Key takeaways
- The SIA 181 standard classifies the bedroom as a sensitive room requiring enhanced protection.
- The permissible sound level of the installation is always assessed at the nominal air change flow rate.
- The acoustic measurement is carried out with doors and windows closed, at the geometric centre of the resting volume.
- Excessive outdoor background noise distorts the measurement and requires a specific night-time campaign.
Acoustic requirements in bedrooms according to the SIA 181 standard
In a dwelling, the bedroom is the room most sensitive to noise generated by building services. A controlled mechanical ventilation system runs continuously, day and night. A continuous airflow noise, a duct resonance or a whistle at a diffuser quickly turns an installation that is compliant on paper into a legitimate reason for complaint by the occupants.
- Sensitive room for rest
- Within the meaning of the SIA 181 standard, a room intended for sleeping or prolonged relaxation, such as a bedroom or a children's room, subject to the strictest requirements regarding continuous noise from technical equipment.
The SIA 181 standard distinguishes between minimum requirements, mandatory for every residential building, and enhanced requirements, often specified in general contractor contracts or for condominium ownership. For continuous noise from the building's technical installations, the permissible sound level of ventilation in a bedroom demands extreme vigilance during sizing and installation. The acoustic rating level takes into account the weighted sound pressure level, corrected for any tonal or impulsive components generated by the installation.
On the construction site, the ventilation fitter must never compensate for insufficient attenuation in the network by simply throttling the bedroom diffusers by hand. Reducing the free area of a supply terminal locally increases the air velocity above 2 m/s, creating direct flow noise in the room. Attenuation must absolutely be provided upstream by baffle or circular acoustic silencers fitted directly on the main and secondary distribution network.
In-situ measurement protocol, night-time background noise and acceptance of the work
The acoustic compliance check is carried out after the complete aeraulic balancing of the installation, with clean filters fitted and interior doors closed. Any reading taken on an unbalanced installation, or one running at a temporary setting, has no contractual value at handover of the work.
- Conditioning the roomSeal all windows and doors leading outside or to other rooms of the dwelling. Switch off any electrical appliance likely to generate parasitic noise.
- Positioning the sound level meterPlace the microphone on a tripod at a height between 1.20 m and 1.50 m above the finished floor, more than 1.00 m from reflecting surfaces and outside the direct air jet of the supply terminal.
- Measuring the operating levelRecord the sound pressure level with the air handling unit at the nominal night-time setpoint, integrating the signal over a representative period.
- Measuring the background noiseStop the ventilation completely to measure the residual noise of the room. This step is essential in order to apply the standardised correction linked to the sound environment of the site.
Night-time background noise is the main constraint of acoustic campaigns on urban construction sites or those near roads. If the difference between the noise of the running installation and the residual background noise is less than 3 dB, the measurement is inconclusive according to the rules of the art: it is impossible to isolate the actual contribution of the ventilation. Between 3 dB and 10 dB of difference, a logarithmic correction is deducted from the measured level. Beyond 10 dB of difference, the background noise no longer affects the recorded value.
If the rating level exceeds the contractual threshold set by the SIA 181 standard, the work is deemed defective. On delivery, the client checks the condition of the work as soon as is customary in the ordinary course of business and notifies the contractor of defects under art. 367 CO. Where an exceedance attributable to the ventilation installation is established, the client's rights apply under art. 368 CO, opening the way to a demand for rectification at the expense of the ventilation system installer. This rectification often requires replacing silencers, adding secondary sound attenuators or completely redoing the sound insulation of the supply ducts.
Diagnosing exceedances and reworking aeraulic components
When a night-time acoustic measurement reveals that the permissible level has been exceeded in a bedroom, the ventilation fitter must locate the exact origin of the noise before any remedial work. A non-compliance recorded with the sound level meter in the far field or at the bed position generally arises from three distinct paths: the self-noise of the supply or extract terminals, direct airborne transmission from the unit along the duct, or structure-borne conduction via rigid fixings.
| Observed phenomenon | Frequent aeraulic cause | Remedial action on the network |
|---|---|---|
| High-pitched whistle at the diffuser | Excessive throttling of the terminal damper to compensate for a poorly balanced network. | Open the terminal damper, balance the upstream branches on the floor regulating dampers and lower the fan speed setpoint. |
| Dull low-frequency hum | Missing or undersized sound attenuator on the supply air section at the unit outlet. | Replace the rigid section with a baffle silencer or fit a circular silencer with an absorbent core of at least 900 mm. |
| Diffuse flow noise | Air velocity above 2.0 m/s in the connection sleeve of the terminal plenum. | Enlarge the section of the connecting duct and switch to a low-velocity diffuser with multidirectional diffusion. |
| Vibrations transmitted through the slab | Duct hangers screwed without anti-vibration mounts or a duct clamped against the lightweight partition. | Decouple the clamp with an elastomer sleeve and fit compliant anti-vibration hangers on the load-bearing support. |
Noise generated by the terminal regulating damper is the most widespread error during commissioning. To throttle an excessive flow without creating a whistling pressure drop directly in the sensitive room, the foreman must shift the pressure drop to a regulating element remote from the room, located upstream of the distribution silencer. If the secondary silencer does not absorb the mid-range frequencies generated by the fan, fitting a flexible acoustic sleeve or inserting a mineral-foam acoustic cartridge in the terminal duct provides targeted attenuation.
Refusal of acceptance, rectification of the work and night-time counter-measurement
As soon as the results of an acoustic check carried out by the client's acoustician establish that the installation does not meet the requirements of the SIA 181 standard, site management refuses to declare acceptance of the ventilation installation. Under Swiss construction law, such an exceedance constitutes a defect of the work within the meaning of art. 368 CO. Art. 368 CO gives the client the right to demand free rectification of the work, to demand a price reduction or, where the defect is so serious that the work cannot be used, to refuse acceptance.
For the ventilation contractor, the notice of defects triggers the obligation to correct the network within the period set by site management. In accordance with art. 367 CO, the client checks the condition of the work as soon as is customary in the ordinary course of business and notifies the contractor of defects. Where acceptance is refused for acoustic non-compliance, the ventilation company does not obtain the release of its guarantee retentions and is exposed to bearing the expert costs incurred to establish the failure.
- Final adjustment of air flows to nominal flowCheck the actual flow at each terminal in the bedroom using a calibrated measuring hood. Adjust the fan speed at the unit to guarantee the strict hygienic air change rate without excess flow.
- Checking decoupling and fixingsCheck that no metal duct is in direct contact with a load-bearing structure or a drywall partition. Replace rigid brackets with sound-insulating clamps fitted with neoprene linings.
- Preparing the night-time counter-expertise protocolSummon the acoustician and site management for a joint measurement between 22:00 and 06:00. Switch off any auxiliary household appliance and document the residual noise level before starting the ventilation.
- Joint inspection record and lifting of reservationsRecord the standardised sound pressure at the specified point. If the value meets the requirement of the SIA 181 standard, have the final lifting of reservations entered in the acceptance record of the installation.
Handling refusal of acceptance and lifting acoustic reservations
When the night-time acoustic inspection reveals that the requirements set by the SIA 181 standard for a bedroom have been exceeded, site management records a major defect in the minutes. This finding blocks the release of guarantee retentions under the SIA 118 standard. The ventilation installer must then refuse automatic attribution of the complaint without a methodical check of the test conditions.
- Checking aeraulic balancing: verify in the commissioning report that the supply air flows correspond strictly to the design values, with no overpressure at the plenum.
- Measuring the actual background noise: record the residual sound level with the installation completely switched off, windows closed and neighbouring technical installations stopped.
- Searching for solid-borne sound bridges: visually inspect the flexible sleeves, the anti-vibration duct hangers and the sound-insulating clamps passing through heavy partitions.
- Examining the supply terminals: check the position of the adjustment cone, the absence of cutting burrs and the integrity of the internal damping foam.
If the exceedance persists despite a perfectly hung and regulated network, the corrective work requires inserting a secondary baffle silencer or an absorbent circular acoustic cartridge directly in the terminal section serving the room. Once these modifications are complete, the company appoints an independent acoustician to carry out a joint counter-measurement according to the SIA 181 standard protocol. Only the expert report validated by this night-time measurement allows the reservation to be officially lifted and the acceptance of the work to be closed.
Frequently asked questions
What should be done if the street background noise already exceeds the permissible threshold in the bedroom?
If the outdoor residual level, with windows closed and ventilation stopped, exceeds the requirement of the SIA 181 standard, the acoustician applies the logarithmic subtraction correction method. The installer rigorously records this background noise in the minutes. If the margin between the running installation and the residual ambient noise remains below three decibels, the compliance of the ventilation alone cannot be disputed without a joint measurement during a period of absolute night-time calm.
Where exactly should the sound level meter microphone be placed during a joint acceptance in a bedroom?
The SIA 181 standard prohibits readings in the immediate vicinity of walls or under the air jet of the diffuser. The microphone on a tripod is positioned at a sleeper's ear height, i.e. about 1.20 metres above the finished floor, and more than one metre from partitions or the window. The direct axis of the supply air is avoided to eliminate any parasitic airflow noise on the measuring diaphragm.
Can a motorised regulating damper be enough to correct a night-time whistling noise?
No. A motorised damper regulates a flow setpoint but introduces a local pressure drop that generates turbulence if it is closed too far. If a whistle appears in a bedroom, the solution is to rebalance the overall network, reduce the supply fan speed and fit a flexible or rigid terminal silencer between the duct and the distribution box.
Is the ventilation contractor responsible for transmission noise from one floor to another?
The installer is responsible for complying with the rules of the art on its ducts. If crosstalk occurs between two superimposed or adjoining bedrooms connected to the same manifold, the lack of a crosstalk silencer engages its liability for execution. If, however, the noise passes through a slab opening poorly sealed by the mason, the reservation falls to the structural work package under the SIA 118 standard.
Texts and standards cited
- norme SIA 181Protection against noise in buildings, acoustic requirements for sensitive rooms and measurement procedures
- norme SIA 118General conditions for the execution of construction works, inspection of the work, notice of defects and acceptance
