Key takeaways
- Full bypass requires a minimum difference of two kelvins between outdoor air and indoor extract air.
- A minimum supply air temperature prevents the heating coil from switching on accidentally in the mid-season.
- Night overventilation discharges the building structure only if fan consumption remains under control.
- The on-site test validates the mechanical stroke of the actuator and the perfect tightness of the heat exchanger damper.
Setting the switchover logic and quantifying passive cooling
Bypassing the plate heat exchanger or stopping the rotation of a heat recovery wheel allows outdoor fresh air to be introduced directly without heat exchange with the extract air. Although factory-installed on most air handling unit controllers, this direct cooling function (free cooling) is commonly disabled by default or configured with inconsistent values. Its thermal benefit nevertheless rests on a proven principle: removing the heat stored in the building structure during the day by using the cool night air available.
- Air-side free cooling
- Passive cooling mode that exploits the temperature difference between cool outdoor air and indoor ambient air to cool rooms without using a refrigeration unit.
To allow switchover to full bypass, the controller must validate four logical conditions simultaneously. The extract air temperature in the extraction network must exceed the summer comfort setpoint, commonly set at 23 °C. The outdoor temperature must be at least 2 K lower than this extract temperature in order to offset the mechanical heating induced by the fan motors. The outdoor air must absolutely be above a minimum supply temperature, set between 16 °C and 18 °C to prevent any thermal discomfort or risk of condensation. Finally, the building's cooling demand must be active at the central control level.
| Operating mode | Heat recovery unit position | Airflow applied | Thermal effect on the building |
|---|---|---|---|
| Standard recovery | Exchanger 100 % active | Nominal hygienic airflow | Energy retained, no thermal discharge |
| Daytime free cooling | Modulated bypass (0 to 100 %) | Nominal hygienic airflow | Partial relief of internal heat loads |
| Night overventilation | Bypass 100 % open | Forced airflow of 100 % to 150 % | Massive thermal discharge of slabs and walls |
Night overventilation takes advantage of the rooms being unoccupied between midnight and six o'clock to renew the indoor air massively. By exploiting the specific heat capacity of the reinforced concrete slabs and internal walls, continuous night air flushing lowers the surface temperature of the walls by 1.5 K to 3 K. This phase shift drastically reduces temperature peaks the following afternoon. The installer must however check the specific fan power: a poorly balanced installation consuming more than 1.5 kW per cubic metre per second would cancel the financial benefit through its own electricity consumption.
Mastering the physical operating limits and testing the actuators
The effectiveness of passive cooling is strictly limited by the local climatic conditions of the Swiss Plateau or valley floors. When the outdoor night temperature falls below 14 °C, the bypass damper can no longer remain fully open without causing the supply temperature to drop below the permissible threshold. The controller must then modulate the position of the bypass damper to mix the direct fresh air with the air that has passed through the exchanger. If the outdoor temperature exceeds the extract air temperature during a heatwave day, the bypass must be tightly closed to avoid bringing overheated air directly into the building.
- Mechanical examination of the dampers and linkageCheck the free movement of the blades of the bypass damper and the exchanger damper. Check the mechanical alignment of the linkage rods, the absence of any tight spot on the shaft and the uniform compression of the side sealing gaskets at the end of travel.
- Electrical forcing of the control actuatorTemporarily disconnect the automatic control or switch the controller to manual mode. Apply a command of 0 V and then 10 V to the proportional actuator to check the full stroke between 0 % and 100 % opening.
- Checking the air tightness of the dampersWhen the bypass is 100 % open, make sure the front damper of the exchanger is tightly closed in order to prevent any parasitic leakage. A leakage flow of only 5 % through a warm exchanger immediately degrades the cooling gain sought.
- Cross-calibration of the temperature sensorsMeasure the duct temperature at the fresh air sensor and at the extract air sensor with a calibrated thermometer. A reading offset of 1 K on one of the sensors completely distorts the differential algorithm that triggers the bypass.
During commissioning operations in accordance with the SIA 118 standard, the ventilation installer records these response times and the switchover temperatures in the test report. This traceability guarantees the client that the actuators carry out the sequence without logical conflict with the terminal units.
Switchover conditions and activation of night overventilation
In most air handling units delivered to Swiss construction sites, the bypass damper of the plate heat recovery unit or the drive of the thermal exchange wheel has the algorithms needed for free cooling built in at the factory. Yet during operational audits or acceptance of installations, this function frequently remains inactive. The cause often lies in control loops left on factory parameters, where the switch-on hysteresis prevents any damper movement as an excessive precaution, keeping the building under counter-productive heat recovery in the mid-season and at the height of summer.
To engage the bypass damper without destabilising the air distribution, three simultaneous physical conditions must be met at the air handling controller:
- The temperature measured at the extract (representative of the room environment) is above the summer comfort setpoint, generally set between 22 and 24 °C.
- The fresh outdoor air has a temperature at least 2 K lower than the extract air, guaranteeing a real cooling contribution without any mechanical demand on the chiller.
- The outdoor air temperature is above the minimum permissible limit for direct supply, avoiding cold air falling on the occupants during occupied periods.
The most powerful lever of the system is night overventilation (night cooling). While administrative or school premises usually switch to reduced mode (night-time non-occupancy), the control switches the extract and supply fans to nominal airflow, or even to a higher stage if the acoustic design allows. Between midnight and six o'clock in the morning, this circulation of fresh air without passing through the exchanger removes the heat stored during the day in the concrete slabs and heavy walls. The thermal inertia of the structural work is thus discharged free of charge, delaying the next day's temperature peak by several hours.
External temperature limits and test protocol at commissioning
Operation of the bypass meets two clear limits dictated by building physics. The lower limit blocks the supply of outdoor air below 16 to 18 °C during occupancy to prevent discomfort from draughts and eliminate the risk of condensation on uninsulated supply ducts in the false ceiling. The upper limit applies as soon as the outdoor air exceeds the indoor extract air temperature: the bypass damper must then close tightly to force the fresh air through the heat recovery unit. In this summer inversion situation, the exchanger serves to subcool the scorching fresh air through contact with the cooler extract air.
| Thermal regime | Outdoor air condition (Text) | Heat recovery unit position | Bypass damper state |
|---|---|---|---|
| Winter / cold mid-season | Text < 14 °C | Active (100 % exchange) | Tightly closed |
| Daytime free cooling | 18 °C < Text < Textract - 2 K | Inactive (0 % exchange) | 100 % open |
| Night cooling (night) | 15 °C < Text < Textract - 2 K | Inactive (0 % exchange) | 100 % open (forced airflow) |
| Heatwave / Inversion | Text > Textract | Active (coolness recovery) | Tightly closed |
The functional test of the switchover during the operations preceding acceptance of the work is the responsibility of the ventilation installer. This methodical check guarantees that the equipment meets the technical requirements without hidden losses.
- Visual and mechanical check of damper travelSwitch the installation off. Manually disengage the actuator of the bypass damper. Operate the linkage from 0 to 90 degrees to check that there is no tight spot and that the side sealing gaskets sit perfectly against the sheet-metal stops.
- Software simulation of the setpoint temperaturesConnect the configuration tool or force the temperature sensor inputs using calibrated resistors. Simulate a room temperature of 25 °C and an outdoor temperature of 17 °C. Check the 0-10 V or 3-point control signal delivered by the controller to the actuator.
- Dynamic check of pressures and tightnessStart the fans at nominal airflows. Check that the damper switches physically without slamming under the differential pressure. Measure the air temperature immediately downstream of the exchanger casing: any abnormal temperature rise confirms an internal leak due to defective sealing of the closed bypass.
Diagnosing and correcting bypass failures in operation
On balanced-flow ventilation installations, the absence of passive cooling almost always comes from a measurement inconsistency or a mechanical blockage not detected by the control. When occupants complain of morning overheating despite cool nights, the technician must analyse the data acquisition chain before blaming the algorithms.
- Checking the duct sensorsUse a reference thermometer to measure the real difference between the outdoor air temperature at the fresh air intake and the air drawn from the extract duct. A 1.5 K offset on a passive sensor is enough to lock the bypass damper control loop.
- Checking mechanical stroke and tightnessRemove the access panel of the heat recovery unit to inspect the linkages. On-off or progressive 0-10 V actuators may indicate full opening on the building management system while the damper remains mechanically restricted by a dust deposit or a shaft misalignment.
- Validating the switchover threshold and humidityCheck whether an inhibit setpoint based on low outdoor temperature blocks the opening. If the lower limit is set above 16 °C instead of 12 °C, the unit never switches on night overventilation during the usual Swiss summer nights.
If the problem persists, manually force the analogue control signal to 10 V from the controller to isolate the fault: an actuator that groans without turning betrays insufficient motor torque against the air pressures. Under the SIA 118 standard, the installer reports any air-side design anomaly compromising the performance of the work. In accordance with art. 365 CO, the contractor notifies the client if a circumstance attributable to the existing equipment compromises the proper conduct of the tests.
Frequently asked questions
Why does the unit refuse to bypass when the outdoor air is cooler than the room?
The control generally includes several conditions interlocked simultaneously: a minimum temperature difference of at least 2 K between extract and fresh air, an indoor temperature above the comfort setpoint, and a minimum safety outdoor temperature, often set at 12 °C. If the fresh air falls below this lower limit or if the room sensor drifts, the controller immediately blocks the opening of the bypass dampers to avoid thermal discomfort.
How can the bypass damper actuator be tested without waiting for the night?
Switch the local controller to test or manual mode via its operator interface. Then inject a forced command value of 100 % on the analogue output driving the damper. The installer visually observes the dampers switching fully in less than 90 seconds, checks that there is no mechanical jamming on the linkages and verifies the 2-10 V feedback signal sent to the supervision system.
What airflow should be applied during night overventilation of a commercial building?
To obtain a real thermal effect on the building structure, the night airflow must be increased to between 100 % and 150 % of the basic nominal hygienic airflow. Running the installation at the minimum unoccupied airflow of 30 % does not remove the heat load accumulated in the concrete slabs. The external acoustics should however be monitored to comply with the night-time noise limits for the neighbourhood.
Does rotary heat recovery require a separate bypass damper?
No, on rotary exchangers, the bypass function is obtained simply by stopping the rotation of the thermal wheel completely. The flow then passes through the matrix without significant sensible exchange or latent transfer. The technician must however make sure that the drive motor stops perfectly on command and that the periodic automatic cleaning purge does not warm the supply air during the night cycles.
Texts and standards cited
- norme SIA 118General conditions for the execution of construction work
- CO art. 365Material and ground: the contractor is responsible for the good quality of the material he supplies; if the material supplied by the client or the ground designated by him is found to be defective, or if another circumstance compromises the proper or timely execution of the work, he must inform the client immediately, failing which he bears the consequences (para. 3).