Key takeaways
- Calcium carbide measurement is the only legally recognized method in accordance with SIA 251.
- Material sampling must strictly target the lower third of the screed thickness.
- The residual moisture threshold for a cement screed on underfloor heating is 1.5% CM.
- A heated calcium sulfate screed requires a strict maximum residual moisture of 0.3% CM.
Locating and sampling in the lower third without damaging the heating system
On a construction site subject to SIA 251, electronic capacitive or pin-type meters serve only to map the dampest areas. Only the chemical method using a pressure bottle with calcium carbide (CM measurement) is authoritative when accepting the substrate prior to laying floor coverings. The test relies on the stoichiometric reaction between the free water in the sampled material and the calcium carbide, which generates acetylene gas and causes the pressure gauge to rise proportionally to the moisture present.
The moisture in a screed is not distributed homogeneously throughout its thickness. The surface in contact with ambient air dries quickly, while water remains trapped within the mass, particularly in contact with the thermal or acoustic insulation layer. Sampling the first few centimeters leads to a falsely favorable result that masks underlying water accumulation, which is a source of major subsequent defects such as blisters, rotting parquet or lifting tiles.
- Marking control pointsIdentify a minimum of three representative sampling points per hundred square meters, prioritizing the thickest areas or the least ventilated rooms, away from direct drafts.
- Probing and gentle mechanical cuttingClear the mortar using a flat chisel and a club hammer without aggressive pneumatic percussion to avoid creating localized thermal heating that would evaporate the water present in the material.
- Selection of the deep fractionSystematically discard rubble from the top two-thirds of the bedding layer. Recover only the hard pieces located in the lower third, directly above the separation membrane.
- Crushing and capsule loadingGrind the fragments in a steel mortar using a club hammer until a fine grain size of a few millimeters is obtained, without touching the dust with fingers to avoid transferring sweat.
Interpreting the limiting thresholds of residual moisture according to the mineral binder
Standard SIA 251 sets very strict quantified requirements regarding the allowable residual moisture content. These values vary according to the chemical nature of the binder (Portland cement or calcium sulfate of the anhydrite type) and according to the presence or absence of a heating system integrated into the floor. An anhydrite screed tolerates much less residual water than a cement screed because gypsum loses most of its mechanical strength in prolonged damp environments and undergoes destructive expansive reactions on contact with common tile adhesives.
| Binder type | Floor configuration | Waterproof or wood covering | Tiles or stone |
|---|---|---|---|
| Cement screed (CT) | Without underfloor heating | 2.3% CM | 2.5% CM |
| Cement screed (CT) | Heated embedded screed | 1.5% CM | 1.5% CM |
| Calcium sulfate (CA) | Without underfloor heating | 0.5% CM | 0.5% CM |
| Calcium sulfate (CA) | Heated embedded screed | 0.3% CM | 0.3% CM |
For a cement-based screed, weighing is usually carried out on a test sample of 20 grams or 50 grams depending on the capacity of the reagent ampoule. Pressure reading is carried out after twenty minutes of continuous agitation using steel balls placed in the steel bottle. If the rate exceeds 1.5% CM on a heated screed, the work is not ready for installation: floor covering cannot begin and the drying protocol must be continued under the responsibility of the trades concerned.
For heated fluid or traditional calcium sulfate screeds, the requirement drops to the drastic threshold of 0.3% CM. The waiting time during the reaction in the pressure bottle is standardized and reading must not be rushed. The absence of a continuous pressure rise ensures that the combined water of the binder is not chemically stripped by the reagent, which would distort the interpretation of free water.
Operating procedure for the carbide test according to SIA 251
On construction sites in Romandy, verifying the residual moisture of a screed tolerates no approximation. While electronic hygrometers allow surfaces to be mapped quickly, only the chemical method using the calcium carbide pressure bottle (CM method) has probative value during work acceptances. Prescribed by standard SIA 251, this destructive measurement constitutes the exclusive reference procedure to contractually certify the dryness of the mortar before laying the final covering. Basing the opening of the installation site on simple surface dielectric measurements exposes the screed layer to major defects regarding adhesion, peeling or degradation under a vapor barrier.
- Targeted sampling in the lower third of the thicknessUsing a flat chisel and a club hammer, extract the sample fragments from the core of the dampest zone, strictly located in the lower third of the screed thickness. Avoid any surface dust. Eliminate aggregates with a diameter greater than four millimeters, as these non-porous gravels distort the weight calculation by underestimating the actual proportion of binder paste.
- Mortar grinding and ultra-precision weighingCrush the pieces in a robust metal mortar until a fine and homogeneous grain size is obtained. This operation must be carried out quickly to limit moisture exchange with the ambient air. Weigh the test sample on the site balance with a calibrated tare: fifty grams for a cement mortar or one hundred grams for a calcium sulfate-based screed.
- Loading the pressure bottle and sealingPlace the weighed sample as well as the steel balls into the dry metal container. Insert the calcium carbide glass ampoule by tilting the flask to prevent any premature breakage against the steel. Place a new seal on the collar, then firmly screw on the pressure gauge head equipped with its calibrated dial.
- Vigorous agitation, reaction and final readingShake the bottle vigorously and vertically to fracture the ampoule and initiate the exothermic reaction between the reagent and the free water, producing acetylene gas. Swirl the bottle to complete internal grinding. Wait for complete thermal and pressure stabilization before recording the final pressure, then convert the result into a CM mass percentage according to the device's chart.
Allowable moisture thresholds by binder and report
Standard SIA 251 modulates the allowable residual moisture values according to the mineral nature of the binder and the presence of underfloor heating. Cement continues a slow hydraulic hardening kinetics and tolerates a share of residual water without mechanical degradation. Conversely, calcium sulfate self-leveling screeds (anhydrite) cannot withstand any water sequestration under a hermetic layer: residual moisture superficially dissolves the gypsum crystals and causes crumbling of the bonding zone.
| Mineral binder of the screed | Integration of underfloor heating | Vapor-permeable covering | Waterproof or sensitive covering (parquet, resin) |
|---|---|---|---|
| Cement | Without underfloor heating | 2.3% CM | 2.0% CM |
| Cement | With underfloor heating | 1.8% CM | 1.5% CM |
| Calcium sulfate (anhydrite) | Without underfloor heating | 0.5% CM | 0.5% CM |
| Calcium sulfate (anhydrite) | With underfloor heating | 0.3% CM | 0.3% CM |
The requirement of 0.3% CM for heated anhydrite screed represents the strictest tolerance in finishing work. Prior heating forces water migration upwards, but only sampling in the lower third certifies core drying. For a cement screed on heating coils, the 1.5% CM threshold is required when the room receives parquet or a resinous covering, compared to 2.0% CM on cold screed. Any exceeding of these limits leads to destructive condensation when thermal installations are put back into service.
Management of non-conformities, sampling damage and moisture disputes
When the calcium carbide meter measurement reveals residual moisture higher than the requirements of standard SIA 251, the floor may under no circumstances be released for the installation of coverings. Faced with a non-compliant result, the screed layer records the raw value on the contradictory report, refuses the acceptance of suitability for covering and prescribes the continuation of drying measures. For a cement screed exceeding its admissibility threshold, forced cross-ventilation or the placement of mobile dehumidifiers is required. For a heated calcium sulfate screed exceeding the strict limit value of 0.3% CM, restarting a thermal cycle according to the agreed protocol remains the only way to evacuate trapped interstitial water without degrading the crystalline structure of the binder.
In the event of a dispute by the parquet or tile installer, no surface capacitive check can invalidate a carbide test. If the representativeness of the sample is called into question by the site management, a contradictory counter-expertise must be carried out the same day. The parties jointly choose a new representative zone, located away from direct drafts and far from French windows. The sample is extracted under direct visual control in the lower third of the thickness, crushed in a steel mortar with immediate weighing on a precision balance. The factory-sealed carbide flasks are checked before introduction. Maintaining the pressure on the pressure gauge during the regulatory period freezes the decision: as long as the normative threshold is not reached, the postponement of installation is recorded in writing, formally releasing the screed company from any liability regarding subsequent defects on the covering.
Frequently asked questions
Why are electronic pin-type or capacitive meters insufficient to authorize installation?
Capacitive or pin-type moisture meters measure the dielectric constant or surface electrical resistance of the screed. These indicative measurements are distorted by the density of the mortar, the presence of salts or metal reinforcement. Standard SIA 251 recognizes only the carbide meter as a binding reference method: only the chemical reaction of calcium carbide with the water of the sample taken in the lower third guarantees an unquestionable mass value.
What should be done if the pressure gauge of the carbide meter continues to rise after twenty minutes?
On a cement screed, a continuous rise on the pressure gauge beyond ten minutes often indicates incomplete crushing of coarse aggregates or defective sealing of the bottle. For an anhydrite screed, a prolonged reaction may reveal the presence of mixed binders or abnormal chemical decomposition. If stabilization does not occur, the test is declared void. The screed layer cleans the device, checks the O-ring and restarts a complete sampling.
How to choose the sampling location without damaging the underfloor heating coils?
The screed layer demands precise as-built drawings from the heating engineer and can use a thermal camera or a heat-sensitive film when the circuits are operating. Measurement points are ideally agreed and marked during casting using vertical recess markers. Chiselling is carried out exclusively with a club hammer and a fine manual chisel, without a mechanical rotary hammer, working parallel to the supposed layout of the tubes.
Why is the moisture threshold much stricter on heated anhydrite screed than on cement screed?
Calcium sulfate is a binder sensitive to residual moisture under tight confinement. In the presence of a heated screed covered with a vapor barrier or adhesive, the migration of residual water causes the mechanical strength of the binder to drop and causes surface softening. Standard SIA 251 thus imposes a strict threshold of 0.3% CM on heated anhydrite screed, compared to 1.5% CM for a heated cement screed.
Texts and standards cited
- SIA 251Floating screeds and bonded screeds inside buildings, execution requirements, drying and allowable moisture thresholds.
- SIA 118General conditions for the execution of construction work, notification duties, acceptances and disputes between clients and contractors.