🧱 CFC 281Section 5 of 610 chapters

Drying, heating-up and moisture measurements: the execution standard

This section is intended for team leaders, foremen and site managers who must oversee screed drying, coordinate the temperature increase of the underfloor heating and certify the residual moisture before installing floor coverings. It defines the legal measurement method, acceptance criteria by binder type, and essential contractual procedures to formally release the screed layer from liability regarding the requirements of parquet installers, tilers and resin applicators.

  • 10chapters
  • 22 000words
  • 6sections in the training course
  • 60chapters in total

Key values to remember 5

SIA 251

2.3% CM

Maximum allowable moisture of a cement screed without underfloor heating for the installation of parquet

SIA 251

1.5% CM

Limit residual moisture of a cement screed with underfloor heating before the installation of a sensitive covering

SIA 251

0.5% CM

Maximum water content of a heated calcium sulphate screed before the installation of parquet or resin

SIA 251

21 days

Minimum age of a traditional cement screed before starting the heating-up process

CO art. 371

5 years

Legal limitation period to enforce the warranty for defects in an immovable structure

Scope of work for the screed layer: drying, heating and interface responsibilities

The hygrothermal treatment of a floating screed is the critical junction where the responsibilities of the screed layer, the heating installer and the floor covering installers intersect. The screed layer's role consists of mixing the screed, embedding the underfloor heating pipe networks without altering the insulating underlays, and then monitoring the evacuation of residual water until the moisture content prescribed by the SIA 251 standard is reached. The physical operation of the heat generators falls exclusively under the responsibility of the heating installer in accordance with CFC 241, but the screed layer prescribes the temperature rise profile and monitors the thermal plateaus within the mortar.

The professional boundary must remain perfectly watertight to prevent any unjustified shift of liability in the event of late defects:

  • Structural work, the reinforced concrete load-bearing slab and the air tightness or protection against rising damp from the ground-contact slab fall under masonry trades (CFC 201 and CFC 211.1). The screed layer receives the raw substrate but does not carry out any structural reinforcement.
  • The hydraulic circuits, mixing valves, circulators and the connection of manifolds are the responsibility of the heating installer (CFC 241). The screed layer never operates the controls of the boiler or heat pump.
  • Finishing smoothing compounds, final adhesion sanding excluding anhydrite screed laitance, adhesives, waterproofing under tiling and the installation of finishes are the responsibility of the tiler (CFC 282), the parquet installer (CFC 273 and CFC 283) or the floor resin applicator (CFC 272) respectively.
  • Inspection upon receipt of the substrate prior to bonding is regulated as the responsibility of the final installer; the screed layer provides the measurement certificate and records the condition of the mortar at the time of the handover of the work.

Methodological pathway: from initial evaporation to the evidence file

To guarantee the durability of a floor without shrinkage cracking or subsequent debonding, drying management requires a rigorous chronology. The ten chapters of this section are consulted as a continuous operational procedure, organized into three major stages: physical diagnosis, forced maturation, and the legal securing of handover.

  1. Diagnostics and mortar kinetics (chapters S5-01 to S5-05)Learning begins with instrumental mastery of the calcium carbide (CM) method, the only destructive process recognized under the SIA 251 standard. The use of electronic surface impedance meters is then repositioned to its proper role as a non-conclusive pre-localization tool. The progression details the sequence of heating-up on underfloor heating, the realistic calculation of natural evaporation times according to the seasons, and technical drying methods using condensation or adsorption dehumidifiers while prohibiting direct-fired space heaters.
  2. Release protocols and covering constraints (chapters S5-06 to S5-08)The second phase formalizes the issuance of the certificate of suitability for installation. It equips the foreman against construction site schedule drifts to issue a substantiated refusal to hazardous acceleration requests. This section differentiates residual moisture tolerances according to the permeability of the finish: porous tiling, solid glued parquet or the waterproof barrier of an epoxy resin, on cement mortar or calcium sulphate fluid screed.
  3. Recurring pathologies and five-year traceability (chapters S5-09 and S5-10)The final part guides the analysis of accidental re-wetting (pipe bursts, reverse condensation, vapor barrier failure on ground-bearing slabs) and structures the evidentiary archiving of construction files. In accordance with the limitation period of art. 371 CO covering defects in immovable structures, the contractor must lock down the complete history of reports, test specimen photographs and heating curves for at least five years.

📘 Chapters in this section 10

Drying, heat-up and moisture measurements

The reference measurement: calcium carbide meter, depth sampling and binder-specific threshold

Master the deep sampling technique and the use of the CM flask to lock in your legal measurements.

Drying, heat-up and moisture measurements

The electrical moisture meter: indicative only, and why it never replaces measurement

Identify false alarms from electronic devices to precisely target your core drillings without any possible dispute.

Drying, heat-up and moisture measurements

The protocol: step-by-step rise, maximum step, cooling down and signed logbook

Apply the exact temperature plateau profile to purge water from the mortar without cracking your slabs.

Drying, heat-up and moisture measurements

How long: thickness, binder, room ventilation and misleading rule of thumb

Evaluate the actual evaporation rate of the mortar based on ambient humidity and banish empirical calendar approximations.

Drying, heat-up and moisture measurements

Accelerating: dehumidifier, ventilation, construction site heating and what does not work

Deploy appropriate condensation dehumidifiers while avoiding thermal errors that block internal drying.

Drying, heat-up and moisture measurements

The document authorising installation: survey, measurement points, signature and transmission

Draft the contradictory acceptance certificate that unambiguously transfers the custody of the screed to the parquet installer.

Drying, heat-up and moisture measurements

Schedule pressure: requests to shorten times, written refusal, and what happens otherwise

Argue your technical refusal in the face of pressure from management to preserve the integrity of your guarantees.

Drying, heat-up and moisture measurements

Depending on the flooring: tiles, parquet, resin, and three different thresholds

Adjust your release criteria according to the tightness of the covering to neutralize any risk of subsequent blistering.

Drying, heat-up and moisture measurements

Dampness returns: leak, waterproofing defect under the slab, or screed that never dried

Distinguish trapped mixing water from external infiltrations using a rigorous comparative expert methodology.

Drying, heat-up and moisture measurements

Archive: measurement photo, room, date, operator, and the file kept for five years

Organize your intervention evidence and time-stamped records to calmly withstand judicial expert assessments for five years.