🧱 CFC 244Air handling unit and heat recoveryChapter 10 of 10 in the section

Installing a rooftop air-handling unit: lifting, slinging and permissible load

This chapter details the technical and safety requirements for successfully craning a ventilation casing onto a slab or technical roof. You will know how to coordinate the load-bearing check with the civil engineer, draw up the lifting plan, mark out the exclusion zone on the ground and rig the machine according to the factory instructions.

Key takeaways

  • Written validation of the permissible load by the civil engineer is a precondition for any placement on the roof.
  • The lifting plan specifies the working radius of the crane and the access routes for the delivery vehicles.
  • The exclusion zone on the ground remains physically cordoned off throughout the entire aerial transfer operation.
  • Slinging is carried out exclusively on the dedicated anchor points using a spreader beam suited to the dimensions of the unit.

Validating the permissible load and orchestrating the lifting plan

Placing a single-block extract and supply unit weighing eight hundred kilos on an upper slab is not something to improvise on the morning of the operation. Before even ordering the mobile crane or reserving the use of a tower crane on the construction site, the ventilation fitter must have written confirmation from the civil engineer certifying the permissible load. The analysis is not limited to the gross mass of the machine shown on the rating plate. It includes the actual operating weight: the counter-flow or rotary heat recovery coils, the motors, the reaction fans, the factory-fitted silencers, as well as foreseeable additional loads such as possible water retention in the condensate trays or future snow accumulation on the casing.

The civil engineer defines the precise position on the roof and validates the sizing of the concrete bases, steel rails or anti-vibration pads. The role of these structural interfaces is to distribute the point loads onto the load-bearing elements of the building in order to avoid any punching of the thermal insulation or perforation of the bituminous waterproofing. If final access requires sliding the unit across the roof from the crane's set-down zone, the temporary route must undergo the same structural verification, with load-spreading plates provided where necessary to relieve the insulation build-up.

The lifting plan is the central document linking the ventilation company, the crane operator and the site management. Drawn up in consultation with the haulier and the mobile crane operator, it sets the geometric constraints of the site: maximum jib reach, working angle, residual hoist capacity at the axis of the base, clearance with regard to parapets and overhead power lines. This document also records the bearing pressure of the crane outriggers on the road or the building's courtyard, which often requires formal authorisation from the public authorities for occupying the carriageway.

  • Manufacturer data sheet specifying the centre of gravity and the actual weight in working order.
  • Civil engineer's calculation note confirming the mechanical strength of the slab under static and dynamic load.
  • Municipal or cantonal authorisation for parking the mobile crane and temporarily closing the carriageway.
  • Roof layout plan showing the exact orientation of the fresh-air and exhaust connections to avoid any hazardous rotation in the air.

Ground marking-off and slinging in accordance with the manufacturer's requirements

As soon as the delivery lorry arrives on the construction site, the ground crew sets up an absolute exclusion zone. The marked-off perimeter encompasses the parking area of the mobile crane, the full swing radius of the counterweight, the access area for the delivery vehicle and the overflight path of the air-handling unit up to its position on the roof. The boundary does not rely on simple barrier tape: it uses rigid site barriers or guide chains with formal prohibition signs. No worker or passer-by may enter beneath the moving load, in accordance with the requirements of SUVA and the OTConst relating to the risks associated with mechanical handling.

  1. Checking the lifting accessoriesCheck the validity of the textile slings or four-leg chains, the absence of cuts or wear, the presence of the working load limit tags and the perfect condition of the connecting shackles.
  2. Installing the spreader beamInsert a tubular or steel-section lifting spreader beam to ensure that the vertical legs pull at right angles without crushing the unit's roof panels or twisting the structural sections.
  3. Attaching to the original lifting pointsEngage the shackles exclusively in the lifting lugs welded to the load-bearing frame or in the specific bores of the base frame provided by the manufacturer.
  4. Lift-off and balance testLift the machine ten centimetres off the lorry bed to check that it is perfectly level, that the crane brake holds, and that the load is properly distributed relative to the offset centre of gravity.

The main point of vigilance lies in the geometry of the casing. A dual-flow air-handling unit incorporates asymmetric components: the exchanger block and the ventilation motors concentrate the masses on one side, shifting the centre of gravity away from the geometric centre. Using adjustable chains with shortening hooks makes it possible to adjust the length of the legs to obtain a strictly horizontal attitude from the moment of lift-off. Any improvised slinging by tightening directly around the front panels or hooking onto the rings of the internal fans is prohibited, as it risks twisting the casing, breaking the airtightness of the walls and jamming the control dampers.

The aerial manoeuvre is carried out under the responsibility of a designated lifting supervisor, equipped with a dedicated radio link to the crane operator if direct visual contact is lost when setting down behind a parapet. Two guide ropes of sufficient length, attached to the ends of the frame, allow the fitters to control the orientation of the machine without ever placing their hands directly on the suspended load. Landing on the vibration isolation pads is done gently to preserve the levelling of the machine and ensure the subsequent gravity drainage of the condensate trap.

Approaching the roof and transferring the load onto the technical bases

The critical phase of the lift begins when the parapet is cleared. An eight-hundred-kilo unit suspended from the jib of a mobile crane reacts immediately to thermal gusts and the channelling effects common on a flat roof. The load is guided exclusively by hemp or polypropylene guide ropes at least fifteen metres long, secured to the ends of the frame before lift-off. It is forbidden to grab the casing of the unit or the aluminium sections directly while the lifting cable is under mechanical tension.

Transferring point loads requires rigorous vigilance with regard to the waterproofing build-up and the underlying thermal insulation. According to the rules of standard SIA 271, the frame of an air-handling unit never rests directly on the waterproofing membrane. The eight hundred kilos of the machine, increased by the operating loads and by the uplift or overturning effects caused by wind, must be distributed via a frame of galvanised metal sections or decoupled concrete blocks resting on suitable load-spreading plates.

Critical support points and mass distribution for an 800 kg single-block unit
Unit componentEstimated share of massImpact on supportsCompensating measure
Fan / motor section45 % (approx. 360 kg)High dynamic point loadReinforced-stiffness anti-vibration pads on the discharge side
Plate heat recovery unit30 % (approx. 240 kg)Constant medium static loadLoad-spreading rails on continuous elastomer pads
Filter and damper section15 % (approx. 120 kg)Low static load, upstream wind exposureMechanical hold-down brackets against uplift
Heat exchange coils and casing10 % (approx. 80 kg)Off-centre mass on the air-connection sidePrecision shimming before tightening the flexible sleeves

Setting down, unslinging and mechanically stabilising the machine

  1. Millimetre-precise approachThe unit is held steady ten centimetres above its anti-vibration pads. The fitters check that the fixing holes of the frame coincide perfectly with the roof plates, never putting their fingers under the structure.
  2. Gradual transfer of the weightThe crane operator lowers the jib slowly in steps of two centimetres. The lifting supervisor checks the uniform compression of the anti-vibration pads until the lifting slings are completely slack.
  3. Checking levels and condensate fallsImmediately check the longitudinal and transverse flatness with a precision spirit level. A slight fall towards the outlet of the condensate tray is required according to the manufacturer's instructions to ensure perfect drainage without stagnant water being retained.
  4. Unslinging with no load on the slingsUnhook the shackles only when the cables and slings are completely slack and the machine is judged stable on its final supports.

Unslinging exposes personnel to severe risks if the roof does not have complete perimeter guardrails compliant with the OTConst. Fitters working on top of the unit or at the edge of the parapet must be protected against falls from height. As soon as the crane hook is released, the team fits the seismic and anti-overturning safety brackets. These metal brackets, mounted with a calibrated clearance and no rigid sound bridge, prevent the single-block unit from shifting or overturning under dynamic storm pressures without short-circuiting the anti-vibration isolation.

The lifting phase ends with a careful visual inspection of the double-skin panels and the surrounding roof: integrity of the factory seals, absence of deformation of the sections at the slinging points, and cleanliness of the bearing area. Any damage found to the roof covering must be reported immediately to the site management and to the waterproofing contractor before starting the duct connections.

Handling lifting contingencies, damage and emergency withdrawal

On a flat roof, craning an air-handling casing leaves no room for improvisation in the face of unforeseen events. When weather conditions suddenly deteriorate, when the crane operator notices abnormal wind exposure, or when an unnoticed obstacle prevents landing on the upstands, the rule is to stop the manoeuvre immediately. The lifting supervisor on the ground and the fitter on the roof must apply the coordinated safe-stop procedure without attempting to force any adjustment.

  1. Detecting a non-conformity of the supportIf positioning reveals misalignment of the anti-vibration pads or excessive deflection of the slab that was not anticipated by the site management, the fitter stops the placement. The unit remains guided by the ropes without relaxing the tension in the slings.
  2. Taking the load back and stabilisingIf immediate placement is not possible, the unit is brought back to the waiting area on the ground, previously stabilised on load-spreading timber planks. No makeshift packing is improvised on the roof waterproofing.
  3. Checking the slinging componentsAny impact on a lifting ring, any deformation of a spreader beam or any rubbing of a sling against a panel requires the accessory to be scrapped and the machine's frame to be visually checked before any new attempt.

Resuming operations requires consultation between the site manager and the civil engineer responsible for the load-bearing structure. If the verified permissible load of the roof gives rise to the slightest technical doubt after a placement has been started, work is postponed until written validation is given. Any change to the working radius of the crane or to the distribution of masses on the waterproofing requires the formal updating of the lifting plan before the teams resume work.

Frequently asked questions

What should be done if the wind speed exceeds the threshold set by the lifting plan?

The manoeuvre must be stopped without discussion. A ventilation unit presents a massive wind surface that destabilises the hook and endangers the fitters during guiding. If the load is being raised, the crane operator lowers it onto the unloading area on the ground. The team leader records the stoppage due to bad weather in the site log until conditions comply with the safety guidelines.

Why is it prohibited to sling the unit directly on its structural sections?

The double-skin panels and the aluminium uprights are designed for airtightness and thermal insulation, not to take vertical lifting forces. Direct slinging crushes the framework, deforms the casings and compromises the seal bearing surfaces. Only the dedicated anchor points welded to the load-bearing frame, or the use of a spreader beam with cross-members beneath the machine, ensure that the force is taken up in accordance with the technical requirements of the ventilation equipment manufacturer.

How should one react if confirmation of the permissible roof load is missing on the day of the crane lift?

The fitter carries out no lifting whatsoever. Even if the lifting team and the mobile crane are in place on the public road, placing a heavy casing without the written approval of the civil engineer jeopardises the stability of the structure. The site manager must demand formal approval of the load paths onto the trimmer joists or main beams before giving the start signal to the crane operator.

What measures should be taken to mark out the exclusion zone beneath the lifting radius?

The footprint on the ground must be completely enclosed using rigid physical barriers and clear marking-off prohibiting the passage of people during the manoeuvres. A dedicated banksman monitors the access points and diverts pedestrian or vehicle traffic. Overflying occupied site accommodation, open routes or workers not protected by the lifting plan is strictly forbidden under the safety requirements.

Texts and standards cited