Skip to content
Website
🧱 CFC 281Substrate, underlays and decouplingChapter 1 of 10 in the section

Inspect the slab: flatness, cleanliness, level and available thickness

This chapter details the rigorous method for checking the levels of a raw slab before pumping the mortar. You will learn how to measure the actual available thickness relative to the metric level mark, identify high spots that do not comply with tolerances, and draft the reasoned support refusal that protects your liability as a screed specialist.

Key takeaways

  • The official metric level mark serves as an absolute benchmark for checking the reserved rough thickness.
  • Standard SIA 251 sets the minimum nominal thicknesses according to the insulation and mechanical loads.
  • A concrete slab that is too high dangerously reduces the cover and leads to bending cracks.
  • The record of insufficient thickness requires an immediate written refusal before ordering from the batching plant.

Check the altimetry and flatness of the raw substrate before ordering

The screed specialist never starts a construction site by unrolling edge insulation strips or laying thermal insulation. The initial technical act consists of verifying that the space between the upper surface of the reinforced concrete slab and the projected finished floor level corresponds scrupulously to the tender data. A common mistake on a construction site is validating the substrate based on a simple visual check or a verbal instruction from the site management. However, as soon as the mixer truck or screed pump leaves the batching plant, the company assumes the material risk of the ordered volume. If the available height proves insufficient during installation, the screed poured out of tolerance falls under the installer's technical fault.

Metric level mark
Altimetric benchmark marked out with a chalk line or laser by the structural work trades, precisely establishing the height of one metre above the planned finished floor level for the structure.
  1. Locating and checking the level markIdentify the finished metre marks established by the surveyor or structural work on the peripheral walls and columns. Check their consistency from one room to another using a rotating laser level to eliminate marking drift.
  2. Measurement of the total rough reservationMeasure the vertical distance between the level mark and the raw slab using a tape measure or laser distance meter. The theoretical value must be equal to 1000 mm plus the thickness of the complete assembly (finishing layer, screed, acoustic underlay, thermal insulation, and any levelling layer).
  3. Grid of singular pointsRecord the level under the reference mark every three metres as well as at doorways, internal corners, and right above the technical ducts fixed to the slab. A slab may respect the average level but present a critical high point in the middle of the span.
  4. Checking local flatnessPlace the 2 m aluminium straightedge on critical areas and measure the gaps using a bevelled measuring wedge. The tolerances of the raw slab fall under the rules of the art for structural work; if they exceed the permitted values, correction cannot be made at the expense of the screed thickness.
Typical breakdown of a reservation for a floating screed on underfloor heating
Assembly componentMinimum permitted thicknessConsequence of a slab high point
Floor covering (e.g. tiles + adhesive)15 mmImpossibility of connecting thresholds and doors
Cement or calcium sulphate screed (SIA 251)65 mm (including 45 mm above the pipes)Loss of cover, shearing and cracking
Underfloor heating system (tubes on studded panels)30 mmCrushing of conduits or forced elevation
Thermal or sound insulation30 mmReduction of acoustic performance
Required theoretical reservation140 mmMandatory refusal if slab level < 1140 mm below mark

Managing the thickness defect: work stoppage and formal notification

When the altimetric survey highlights a concrete slab that is too high, the remaining thickness for pouring the screed becomes less than the requirements of standard SIA 251. Faced with this situation, the fatal mistake is to try to adapt on the spot by reducing the insulation or pulling the mortar thinner than planned. A floating screed that is too thin suffers from a rocking effect, cracks under operational loads, and ends up breaking the tiles or loosening parquet floors. The responsibility for these defects will be entirely attributed to the screed specialist who accepted the substrate without formulating reserves. The duty to notify regarding a non-compliant substrate is developed with all its legal mechanisms in the CFC 201 trade; reference is made to it for the details of the contractual procedure.

  • Immediately stop any preparation or pouring operation upon discovering an insufficient level.
  • Record the precise altimetric surveys on a location plan indicating the missing millimetres.
  • Take convincing photographs showing the control straightedge, the laser level, and the tape measure.
  • Notify the site management by telephone, then confirm without delay by a formal written notice.
  • Formally refuse the pouring as long as the substrate is not corrected or the levels redefined.

The written notification of substrate refusal must be sent to the site management before any order of a mixer truck. This document details the levels measured relative to the official level mark, recalls the minimum thickness required by standard SIA 251 for the planned binder type, and sets out the structural risks incurred in the event of under-thickness. The letter clearly stipulates that the intervention deadline is suspended and that the resumption of the structural work (for example by milling, planing, or chipping away the reinforced concrete at high points) is the responsibility of the client. As long as a solution compliant with technical rules has not been validated in writing, the truck must not be dispatched to the construction site.

Comparison of slab tolerances and requirements of standard SIA 251

The geometric acceptance of the raw substrate determines the mechanical integrity of the entire floor assembly. The reinforced concrete slab delivered by the masonry company frequently exhibits cumulative altimetric deviations related to formwork deflection, settlement under fresh load, or delayed deformations. When the screed specialist intervenes, the height below the reference level is fixed by door thresholds, French windows, and awaiting technical ducts. Any local elevation of the raw concrete absorbs the space reserve and compresses the mortar thickness planned by the specifications.

According to standard SIA 251, the thickness of a floating screed on an insulation layer cannot fall below thresholds strictly dimensioned according to the compressibility of the insulation and the targeted operational load. In the frequent case of underfloor heating, the rule requires a minimum cover of 35 mm of material above the top of the tubes for a fluid mortar or a standard additived cement screed, bringing the total screed thickness to at least 55 or 65 mm depending on the pipe diameter. If the slab exhibits an out-of-tolerance high point, this level is no longer respected, creating an immediate risk of bending cracks or localized punching.

Flatness requirements of the raw substrate and consequences for the screed system
Controlled elementPermitted tolerance on raw slabImpact on the floating screedRequired measure in case of exceeding
Local flatness under the 2 m straightedgeMaximum deviation of 8 to 10 mmMortar thickness variation and risk of acoustic bridgesPlaning of bumps or heavy smoothing by structural work
Absolute level relative to the level markAltimetry deviation of ± 10 mmLoss of nominal screed thickness at high pointsRefusal of substrate and correction of concrete bedding
Offsets at concreting jointsProjections less than 3 mmTearing of the polyethylene film or rupture of the insulationSpot grinding of sharp edges by the mason
Technical ducts crossing on the floorComplete embedding via levelling layerLocalized crushing and mechanical weakeningPrior installation of a bonded levelling screed

Flatness control is systematically carried out using a 2-metre aluminium straightedge equipped with a graduated measuring wedge, as well as via a laser grid linked to the official metric mark drawn on the walls. Hollows and bumps must be methodically recorded across the entire room. If a high point reduces the distance between the concrete and the finished level to the point of cutting into the thermal or acoustic insulation, the screed specialist cannot compensate for this anomaly by thinning their covering layer. A screed that is too thin loses its load-distributing rigidity and breaks under construction traffic or usage loads.

Reasoned substrate refusal procedure and joint inspection record

As soon as the altimetric surveys reveal a slab that is too high, material ordering and batching plant deployment must be immediately suspended. Allowing ready-mix trucks or silo trucks to arrive on site when the reservation is insufficient places the craftsman in a technical and financial dead end. Pouring an out-of-tolerance screed commits the applicator's liability towards subsequent trades, notably the tiler or parquet layer, who in turn will refuse a surface that does not comply with the finishing altimetric requirements.

  1. Drawing up the joint survey planTransfer the measured heights below the metric mark every three metres onto the level plan, marking the critical areas on the floor with indelible chalk where the screed loses its minimum thickness.
  2. On-site convocation of the site managementHave the available thickness levels inspected in the presence of the site manager and the representative of the structural work company, comparing the recorded values with the principle cross-section of the tender.
  3. Joint signature of the inspection recordHave the survey sheets countersigned immediately by the parties present to lock in the technical facts before any equipment is cleared away.
  4. Sending the reasoned substrate refusalAddress a formal written notification confirming the impossibility of laying the assembly according to standard SIA 251, requesting written orders from the site management for remedial measures.

The refusal letter must describe the observed defects with precision: exact location of raised slabs, measured levels relative to the metric mark, calculated theoretical residual thickness, and deficit relative to the prescribed thickness. The rules of the Code of Obligations governing the construction contract and the provisions of standard SIA 118 require the contractor to report without delay any defect in the ground or material supplied by the client that would compromise the flawless execution of the work. The complete legal foundations of this duty to notify are detailed in the professional rules for structural work.

The document must conclude by setting a deadline for the remediation of the base. Rectification work belongs exclusively to the mason: it generally consists of mechanical planing or milling of the concrete bumps under continuous suction, followed by industrial dedusting. Only after a new joint inspection validating the total reservation can the delivery of mortars be rescheduled on the intervention schedule.

Arbitration and protective measures in case of a non-compliant slab

When the altimetric survey confirms that a slab that is too high prevents compliance with the minimum thicknesses prescribed by standard SIA 251, conflict often arises due to the imminence of the schedule. Site management, pressed by delivery deadlines, may be tempted to order the pouring by reducing the mortar thickness or removing an acoustic insulation layer. Accepting this verbal injunction directly engages the screed specialist's liability for future defects: cracking due to lack of pipe cover, rocking of panels, or sagging under load.

  1. Interrupt the orders to the concrete batching plantsBlock the supply as soon as the reservation defect is noted. Inform the supplier to avoid costs for a turned-away mixer truck or lost batch.
  2. Draw up joint stakingSummon the site management and the civil engineer on site. Record the level levels using a laser relative to the official one-metre level mark, precisely locating the concrete bumps.
  3. Notify the reasoned substrate refusalTransmit a written notice on the same day recording the measured deviations, the thickness deficit compared to the requirements of standard SIA 251, and the stoppage of operations in non-compliant areas.
  4. Demand remediation by the structural workBringing into compliance is the mason's responsibility: mechanical planing or bush hammering of slab over-thicknesses, or formal agreement from the acoustic engineer to modify the compressibility of the sub-layers.

Nếu gros œuvre refuse d'intervenir et que le rabotage est impossible en raison de l'enrobage minimal des armatures structurelles, la direction des travaux doit modifier le complexe de sol. Deux voies restent ouvertes : recourir à un isolant à haute performance thermique ou acoustique de moindre épaisseur, ou substituer la chape prévue par un mortier autonivelant à liant spécial autorisant une épaisseur réduite, dont le surcoût financier relève du compte prorata ou du lot maçonnerie défaillant.

Frequently asked questions

What should you do if site management demands to reduce the screed thickness to compensate for the slab?

Formally refuse in writing. Reducing the thickness below the thresholds of standard SIA 251 compromises mechanical strength and creates a major risk of cracking or punching. If site management maintains its order despite your warning, demand a formal written order recording the complete discharge of your liability before any pouring.

Who should bear the costs of planing a concrete slab that is too high?

The costs are borne by the structural work company responsible for the non-compliant pouring of the raw slab. The screed specialist must neither execute nor finance this heavy rectification work. The intervention is the subject of a joint inspection record with site management to directly attribute the chipping, milling, and cleaning work to the masonry lot.

Can a local lack of thickness be compensated by thinning the acoustic sub-layer?

No, this modification is strictly prohibited without the acoustic engineer's written agreement. Locally reducing or compressing a resilient sub-layer creates a rigid acoustic bridge and degrades the impact sound insulation of the structure. The nominal thickness of the insulation must be preserved to guarantee the acoustic efficiency required by current building standards.

How should defects be recorded if site management does not travel to the construction site?

Draw up a joint survey in writing yourself, supported by a photographed and geolocated level book showing the measuring rod below the one-metre mark. Send this record without delay by registered mail or secure electronic mail with acknowledgement of receipt, confirming the immediate suspension of pouring until the substrate is brought into compliance.

Texts and standards cited

  • SIA 251Sets the design and execution requirements and minimum thicknesses applicable to floating screeds in buildings.
  • SIA 118Defines the general conditions for the execution of construction work, notably the duty to notify and the formal notification of reserves.

In the same section