 0.3 CM-% (bonded parquet) | Non-conform (continue heating) |
| Kitchen (Lot A) | Conventional cement | Yes (in operation) | 1.4 CM-% | ≤ 1.5 CM-% (tiling) | Conform for installation |
| Hall / Entrance (Lot B) | Conventional cement | No | 2.1 CM-% | ≤ 2.0 CM-% (vitrified stoneware) | Non-conform (drying deficit) |
| Basement corridor | Conventional cement | No | 1.8 CM-% | ≤ 2.0 CM-% (textile covering) | Conform for installation |
To guarantee the accuracy of results, the survey of measurement points must record the test equipment used, the serial number of the calcium carbide device, the mass of the sample taken with a core drill or chisel over the entire height of the screed, as well as the standardised manometric reaction time. The document includes an attached schematic plan showing the exact location of the plugged test hole. This physical traceability prohibits any subsequent dispute regarding the investigation area or potential damage to embedded heating pipes.
Distribution circuit, formal handover and transfer of custody of the work
Transmission to the flooring contractor constitutes the pivotal act that transfers physical custody of the substrate and responsibility for future defects. The official moisture measurement and installation authorisation protocol is not circulated informally: it is drawn up by the technician who performed the test, validated by the screed foreman, and then transmitted without delay to site management as well as to the tradesperson responsible for finishing work. Upon receipt of this signed report, the installation company (tiler, parquet layer or resin floor applicator) takes note of the substrate's conformity and assumes full and complete responsibility for the finishing work it undertakes.
- Drawing up the joint moisture inspection recordThe screed layer records the values read on the pressure gauge for each referenced measurement point, in the presence of the flooring contractor and site management if possible.
- Verification of admissibility thresholdsSite management and the flooring contractor compare the residual water contents recorded with the specific requirements of the prescribed covering and the binder in place in accordance with SIA 251.
- Formal notification of the installation authorisationThe official installation authorisation form is signed by the stakeholders, certifying that the screed has reached its equilibrium state and its critical dryness threshold.
- Resumption of custody and immediate verificationThe flooring contractor becomes the custodian of the substrate; they retain the right to carry out their own confirmation measurements before applying their primer or adhesive.
The original copy of the document is filed in the site logbook of site management and kept in the as-built documentation file. A full copy is given to the client as well as to the flooring contractor. This rigorous formalism seals the contractual chain and prohibits any shifting of blame onto the screed package in the event of tile detachment, parquet lifting or adhesive blistering occurring after the premises are put into service.
Dispute management, refusal to sign and moisture re-absorption
When the residual moisture remains higher than the permissible values of SIA 251, the measurement protocol becomes a record of non-maturity. The screed layer records the value measured per room, refuses the installation authorisation and transmits the report without delay to site management and the flooring company. If the client or flooring contractor demands that work begin regardless, the screed layer refuses to endorse liability for future defects. Such a situation requires a formal release signed by site management or a written service order expressly releasing the screed applicator in accordance with the rules of the Code of Obligations.
The flooring contractor's refusal to countersign the measurement point survey constitutes another common point of friction. The floor layer or parquet layer may dispute the location of a probe or the accuracy of a measurement using the calcium carbide bomb. In this case, the parties carry out a joint counter-measurement on unheated reserved areas. The screed layer documents the session with dated photographs of the pressure gauge, notes reservations on the report and has the witnesses present sign. In the absence of a representative of the subsequent trade during the call-up, the document is sent the same day by registered mail with an electronic copy to site management.
| Encountered situation | Direct consequence | Action required by the screed layer |
|---|---|---|
| Non-compliant water content | Risk of blistering or detachment | Refusal to authorise installation, extension of ventilation or heating |
| Flooring contractor's refusal to sign | Lack of agreement on substrate condition | Immediate joint counter-measurement or notification by registered mail |
| Subsequent water damage | Rewetting of dry mortar | Joint inspection record cancelling the previous protocol |
Once transmission to the flooring contractor has been carried out and countersigned, custody of the work is transferred. If damage occurs subsequently, such as a plumbing leak, facade infiltration or wet plastering work reintroducing massive moisture, the screed layer is covered by their initial report. As soon as such an event occurs, they report the alteration in writing: the previous authorisation protocol becomes void and a new complete series of measurements must be ordered at the expense of the party responsible for the damage before any resumption of installation.
Frequently asked questions
What to do if the parquet layer lays their wood without waiting for the moisture survey?
The screed layer immediately sends a formal notice for premature intervention to site management and the parquet layer. This written document notes the commencement of work without prior validation of the measurement point survey in accordance with SIA 251. From this moment on, the contractor assumes full responsibility for deformations, warping or detachments linked to residual moisture, completely releasing the screed layer from their guarantee on the floor assembly.
Who mandates and financially covers counter-measures in the event of a dispute?
If the contractor disputes the result obtained with the calcium carbide bomb, the costs of the counter-measure depend on the joint inspection record. When the value measured per room confirms that the floating screed complies with the requirements of SIA 251, the intervention costs are borne by the requesting contractor. If the screed proves to be indeed too wet, the screed layer takes charge of the operation and extends the necessary drying measures.
How to react to rewetting of the mortar after signing the protocol?
The screed layer must record the water ingress through a joint inspection record with photos and notify site management in writing. The granted installation authorisation is formally suspended. The transfer of custody protects the screed layer against the consequences of the damage, but technical drying and a new complete moisture survey remain essential before reauthorising access for finishing contractors.
Can the contractor demand a different measurement method from that of the screed layer?
SIA 251 establishes measurement with the calcium carbide bomb as the recognised method for determining the installation maturity of screed mortars. Capacitive or dielectric probes help guide surface diagnosis, but do not constitute contractual evidence to authorise the covering. The contractor cannot reject the legitimate result of a CM sample taken in accordance with trade practice.
Texts and standards cited
- norme SIA 251Floating screeds and underlays in buildings, execution specifications and installation maturity criteria
- norme SIA 118General conditions for the execution of construction work, duties to warn and handovers of works