🧱 CFC 281Cement or anhydrite screed: selection and executionChapter 2 of 10 in the section

Thickness: minimum according to binder and load, with the thinnest point being decisive

This chapter provides the technical benchmarks for determining the minimum regulatory thickness of a floating screed according to SIA 251. You will learn how to calculate allowances based on the cement or calcium sulphate binder, incorporate anticipated service loads, and organise a complete altimetric survey of the substrate to neutralize the critical point before application.

Key takeaways

  • The mechanical compliance of a floating screed is always assessed on the basis of its lowest point thickness.
  • Calcium sulphate screed allows for lower nominal thicknesses than traditional cement screed.
  • An increase in service loads requires a proportional thickening of the load-distribution slab to prevent failure.
  • Laser surveying referenced to the level mark identifies high points prior to casting.

Minimum thicknesses prescribed by SIA 251 according to binder and load

On a unbonding layer or a compressible thermal and acoustic insulation layer, the floating screed acts as a load-distribution plate. Its bending strength depends directly on the cube of its effective thickness. A satisfactory general average never protects the structure against punching shear if a local area presents a millimetric shortfall. SIA 251 establishes the minimum nominal thicknesses required depending on the nature of the hydraulic binder, the mechanical strength class of the mortar and the intended use of the room.

Minimum thicknesses of unheated floating screeds according to SIA 251 (standard elasticity insulation)
Binder and mortar classService load ≤ 2.0 kN/m² (residential)Service load ≤ 3.0 kN/m² (offices)Service load ≤ 5.0 kN/m² (commercial / workshops)
Cement (CT-C20-F4 or CT-C25-F4)45 mm55 mm65 mm
Self-levelling fluid cement (CT-C25-F5)40 mm50 mm60 mm
Calcium sulphate / anhydrite (CA-C25-F5)35 mm45 mm55 mm
High-strength calcium sulphate (CA-C30-F6)30 mm40 mm50 mm

For a screed on underfloor heating, the calculation principle changes: the thickness must be measured strictly above the top of the hot water pipes or insulation panel studs. SIA 251 requires a minimum cover of 35 millimetres of cement mortar above the top of the pipe to guarantee both mechanical stability and heat distribution. For a fluid calcium sulphate screed, which is denser and free of significant linear shrinkage, this cover can be reduced to 30 millimetres for standard residential loads.

Methodical search for the thinnest point before casting

The thinnest point of a screed is almost never found in the middle of rooms. It is concentrated in areas of structural geometric constraints: directly above concrete partition walls, on poorly levelled precast slab heads, at floor ventilation duct crossings, or in the immediate vicinity of entrance thresholds and French doors. It is at these precise points that the insulation is compressed by an underlying reinforced concrete overthickness, or where the overall allowance was underestimated relative to the finished level determined by site management.

  1. Transfer and control of the one-metre level markUsing a rotary laser level set to the official altimetric reference of the construction site, check the consistency of the level line marked at one metre above the finished floor on each perimeter wall. Any marking error by site management would distort all levelling pegs.
  2. Grid layout and survey of the rough allowance heightBefore laying the separation felt or film, measure the distance between the laser line and the rough slab using a three-metre grid. Immediately identify the area where the rough slab rises to its highest level: this is the zero point of your minimum allowance.
  3. Checking sleeves and duct crossingsUse a tape measure to determine the distance between the top of the electrical or sanitary sleeves embedded in the levelling layer and the theoretical screed surface level. If this free clearance is less than the minimum prescribed by SIA 251, the assembly must be corrected before casting.
  4. Setting out screed screed-height pegs and stakingPlace tripods or metal screed-height pegs, setting the base firmly on the actual top of the insulation. Adjust the flush height of each reference marker to guarantee the nominal thickness at the highest point of the floor, even if the lower areas receive an extra thickness of mortar.

Consequences of a localized thickness deficit on the integrity of the structure

A floating screed functions as a rigid slab placed on an elastic or thermal-acoustic mattress. Its capacity to distribute service loads to the load-bearing structure without failing depends directly on the bending moment it can withstand. This resisting moment is proportional to the square of the effective thickness. When an area has an insufficient thickness, even if limited to a few square metres or a duct crossing, the rigidity of the plate collapses locally. The screed never compensates for a weak point through the overthickness of neighbouring areas: under the action of a concentrated or rolling load, the bending tensile stresses concentrate precisely at the point where the section is smallest.

Mechanical behaviour and risks according to the extent of the thickness deficit on insulation layers
Observed effective thicknessBehaviour under loadDirect pathology on the structureImpact on upper layers
Deficit of less than 5 mm (cement screed)Reduced residual allowable bending, superficial microcracking under dynamic load.Restrained shrinkage cracks at singular points.Tolerated subject to low loads and flexible adhered installation.
Deficit of 10 to 15 mm (cement or calcium sulphate binder)Loss of plate inertia greater than 30%, rupture of the neutral axis under concentrated load.Through-cracking, spalling along edges and local subsidence.Shearing of ceramic tiles, failure of mineral joints.
Tube cover less than 30 mmThermal concentration and extreme differential gradient between the top of the tube and the surface.Rectilinear cracking mirroring the layout of the heating coils.Visible pattern of pipes through thin flooring, debonding of the floor covering.
Direct contact with a hard point (duct, slab reinforcement)Total mechanical locking, elimination of the acoustic damping effect.Severe structural sound bridging and immediate fracture under traffic loads.Full transmission of impact noise to underlying rooms.

In addition to mechanical breakage, insufficient cover on an underfloor heating system degrades heat transfer. When the thickness above the tubes becomes insufficient, heat no longer diffuses evenly through the mortar mass. Localized hot bands are created, which increase differential expansion stresses. These repeated thermomechanical stresses cause premature debonding of tile adhesives or warping of parquet flooring installed later by finishing trades.

Technical trade-offs and corrective measures for insufficient allowance height

As soon as preliminary levelling reveals a high point that does not allow the minimum thickness required by SIA 251 to be reached, the screed layer must suspend casting and refuse on-site improvisation. The temptation to locally plane down the mortar thickness without modifying the underlying assembly leads directly to disputes during heating commissioning or acoustic testing. Three solutions conforming to trade standards are then available to site management, each of which must be formally validated in writing prior to any implementation.

  • Modification of the screed binder: substitute a traditional cement screed with a self-levelling calcium sulphate (anhydrite) based mortar. Thanks to its superior flexural tensile strength and almost total absence of shrinkage, this binder allows nominal thicknesses and pipe covers to be reduced by approximately 10 to 15 mm compared to cement mortar for the same load class.
  • Replacement of the screed insulation: replace standard thermal or acoustic insulation with a high mechanical performance panel exhibiting equivalent thermal resistance for a lesser thickness, or opt for a thin acoustic underlayer with technical approval when total floor height is restricted.
  • Planing the load-bearing formwork or rectifying the structural work: require the masonry company to grind down concrete ridges, smooth slab peaks, or correct unremunerated service pipe runs that create the incriminated high point.

Any modification of the finished level line implies close coordination with other finishing trade contractors. Raising the upper level of the screed to make up for the critical point entails modifying the clearance height under interior doors, shifting the level of entrance or balcony thresholds, and altering the first step of fixed stairs. Only site management has the authority to decide between raising the overall floor level and locally repairing the load-bearing formwork.

Management of thickness non-conformities and post-casting recourse

When post-casting inspection or the early appearance of cracks reveals insufficient height, the arithmetic mean of the surveys no longer protects the structure. Mechanical failure under service loads invariably occurs at the most vulnerable precise location. If doubts persist after checking with a measuring rod or in the presence of localized subsidence, verification is carried out by unreinforced destructive core drilling or careful chisel probing down to the insulation layer. This joint inspection allows the actual thickness of the hardened mortar to be formally recorded and the actual cover of pipes or floor heating tubes to be verified.

  • Conditional maintenance and load revision: if the thickness reduction remains minimal and localized outside heavy traffic zones, an adjustment of the allowable service load can be negotiated in writing with the civil engineer and the client.
  • Structural surface reinforcement: for a cement mortar showing a borderline level, the application of an epoxy resin composite system saturated with glass fibre fabric allows the flexural tensile strength of the assembly to be increased.
  • Demolition and complete repair: as soon as the deficit compromises overall stability or pipe cover is below the normative threshold, clean sawing of defective areas and laying a new screed is the only lasting solution.

The allocation of responsibilities depends exclusively on the traceability established prior to intervention. If the screed contractor pumped the mortar without recording the lack of allowance relative to the structural work's level mark, they assume full responsibility for the defect. Conversely, if they transmitted their formal notice of defects to site management in accordance with SIA 118 and the Code of Obligations, and the written order to cast was maintained by site management, the financial cost of repairs rests with the client.

Frequently asked questions

What should be done if the thinnest point is 5 mm less than the SIA 251 minimum?

A localized deficit of five millimetres directly weakens the structure under concentrated loads. Before installing any floor covering, site management must be notified in writing. Two technical options exist: either a waiver formally accepted by the civil engineer if the room bears a very light load, or the execution of a surface reinforcement using reinforced epoxy resin, or even complete remedial work by local demolition if the screed sounds hollow.

Why does a fluid calcium sulphate screed allow for a lower thickness than a cement screed?

Anhydrite mortar has superior compactness and develops high flexural tensile strength, while exhibiting virtually zero shrinkage during setting. According to SIA 251, these mechanical characteristics allow a reduction in nominal thickness of approximately ten to fifteen millimetres compared to a traditional cement screed, while guaranteeing identical load-bearing capacity against domestic service loads and optimal cover for heating pipes.

How can the thickness of a fresh screed be measured accurately during application?

The installation team uses a graduated metal depth gauge or a millimetric rod, pushing it vertically into the fresh material until it hits the polyethylene film or insulation. This check is carried out systematically at the high points identified during prior laser levelling, as well as above sanitary or heating pipe networks, where the available height reserve remains most critical for proper coverage.

Does a reinforcing mesh allow the minimum thickness prescribed by SIA 251 to be reduced?

No, metal reinforcement does not increase the bending resistance of a non-structural floating screed and in no way allows the required minimum thickness to be reduced. Its role is limited to limiting the opening of shrinkage cracks during the setting of the cement mortar and holding the edges flush together. To decrease thickness without losing strength, the binder must be changed to a liquid calcium sulphate screed.

Texts and standards cited

  • SIA 251Screeds in buildings - Technical requirements and thickness tolerances
  • SIA 118General conditions for the execution of construction work and duty to notify
  • code des obligationsGeneral rules relating to service contracts and liability for defects