🧱 CFC 244Commissioning, measurement and air flow balancingChapter 7 of 10 in the section

Maintenance: frequency per component, measured points and a useful contract

This chapter details how to structure a ventilation maintenance contract and carry out preventive visits. You will know how to define the real frequencies per component, equip your flow and differential pressure readings, test fire dampers methodically and record findings in a traceable, legally enforceable technical report.

Key takeaways

  • A contract without a detailed designation of filters and dampers creates no precise technical responsibility.
  • Frequency ranges from quarterly for pre-filters to yearly for heat exchangers and motors.
  • Each visit requires physical measurements of pressure drop, current and airflow.
  • Testing each fire damper individually requires an actual release and a signed record.

List every component and its frequency to make the contract enforceable

A ventilation maintenance contract that merely promises an "overhaul in accordance with the rules of the trade" deprives both the technician and the owner of any enforceable technical reference. The contract for work and services, within the meaning of art. 363 CO, requires a precisely defined performance in order to assess the execution of the work. The contractor's obligations, recalled in art. 364 CO, impose a technical duty of care that cannot be assessed without an exhaustive inventory of the air handling unit, the ducting and the terminal devices. Without an item-by-item designation of wear parts, the client does not know what they are paying for and the fitter cannot justify invoicing for specific filter supplies.

Service frequencies and minimum operations per component
Air handling componentStandard frequencyRequired technical operation
Fresh-air pre-filters (coarse)Every 3 to 6 monthsDelta-P measurement, systematic replacement without dusting off
Fine filters (supply ePM1)Every 6 to 12 monthsVisual inspection, fouling measurement, replacement at threshold
Heat recovery unit (plate / wheel)AnnualComb cleaning or low-pressure steam cleaning, belt inspection
Motor-driven fans (EC or belt)AnnualAlignment check, belt tension, terminal tightening
Condensate tray and trapSix-monthlyDisinfection, sludge removal, water seal check
Air treatment coilsAnnualFin vacuuming, connection tightness check
Mechanical fire dampersAnnualIndividual release, blade dusting, manual reset

The replacement rate of filtration stages depends on the building's outdoor environment. A fresh-air unit located next to a main road saturates its media twice as fast as in a rural area. Filters must never be shaken or washed on the construction site: these practices destroy the fibre network and release contaminants into the distribution ducts. The contract must specify the brand or the minimum spectral efficiency of the consumables to prevent the fitting of generic frames that do not comply with the original airflow calculations.

Systematic physical measurements, fire damper operation and deliverable

A preventive visit is not limited to a visual check. It requires calibrated measuring instruments: a digital differential manometer for the pressure drop across filters and coils, a clamp ammeter for the current drawn by each motor phase, a hot-wire anemometer or measuring hood for airflows at critical terminals. Any deviation in amperage signals a seized bearing or an abnormal change in network resistance. These figures serve as a year-on-year comparative reference.

  1. Location and accessIdentify the fire damper on the floor plan and locate the access hatch. Check the cleanliness of the duct upstream and downstream of the blade.
  2. Mechanical or electrical releaseOperate the thermal trigger or cut the holding supply to the actuator to cause the damper to close abruptly.
  3. Closure and tightness checkVisually inspect that the blade seats fully on its intumescent seal. Check that the auxiliary limit switch changes over cleanly.
  4. Reset and lockingReset the mechanism by hand or via the motor. Make sure it latches securely and that there is no rubbing on the metal casing.

The maintenance report handed to the client at the end of the service is the key document in the building's technical file. It lists the components serviced, records all the physical measurements taken, lists every damper operated without exception and flags wear parts at risk of imminent failure. In the event of a fire or a health-related dispute, only this signed record can prove that the installer worked in accordance with the state of the art and releases the contractor from contractual liability.

Contractual definition: exhaustive inventory and frequency per component

A maintenance contract for a ventilation system cannot be limited to a generic mention of an "annual check in accordance with the rules of the trade". Legally and technically, such wording prevents any claim in the event of mechanical failure or critical fouling. For a contract for work and services within the meaning of art. 363 CO to have its protective effects, or for a mandate within the meaning of CO to bind the contractor precisely, the document must append the complete equipment inventory of the system, component by component, with the explicit frequency of the planned interventions.

Wear of air handling components does not follow a single rhythm. A fine filter in an air handling unit (AHU) exposed to urban outdoor air clogs within a few months, whereas a direct-drive fan requires an annual vibration check and a plate heat recovery unit needs cleaning every six months or every year depending on the particle load of the return network. The absence of a precise designation of components shifts the risk of fouling and excess electricity consumption directly onto the client.

Minimum recommended frequency per air handling component according to Swiss hygiene guidelines
ComponentMinimum contractual operationService frequencyCompliance criterion / rejection threshold
Fresh-air filters (stage 1: ISO Coarse / ePM10)Visual integrity check, pressure drop check, systematic replacementSix-monthly (1 to 2 times a year depending on exposure)Δp limit reached or mechanical damage to the medium
Fine return or supply filters (stage 2: ePM1)Systematic replacement and cleaning of the mounting frameAnnual (or on pressure switch signal)Maximum permissible pressure drop specified by the manufacturer exceeded
Heat exchanger (plate / rotary)Tightness check, cleaning of exchange surfaces, check of the rotor beltAnnualNo clogging of the fins, belt intact, smooth rotation
Water coils (air heat exchangers)Dusting of the fins, cleanliness and mechanical integrity checkAnnualFins not bent, airway clear with no deposits or corrosion
Condensate tray and ball trapCleaning, disinfection, check of gravity drainage and primingSix-monthly (spring and autumn)Immediate drainage without stagnation, trap water level maintained
Motors and motor-driven fansAlignment check, bearings, insulation measurement, terminal tighteningAnnualNo abnormal vibration, bearings free of mechanical noise
Balancing dampers and fresh-air/exhaust dampersFull operation, blade cleaning, linkage lubricationAnnualSmooth 0-100 % travel without jamming, airtight closure

Visit metrology, fire damper operation and traceability

A maintenance visit does not consist of looking over the technical cabinet. The CFC 244 technician applies an instrumented physical testing protocol. Each measurement must be recorded to build the operating history and spot airflow drift before an outright failure. The fitter uses a calibrated differential manometer, a clamp ammeter and a hot-wire anemometer or Pitot tube to quantify the real behaviour of the air network.

  • Measurement of the differential pressure across each filtration stage (Δp in pascals), compared with the initial pressure drop of the clean filter.
  • Reading of the current drawn per phase on each fan motor (measured in amperes at rated voltage) to detect mechanical overload or the onset of seizing.
  • Check of the static pressure available at the discharge and suction of the motor-driven fan units.
  • Measurement of air temperatures on the four flows of the unit (fresh air, supply, return, exhaust) to calculate the real thermal efficiency of the exchanger.
  • Check of the negative pressure in the return chamber and check that there is no excessive negative pressure at the AHU access doors.

Checking fire dampers falls directly within the ventilation fitter's duties during maintenance. Swiss fire protection regulations require a periodic mechanical functional test. For each damper identified on the principle diagram and the zoning plan, the technician opens the airtight access hatch, tests the thermal release (mechanical fuse) or the release commanded by a spring-return actuator, checks the condition of the intumescent seal and makes sure the blade closes tightly. Any damper that is inaccessible because of a fixed false ceiling or a non-accessible technical shaft must be recorded immediately as an accessibility defect.

Handling maintenance disputes and recourse in the event of technical failure

When premature fouling of a network or the jamming of a fire damper engages the operator's liability, the absence of a precise contractual inventory blocks any recourse. The ventilation contractor facing an operating dispute must immediately objectify the service failure through contradictory airflow measurements. If the property manager complains of a pressure drop or excess consumption, the technician checks the pressure drop across the filtration stages with a calibrated differential manometer. The direct comparison between the value measured on site and the theoretical fouling threshold set at commissioning settles the dispute: if the filter was not replaced at the agreed frequency, the rise in pressure drop exonerates the installer.

In the event of a fault on a fire damper stuck in an intermediate position, the dispute often concerns the failure to release during the annual tests. The maintenance report signed by the fitter and countersigned by the client is then the only enforceable document. It must record without ambiguity the physical tag of the device according to the ventilation diagrams, the exact date of the kinematic test, the check of the position contact and the resetting of the thermal fuse or actuator. If access to the damper was made impossible by the later installation of a non-removable suspended ceiling or stray cable trays, the technician records the inaccessibility in writing with dated photographs. This formal reservation releases the maintenance company before a building control inspection finds the infringement.

For airflow drift on fresh air or exhaust air, the procedure requires a comparative reading with a Pitot tube or vane anemometer on straight measuring sections. If the deviation exceeds the airflow tolerances allowed relative to the initial acceptance record, the operator is formally called upon to authorise the corrective work provided for in the contract. Written traceability protects both parties: without a visit report recording the current drawn by the fan motors, the static pressures and the visual check of the belts, any mechanical deterioration is presumed to stem from a monitoring failure attributable to the contracted service provider.

Frequently asked questions

What should be done if a fire damper is inaccessible during the periodic maintenance visit?

The fitter must never validate a damper that has not been tested. They immediately record the impossibility of access in the maintenance report, stating the device tag, the nature of the obstacle and its exact location. They notify the anomaly in writing to the site management or the owner of the building, requiring the creation of a properly sized access hatch before carrying out the release test required by the VKF/AEAI fire protection guidelines.

How can the replacement of an F7 filter be justified if the contractual date has not been reached?

The decision rests exclusively on the airflow measurement. The technician reads the differential pressure on either side of the filter medium using an inclined-tube or electronic manometer. If the measured value exceeds the maximum final pressure drop recommended by the manufacturer or the air hygiene standard, replacement becomes mandatory without waiting for the calendar date, in order to preserve the hygienic airflows and the unit's motor.

Who is responsible for keeping the maintenance logbook of the air handling unit?

The building owner bears the legal responsibility for holding and keeping the operating register. However, the ventilation installer in charge of maintenance has a professional obligation to complete and sign the technical report after each intervention. They enter the electrical current measurements, the airflows, the fouling condition of the exchangers and the fire safety checks. This document is then appended to the building's operating file.

What minimum airflow measurements must a ventilation maintenance contract require?

The contract must specify the measurement of the differential pressure on each filtration stage, the reading of the current drawn per phase on each fan, and the check of the static pressure available at the unit outlet. On the main networks, a spot check of the fresh-air flow with a Pitot tube confirms that the volumes distributed match the values set at the initial acceptance of the installation.

Texts and standards cited

  • Norme SIA 382/1Ventilation and air-conditioning systems: general principles and requirements for energy performance and hygiene.
  • Directives de protection incendie AEAIRequirements applicable to the maintenance, periodic testing and operational reliability of fire dampers.
  • Norme SIA 118General conditions for the execution of construction work and management of maintenance services for technical installations.