Key takeaways
- Every installed damper must undergo a complete individual test before the false ceilings are closed.
- Mechanical or thermal release confirms that the blade closes freely without friction.
- The open-position and closed-position microswitches ensure reliable signalling to the control panel.
- The named test report for each damper is the legal proof required by the VKF/AEAI fire protection guidelines.
Carrying out the individual mechanical and thermal release test
On a ventilation construction site, careful installation of a fire damper says nothing about how it will actually work under airflow or at rest. A crushed collar during mortar sealing, a self-drilling screw that is too long and protrudes into the casing, or a deposit of plaster dust on the seating surfaces is enough to jam the blade in a half-open position. The fire protection guidelines of the Association of Cantonal Fire Insurance Institutions impose an obligation to achieve a result: every compartmentation device must seal the penetration tightly as soon as it is activated.
The individual release test is carried out damper by damper, without any statistical sampling. Two activation modes must be tested depending on the damper's equipment: breaking the thermal fuse or using its manual test button for spring mechanisms, and the electrical power-cut command for spring-return actuators.
- Visual inspection through the inspection hatchOpen the access hatch on the duct or on the damper body. Check that there is absolutely no rubble, protruding screws or cement dust in the path of rotation of the blade and along the intumescent seals.
- Release of the closing mechanismFor a mechanical damper, press the test button that simulates the melting of the thermal fuse at 72 °C. For a motorised model, cut the electrical holding supply to the actuator.
- Checking travel and tightnessObserve the path of the blade. It must pivot smoothly, without jerks or metallic rubbing, until it comes firmly against the elastomer perimeter seal.
Resetting, validating status signals and recording the test report
A flawless closure is only half of the test procedure. The ventilation fitter must also ensure the mechanism is fully reset and that the status feedback microswitches physically change state. A badly engaged contact sends false safety information to the building management system, preventing authorisation to start the air-handling units.
On a manual mechanism, resetting is done by turning the handle or external lever until the pawl locks mechanically. This operation compresses the internal coil spring. On an actuator-driven damper, restoring the electrical voltage engages the motor, which resets the blade to its open position while compressing its internal safety spring. In both cases, the technician uses a multimeter to check that the dry circuit corresponding to the open operating position is closed.
- Limit-switch microswitches
- Position switches built into the damper housing, potential-free, mechanically indicating the actual state of the blade: damper fully open or damper fully closed. An intermediate status is not tolerated.
All these findings must be recorded in a formal document drawn up by the ventilation fitter. This document legally binds the company within the meaning of art. 364 CO, under which the contractor is liable for the proper and faithful execution of the work entrusted to it. A damper for which no individual test report is provided is legally considered defective by the fire protection authority.
| Protocol item | Data to be entered | Acceptance criterion |
|---|---|---|
| Physical identification | Damper number on the ventilation plan | Exact match with the marking engraved on the body |
| Location on site | Building, floor, room crossed, fire-rated wall | Physical position accessible from the floor |
| Release test | Time, date and method (test button or 24V/230V power cut) | Complete closure with no mechanical jamming observed |
| Position signals | Switching of the open/closed limit-switch contacts | Clear signal verified with a multimeter or on a test box |
| Fitter's signature | Name in block letters, CFC 244 company, operator's initials | Validation before formal handover of the installation |
Correcting travel anomalies and compliance with the VKF/AEAI fire guidelines
Unit testing on the construction site forgives no geometric defect. A fire damper delivered from the factory with its certificate of conformity can lose all effectiveness if mortar or plaster sealing has deformed its casing, or if the suspension rods have applied a twisting stress to the sheet metal. On release, the blade pivots on its axis under the action of the return spring or the spring-return motor. If the friction exceeds the available mechanical torque, the blade stops in an intermediate position. According to the VKF/AEAI fire guidelines, air-duct compartmentation offers no partial resistance: a partly open blade is equivalent to an open opening through a fire-rated wall, allowing hot gases and toxic smoke to pass instantly towards the escape routes.
| Finding during the test | Mechanical or installation cause | Corrective measure CFC 244 |
|---|---|---|
| Blade stuck half-way during thermal release | Casing crushed by sealing mortar or through-screw too long | Free the damper body, check the internal dimensions with a calliper, remove the faulty fixing |
| Closed limit-switch contact fault | Misaligned microswitch, linkage cam bent by an impact on site | Adjust the actuating tab of the auxiliary microswitch, check continuity with an ohmmeter |
| Slow or hesitant closing of the mechanism | Plaster dust on the axis bearings, altered spring tension | Vacuum the entire interior, wipe the bearings without greasy lubricant that attracts soot |
| Unwanted release on motorised reset | Thermoelectric fuse element cracked or badly seated in its housing | Replace the fuse cartridge, check that the probe is clipped correctly in the airstream |
Validating the reset is the second, inseparable phase of the test. On an actuator-driven model, the operator checks the complete reset time under voltage and confirms that the dry open-position contact switches cleanly. On a manually reset damper, locking the trigger must produce a clear audible engagement, with no tight spot on the handle or knob. The technician checks visually, through the tight inspection hatch required upstream or downstream, that the blade sits perfectly parallel to the airflow so as not to create parasitic pressure loss in normal operation.
Drawing up the unit test report and traceability for operation
The VKF/AEAI fire guidelines and the recognised rules of the trade formally exclude sampling checks. Every fire damper installed in a building must have its unique identifier engraved or labelled indelibly on its casing and entered on the ventilation as-built plans. This identifier links the device to the safety synoptic panel and to its dedicated line in the test report. If a fire occurs years after the work has been handed over, the ventilation system installer must be able to provide material proof that the damper concerned was physically tested, operated and certified in working order when the installation was handed over.
- Unit identification of the device (plan identifier, floor, room crossed and duct section number).
- Technical characteristics read from the manufacturer's plate (VKF/AEAI approval number, fire resistance class, nominal dimensions, date of manufacture).
- Type of release tested (mechanical by thermal fuse or thermoelectric by safety motor).
- Closing test result (closing speed, visual tightness of the blade, absence of residual friction).
- Check of the electrical signalling contacts (actual switching of the closed-position and open-position signals).
- Date of the test, full name of the responsible fitter and initials of the site management.
The individual test report is then included in the operating file handed over to the owner of the building, in accordance with the requirements of the SIA 118 standard at the acceptance of technical installations. This record forms the basis of the periodic maintenance log. The building operator subsequently records in it the annual statutory inspections prescribed by the cantonal building insurance and the fire protection authority. A report without spatial identification or without countersignature is legally void in the event of an expert investigation after a fire. The documentary rigour of the ventilation fitter is the only enforceable evidence showing strict compliance with the recognised rules of the trade on the day of commissioning.
Handling test anomalies and traceability for acceptance
When a damper fails to release during the individual test or stays stuck half-way, the whole air-duct section is considered vulnerable. Forcing the mechanism or validating the report in advance is out of the question. According to the VKF/AEAI fire guidelines, each compartmentation device must systematically prove its actual tightness on site. A slipping actuator or a restrained return spring generally betrays a misalignment or a deformation of the duct under the weight of the downstream ducting. The installer records the failure on the unit sheet, stating the work reference.
- Check the casing geometry and the fixingsMeasure the diagonals of the metal casing with a square and a tape measure to detect twisting induced by the hangers or the fire sealing. Disconnect the flexible connector to check whether the blade turns freely again under the action of the spring alone.
- Check the microswitches and limit-switch signalsOperate the release cam by hand to observe the physical switching of the dry contacts. If the closed-position signal is not relayed to the spare terminal block, readjust the cam without forcing the contact blades.
- Carry out the complete re-test and update the test reportCarry out a new mechanical or electrical release followed by a complete reset of the mechanism. The self-inspection report is then countersigned with a detailed note of the corrective work before final transmission to the site management.
The as-built file includes each unit test report, the principle diagram, the ventilation plan showing the dampers and the installer's installation certificate. This binder is the documentary proof required at acceptance of the work under the SIA 118 standard and for all later periodic audits by the fire protection authority.
Frequently asked questions
What should be done if the damper closes correctly but the limit-switch contact does not switch?
A signalling fault blocks acceptance of the installation. Open the inspection hatch and operate the damper by hand to inspect the mechanical cam that actuates the microswitch. Often the cam is loose on the axis or dust is blocking the plunger. Clean dry, retighten the cam screw and test electrical continuity with a multimeter before validating the unit test report.
Can a thermal fuse that has tripped be reused to test the mechanical damper?
No. Bimetallic or glass-bulb thermal fuses melt or burst under the effect of heat and are destroyed. For the individual release test, the installer uses the lever or mechanical test button provided by the manufacturer on the external housing. If a fuse has been damaged or tripped by mistake, it must be replaced with an identical certified original part before any reset.
Who must attend the damper release tests on a Swiss construction site?
The ventilation installer first carries out the full self-inspection and fills in the report for each identified damper. The official acceptance tests then take place in the presence of the site management and, depending on the building class, of the fire quality assurance officer designated under the VKF/AEAI fire guidelines. Joint signature of the document on site binds the company and validates the compliance of the air-duct compartmentation.
What document must be provided if a damper is not accessible during the tests?
An inaccessible damper is a work that has not been accepted. The installer must issue a written reservation to the site management. If third-party services hide the inspection hatch or the reset axis, access must be cleared before the inspection. The report cannot be issued with a note stating that access was impossible: each device must be tested individually and documented, failing which operation of the ventilation system is prohibited.
Texts and standards cited
- SIA 118General conditions for the execution of construction work, acceptance of the work and handling of defects
- Directives incendie AEAISwiss fire protection regulations governing quality assurance and fire-rated closures