Key takeaways
- The F400 120 class guarantees two hours of hot-air extraction at four hundred degrees.
- The smoke extraction fan requires an electrical supply that is maintained in the event of a thermal incident.
- The fire-resistant cable and its routing must retain their mechanical and electrical integrity.
- The in-situ test validates the direction of rotation, the airflow rates and the emergency control.
Choosing the temperature resistance class and connecting the extractor to the network
A conventional comfort fan deforms quickly under the effect of hot smoke. As soon as the temperature exceeds 80 °C, the bearings seize, the aluminium or thin sheet-metal blades expand against the casing, and the motor winding short-circuits. Mechanical smoke extraction requires air extractors capable of discharging gases at very high temperature without mechanical deflection. In French-speaking Switzerland, the VKF/AEAI fire protection directives and the building's fire protection concept set the thermal resistance requirements placed on the ventilation installer.
| Resistance class | Test temperature | Holding time | Typical applications on construction sites |
|---|---|---|---|
| F300 60 | 300 °C | 60 minutes | Commercial premises, protected escape corridors |
| F400 120 | 400 °C | 120 minutes | Underground car parks, large commercial volumes |
| F600 120 | 600 °C | 120 minutes | Special structures, tunnels, heavy industrial premises |
The ventilation contractor fixes the casing or roof unit according to the details of the certified manufacturer. The installation requires special flexible connectors made of a flame-retardant fabric resistant to 400 °C, clamped onto rigid metal flanges. The use of a standard anti-vibration connector in PVC or ordinary fabric is prohibited. It would burn within the first seconds of the incident, breaking the airflow continuity of the smoke extraction network.
The installer must also check the location of the electric motor. If it is placed directly in the hot air flow, it must have the corresponding thermal approval. If the motor is mounted outside the flow, as in a roof unit with vertical discharge and a ventilated compartment, the cooling channel of the motor frame must never be blocked or connected to combustible ductwork.
Fire-resistant wiring, safety and in-situ test protocol
The most robust fan remains useless if its supply line fails under the action of heat. The fire-resistant wiring must ensure function maintenance for the entire duration prescribed by the smoke extraction concept. While running the main line from the main distribution board falls to the electrician for CFC 232, the ventilation fitter carries out the direct connection of the local box and the bridging of the differential pressure switch or the terminal control device.
- Exclusive use of approved ceramic junction boxes for function maintenance.
- Fixing of the safety cables with metallised metal clamps, without plastic plugs.
- Installation of a lockable local isolator in cast aluminium or sheet steel with a position contact.
- Direct connection of the motor without incorporating a thermal relay that cuts the motor in the event of thermal overload.
As regards organisation and the prevention of occupational risks on the construction site, the employer takes the technical measures required by art. 3 OPA to ensure workers' safety when handling heavy loads and suspended electric motors. Tests carried out under voltage are performed with suitable protective equipment.
- Checking the direction of rotation and alignmentsApply a brief electrical pulse to validate the direction of rotation of the impeller. An impeller running backwards still delivers a misleading residual airflow, but with insufficient pressure to overcome the pressure loss of the network.
- Measuring actual airflow rates and pressuresMeasure the overall airflow with a Pitot tube or an anemometer on a straight section of the duct. Adjust the balancing dampers to ensure the intended sweep velocities in the clearance zones.
- Testing the interlocking in real conditionsSimulate the smoke extraction command from the control panel or the firefighter's key. Check that the extraction dampers and fresh-air inlets are fully open before the impeller actually starts, to avoid putting the ducts under negative pressure.
- Drawing up the test reportRecord the current drawn on each phase, the measured airflow, the available static pressure and the run-up time on the protocol handed over to the site management.
Extraction drive train and thermal stresses according to the VKF/AEAI
In the event of a fire, a comfort fan fails very quickly: the insulating varnish is charred, the bearings seize through expansion and the deformed scroll rubs against the impeller. Mechanical smoke extraction requires a certified unit that maintains its airflow operating point under extreme temperatures. The VKF/AEAI fire protection directives define the resistance class according to the use of the compartment, the fire load and the foreseeable dynamics of the smoke. In an underground car park, an atrium or a pressurised lobby, the machine must guarantee its airflow rates and pressures without mechanical weakening, because a failure jeopardises the evacuation of users and the intervention of firefighters.
The physical location of the fan determines the exposure of its motor. In a configuration with the motor in the air flow, the stator requires a high-temperature winding and C3-clearance bearings filled with special grease to withstand the burning gas. In a configuration with the motor outside the flow, installed in an insulated casing with a double-skin housing or belt drive under a ventilated guard, the foul air does not touch the drive. This arrangement is required in greasy or corrosive atmospheres such as the vapours of professional kitchens. The ventilation contractor ensures that the auxiliary cooling air never comes from the affected zone.
The mechanical installation compensates for the large expansion of the metal when hot. The flexible connectors joining the inlet and the discharge to the network are made of non-combustible silicone-coated glass fabric certified A1 or A2-s1, d0 with galvanised or stainless steel flanges, avoiding any tearing under negative pressure. Ceiling suspensions are made with threaded rods calculated to absorb the thermal creep of the steel, anchored with fire-approved metal anchors. The anti-vibration mounts under the frame must imperatively include metal stops or fail-safe encased springs: plain elastomer pads are excluded, because their melting under heat throws the machine out of alignment and tears off the connecting ducts.
| Resistance class | Thermal profile | Typical use | Installation specifications |
|---|---|---|---|
| F300 60 | 300 °C for 60 min | School buildings, commercial premises and retail areas | Reinforced flexible connectors 300 °C, class 8.8 suspensions, motor in the flow class H. |
| F400 120 | 400 °C for 120 min | Underground car parks, logistics warehouses and stations | High-strength inclined-blade impeller, protected spring mounts, reinforced motor. |
| F600 120 | 600 °C for 120 min | Special underground structures, tunnels and heavy industry | Welded-fabrication scroll, axial expansion guided by slides, ceramic shaft seal. |
Resistant wiring, bypassing of safeties and in-situ tests
The thermal resistance of the extractor is of no use if its supply line is destroyed by the fire. The fire-resistant wiring must ensure function maintenance of E30 to E90, installed on specific metal cable trays with reinforced brackets and closer clip spacing. The connection to the fan requires a terminal box in cast iron or sheet steel fitted with steatite ceramic terminal blocks and brass cable glands. The local isolator must withstand the temperature of the flow or include an auxiliary position contact signalled to the control panel. In alarm mode, the comfort controls are deactivated: the frequency converter switches to forced firefighter operation, locking the maximum speed and bypassing the local thermal safeties (PTC sensors and bimetal switches) in order to extract the smoke until the ultimate mechanical destruction of the unit.
- Preliminary static mechanical checkCheck by hand that the impeller turns freely, check the radial clearance between impeller and inlet cone, inspect the belt tension and tighten the high-temperature connectors.
- Cold rotation test and electrical measurementsEnergise in local manual control to validate the direction of the air flow. Measure the currents on each phase and make sure there are no parasitic vibrations on the fixings.
- Checking the fire interlocksSimulate an alarm command from the control panel. Check that the smoke extraction dampers and flaps are fully open before the fan reaches full rotation, to prevent the ducts from collapsing.
- Airflow measurements and acceptance reportMeasure the overall differential pressure and the volumetric airflow with a Pitot tube in accordance with the concept validated with the VKF/AEAI authority, then formalise the in-situ test protocol for the building documentation file.
Handling test failures and clearing extraction reservations
During an in-situ functional test, a failure to start or a premature shutdown of the extraction unit is a major non-conformity. The VKF/AEAI fire protection directives require smoke extraction to be maintained for the required duration without any comfort cut-out. If the motor stops suddenly, the fitter must immediately check the bypassing of the local thermal safeties: a fan certified for the chosen temperature resistance class must never have its supply cut by a standard current relay during smoke evacuation.
- Isolating the mechanical or electrical malfunctionCheck the direction of rotation of the impeller, the currents drawn on each phase and the free movement of the rotor after turning it over cold. Measure the alignment of the high-temperature flexible connectors to rule out any start of tearing or suction under strong negative pressure.
- Integrity check of the supply linkVisually inspect the routing of the fire-resistant wiring between the lockable local isolator and the motor's high-temperature terminal box. Make sure that the metal clamps and hangers have undergone no mechanical deformation and comply with the prescribed spans.
- Repeating the full test with a reportRepeat the control test in the presence of the electrician and the fire quality assurance manager. Record in writing the negative pressure measurements, the extracted airflow rates and the confirmation of the priority safety command in the building's operating log.
If the airflow measured at the grilles does not comply with the requirements of the fire concept, the fitter checks the actual opening of the extraction dampers and fresh-air intakes before considering any change to the rotation speed. Any pulley replacement or airflow readjustment must preserve the motor's power margins without compromising the approved thermal resistance of the casing. The joint test report is the mandatory document for authorising the operation of the structure.
Frequently asked questions
How do you tell an ordinary local isolator from a model intended for smoke extraction?
The housing of a smoke extraction isolator includes an auxiliary contact dedicated to position signalling and a suitable metal or self-extinguishing synthetic enclosure. It must be lockable in the closed position to prevent any untimely cut-out during operation, and be connected with metal cable glands maintaining the continuity of the fire-resistant link without melting under the effect of the surrounding hot air.
What check should be made on the flexible connector during an extraction test?
On start-up, the flexible connector joining the casing to the rigid network is subjected to strong negative pressure. The fitter checks visually that it does not collapse inwards, which would halve the air passage. The technical fabric must remain taut without flapping excessively, be mounted with sealed stainless steel clamps and carry a thermal certification identical to the temperature class required for the motor-fan unit.
Why does a variable speed drive pose a problem on a smoke extraction fan?
A standard drive trips into a protective shutdown in the event of overheating, overcurrent or a transient voltage dip. On a smoke extraction network, it must include a specific forced-operation function that ignores internal faults. If this programming is missing, the fan stops within the first minutes of the incident instead of extracting the hot gases as prescribed by the concept.
What should be done if the fan's direction of rotation turns out to be reversed during the in-situ test?
A centrifugal or axial impeller running backwards still moves air in the right direction, but with an airflow that often drops by more than 60 per cent. As soon as the airflow deficiency is noted, the fitter isolates the isolator, has two phases of the electrical supply swapped, then repeats the current measurement with a multimeter to validate the return to the nominal operating point.
Texts and standards cited
- Directives de protection incendie AEAISwiss requirements governing the design, the thermal resistance classes and the obligation of full tests of smoke and heat extraction installations.