Key takeaways
- A leaky network wastes fresh air flow directly into the ceiling void.
- SN EN 12237 classifies circular networks from A to D according to their permeability.
- The pressure test must be carried out before the removable or fixed suspended ceilings are installed.
- The report records the developed surface area, the test pressure and the measured leakage flow.
SN EN 12237 airtightness classes and the real cost of leaks in the ceiling void
In a balanced-flow ventilation system, supply air represents costly thermal and mechanical energy. When duct networks have jointing defects, the treated air escapes into the technical voids and ceiling voids instead of ventilating the living or working rooms. An air loss of 15 % forces the air-handling unit to overconsume to meet the hygienic flow rates at the terminals, which degrades the efficiency of the heat recovery and the building's Minergie balance.
- Leakage limit factor (fmax)
- Maximum permitted air flow per unit of wall area of the ventilation network, expressed in cubic metres per second per square metre, calculated according to the standardised static test pressure.
The standard SN EN 12237 governs the airtightness of circular sheet steel ducts, while rectangular ducts fall under the corresponding standard of the same field. In standard commercial or residential buildings in Switzerland, class B is the minimum level commonly accepted by tender specifications, but class C is systematically required for high-performance installations, high-pressure networks or ducts passing through unheated rooms.
| Airtightness class | Air leakage limit (fmax in m³/(s·m²)) | Relative leakage ratio | Typical use in ventilation |
|---|---|---|---|
| Class A | 0.027 × pt^0.65 × 10^-3 | 3.0 | Low-pressure networks, unfinished plant rooms |
| Class B | 0.009 × pt^0.65 × 10^-3 | 1.0 (reference) | Standard comfort installations |
| Class C | 0.003 × pt^0.65 × 10^-3 | 0.33 | Medium-pressure networks, Minergie-P requirements |
| Class D | 0.001 × pt^0.65 × 10^-3 | 0.11 | Clean rooms, hospitals, laboratories |
A leaky network causes air balancing problems that cannot be resolved during commissioning. The fan compensates for the pressure drop by increasing its rotation speed, which causes noise at the dampers and impairs the efficiency of the supply fan unit. Airtightness must be treated as a measurable construction parameter and not as an adjustment variable.
Site measurement protocol and drawing up the test report
The leakage test must be carried out on representative sections or on the whole route before the thermal insulation is installed and imperatively before the suspended ceilings are closed. If the test reveals an inadmissible leak when the plasterboard or metal tiles are already fixed, locating the whistling sounds requires destructive openings that damage the finishing work, causing significant programme delays.
- Isolating the sectionRemove or isolate fragile terminal components. Seal the duct ends, branch connections and diffuser outlets using inflatable rubber balloons or rigid, airtight, clamped plugs.
- Calculating the surface areaRecord the diameter or perimeter and the exact length of each element under test in order to determine the total developed surface area, in square metres, of the section being tested.
- Connecting the test equipmentConnect the pressurisation unit, fitted with a calibrated measuring fan and a calibrated differential pressure gauge, via an airtight hose to a dedicated branch connection.
- Pressurisation and readingInject air until the specified test pressure is reached (generally the nominal operating pressure plus the standard margin). Hold the pressure stable for the required duration and record the injected air flow, which exactly compensates for the leakage.
- Leak detection when the limit is exceededIf the leakage flow exceeds the permissible limit of the target class, locate the leaks using a cold smoke generator or a neutral foaming liquid applied to the joints.
Technical validation requires the immediate drawing up of an airtightness test report. This document, signed by both parties, states the construction site details, the precise location of the section on the plan, the developed surface area subjected to the test, the target class under SN EN 12237, the test pressure in pascals, the maximum permissible leakage rate and the measured result. It is co-signed by the installation foreman and the site management.
The Code of Obligations governs the inspection of the work: under art. 367 CO, after delivery, the client must inspect the state of the work as soon as it is able to and notify the contractor of any defects. The airtightness test report is the material proof that the ventilation work handed over complies with the rules of the trade before the other trades conceal the installations.
Coordination on the construction site: testing before the suspended ceilings are closed
The schedule of a ventilation construction site tolerates no delay in the airtightness test. Carrying out the ventilation check under SN EN 12237 after the plasterboard has been fitted or the metal tiles clipped in turns a routine operation into a heavy dispute. As soon as the hangers support the main section and the floor branch connections, but imperatively before the plasterer or ceiling fitter closes off the ceiling void, the ventilation installer must lock in the inspection milestone.
A circular or rectangular network assembled carelessly can let up to 15 % of the supply air flow escape directly into the ceiling void. The client pays to treat, filter and heat a volume of air calculated for the hygienic air change of prime rooms such as offices or hotel bedrooms. When this air escapes above the plasterboard through poorly crimped joints, badly positioned self-drilling screws or missing sealant, the air-handling unit compensates by increasing its rotation speed. The installation consumes a constant surplus of electricity to ventilate an uninhabited technical space, while also risking parasitic whistling audible to the occupants.
Planning must include the sample sections or the entire network according to the requirements of the award specification. In the case of a works contract subject to SIA 118, the contractor notifies the site management of the test date sufficiently in advance for it to attend the pressurisation. The surrounding thermal or fire insulation of the ducts must not be applied before the test either: mineral wool masks porosities and disjointed fittings without guaranteeing lasting airtightness under pressure.
Leakage test failure, acoustic location and compliant test report
When a network fails the pressurisation test, the air flow injected by the generator to maintain the test pressure exceeds the limit value set by SN EN 12237 for the specified class. The team leader must then proceed methodically to identify the defects without dismantling the entire network. Static pressurisation to 200, 400 or 1000 Pascals produces a clear whistle at major point leaks, while the use of an artificial smoke generator makes it possible to visualise diffuse defects along longitudinal seams or on connection clamps.
| Airtightness class | Leakage limit factor (fmax) | Typical building application | Usual test pressure |
|---|---|---|---|
| Class A | 0.027 × pt^0.65 l/(s·m²) | Low-pressure extract networks, unfinished plant rooms | 200 Pa |
| Class B | 0.009 × pt^0.65 l/(s·m²) | Minimum standard for commercial and residential distribution | 400 Pa |
| Class C | 0.003 × pt^0.65 l/(s·m²) | Common requirement for high energy performance buildings | 400 to 1000 Pa |
| Class D | 0.001 × pt^0.65 l/(s·m²) | Laboratories, clean rooms, specific hospital applications | 1000 Pa |
- Airtight isolation of the sectionRemove the terminal units, dampers and sensitive measuring devices. Fit inflatable blanking balloons or metal blanking plates with rubber seals at the ends of the section to be tested.
- Locating and repairing airtightness defectsInspect the spigot-and-socket joints, the branch connection bases and the frames of rectangular ducts. Replace perforated flexible connectors, retighten the clamps and apply an acrylic sealant or an approved heat-shrink tape to the leaking joints.
- Retest and recording of measurementsPut the section back under the required test pressure. Stabilise the pressure for at least five minutes and record the leakage flow measured by the orifice flow meter of the test unit.
- Validation of the airtightness test reportComplete the technical document with the tested developed surface area, the test pressure, the measured leakage rate compared with the permissible value of SN EN 12237, and obtain the signatures of both parties.
The airtightness test report is an indispensable contractual document at the final account and the acceptance of the work. Under art. 364 CO, the contractor is liable for the proper execution of its work and must deliver a network that complies with the recognised rules of the building trade. When the ventilation engineer or the site management requires a class B or C network to meet the building's energy balance, the airtightness certificate attached to the as-built file attests that the ventilated air reaches the occupants in full, without hidden losses.
Handling airtightness non-conformities and rectification before acceptance
A measured leakage flow above the limit set by SN EN 12237 is an execution defect that blocks the continuation of the finishing work. When the pressurisation unit indicates a failure for the target class, the installer must refuse any authorisation to close the suspended ceilings. If plasterboard is fitted over a leaky distribution, the heated or cooled air is lost in the ceiling void instead of supplying the occupied rooms, which distorts the final air balance results.
- Locating individual leaksPut the section under a pressure of 200 Pa, switch off the ambient noise sources on the construction site and spray a neutral foaming liquid on the flanged frames, the spigot-and-socket joints without factory seal and the saddle branch connections.
- Mechanical repair and sealingRetighten the assembly clips at the corners, replace seals damaged by the self-drilling screws and apply a certified acrylic or polyurethane sealing compound to the faulty joints.
- Retest and validationObserve the full curing time of the sealants, refit the inflatable blanking balloons, repeat the measurement at the contractual test pressure and record the positive result on the airtightness test report.
In the event of a dispute with the site management, CO para. 2 allows the client, if it is certain that the work will be executed defectively or contrary to the agreement through the contractor's fault, to set a reasonable deadline, notifying the contractor that, after this deadline, the repairs or the continuation of the work will be entrusted to a third party at the contractor's expense and risk. The initially non-compliant airtightness test report, countersigned by both parties, then serves as a technical document agreed by both sides to justify the plasterer's delayed intervention.
Frequently asked questions
Which airtightness class should be chosen for a standard commercial ventilation network?
SN EN 12237 defines classes A to D. For a standard commercial building or a Minergie dwelling, class ATC 3 (equivalent to the former class C) is the usual rule prescribed in tenders in French-speaking Switzerland. Class ATC 4 (class B) is sometimes still accepted for very short small terminal networks, but it allows three times more leakage, which heavily penalises the electricity consumption of the fans.
Why test the ventilation network before the suspended ceilings are closed?
Testing before the suspended ceilings are closed avoids disproportionate rectification costs. Once the partitions and plasterboard are screwed in place, locating an air whistle requires inspection cameras or partial removal of the linings. Testing the bare ventilation section gives direct access to the flanges, allows the necessary sealing products to be applied without constraint and allows the airtightness test report to be validated by the site management before the plasterers and painters start work.
How should sensitive components be isolated during the pressure test?
Fire dampers, terminal control dampers, water coils and diffusion terminals do not always withstand the test pressure of 200 to 500 Pa. The ventilation installer must remove these units or fit airtight pneumatic blanking bladders directly upstream. The main network in spiral or rectangular sheet metal is thus isolated from the terminal equipment so as to measure exclusively the intrinsic permeability of the ducts and their joints.
What should be done if the section repeatedly fails the leakage test?
If the leakage rate exceeds the permitted threshold after superficial sealing, the network must be segmented. Fitting intermediate blanking balloons makes it possible to test the branches separately to identify the faulty sub-network. The error frequently comes from circular accessories without factory double-lip seals, assembled with simple untreated adhesive tape that has come unstuck, or from poorly crimped rectangular frame corners requiring a reinforcing angle.
Texts and standards cited
- SN EN 12237Ventilation for buildings - Ductwork - Strength and leakage of circular sheet metal ducts
- COdelay and foreseeable defective execution: if the contractor does not begin the work in time, delays its execution, or if the delay is such that it can no longer complete it by the agreed date, the client may withdraw from the contract without waiting for the agreed deadline (para. 1); if it is certain that the work will be executed defectively or contrary to the agreement through the contractor's fault, the client may set a reasonable deadline, notifying the contractor that, after this deadline, the repairs or the continuation of the work will be entrusted to a third party at the contractor's expense and risk (para. 2).