🧱 CFC 244Duct network and airtightnessChapter 8 of 10 in the section

Outlets and diffusers: throw, residual velocity and comfort for seated occupants

In open-plan or individual offices, an unsuitable diffuser selection turns a compliant hygienic airflow into an unbearable draught for seated occupants. This chapter guides you through the precise sizing of supply outlets, the calculation of air jet throw and the strict application of the residual velocity criteria prescribed by SIA 382/1.

Key takeaways

  • The occupied zone stops fifty centimetres from the walls and two metres in height.
  • The residual air velocity must not exceed twenty centimetres per second at a seated workstation.
  • The ceiling effect extends the throw of the jet by approximately forty per cent through Coanda adhesion.
  • The choice of the equalising plenum directly determines the regularity of the airflow profile at the outlet.

Defining the occupied zone and controlling the trajectory of the air jet

The classic mistake on construction sites is to check the overall volumetric flow rate of a room without analysing the actual behaviour of the projected air stream. In a commercial space, an employee stays seated for several hours at the workstation. If the throw of the air jet reaches a person's head or neck at excessive velocity, the installation causes immediate thermal discomfort through forced convection, leading to recurring complaints and requests to block off the diffusers improvised-style.

Occupied zone
Interior volume of a room bounded by planes located fifty centimetres from the external or internal walls, and lying between the finished floor and a maximum height of two metres, where the requirements for thermal comfort and air velocity apply.

According to the requirements of SIA 382/1, the residual velocity in the sedentary occupied zone must not exceed 0.15 to 0.20 m/s in cooling mode. The throw of a diffuser, usually denoted L0.2, is the axial distance covered by the air stream between the outlet opening and the point where its centreline velocity drops to exactly 0.20 m/s. The ventilation installer must therefore position the outlets so that the terminal mixing zone lies outside the direct working volume, or on the ceiling well upstream of the point where the jet drops.

Residual velocity limits according to activity, based on SIA 382/1
Type of activity in the roomTarget comfort levelMaximum permitted residual velocityDirect impact on the occupant
Individual offices and open-plan officesCategory A (high requirement)0.15 m/sSensation of coolness imperceptible at rest
Meeting and training roomsCategory B (standard)0.18 m/sSlight air movement tolerated in meetings
Circulation and reception areasCategory C (moderate)0.25 m/sAir movement without nuisance to pedestrians

Using the Coanda effect and selecting the diffusion geometry

The aeraulic behaviour of an air diffuser differs fundamentally depending on whether it blows as a free jet or close to a flat surface. The ceiling effect, commonly called the Coanda effect, occurs when a tangential jet creates a relative low pressure between the air sheet and the underside of the slab. This low pressure literally pins the airflow to the ceiling, preventing the warm ambient air from immediately slipping under the jet and considerably extending its horizontal travel.

When fitting out rooms with a smooth suspended ceiling or a raw concrete slab, this effect stabilises the cold airflow and promotes progressive induction: the fresh air mixes with the ambient air before losing its kinetic and thermal inertia. If the ceiling has pronounced relief or if the diffuser is suspended in the technical void without a guiding surface, the jet becomes a three-dimensional free jet. In this configuration, the throw decreases, but the opening angle widens abruptly, causing early dumping of cold air towards the floor.

  • Linear slot diffuser: recommended for glazed walls, narrow projection and strong peripheral induction.
  • Helical ceiling diffuser with vanes: ideal for high variable flow rates, rapid rotation limiting the vertical throw.
  • Multi-directional diffuser with adjustable cones: 4-way projection, suited to regular layouts in 600x600 tiles.
  • Wall outlet with double deflection: requires a minimum free projection distance of three metres before hitting a partition.

To validate the selection on the drawing, the ventilation installer applies the rule of colliding opposed jets: two diffusers facing each other must never add their terminal throws to the point of reaching a resultant velocity above the values of SIA 382/1 at the centre of the room. If the distance between two outlets is four metres, the individual throw L0.2 of each unit under the ceiling must not exceed two metres fifty, otherwise a converging downward jet will be generated straight onto the work tables.

Calculating the critical throw and preventing draughts at seated workstations

Choosing a supply diffuser is not simply a matter of its nominal flow rate or its acoustic attenuation. On administrative or school construction sites governed by CFC 244, the main cause of complaints at commissioning is an air jet dropping directly onto the workstations. SIA 382/1 defines the requirements for indoor thermal and aeraulic comfort, imposing a strict limitation of air velocities in the occupied zone. When an employee remains seated at a desk for several hours, excessive air velocity at the neck or shoulders triggers an immediate sensation of discomfort, even if the overall room temperature meets the setpoint.

The throw of a jet, usually denoted $L_{0,2}$, is the distance travelled by the air stream between the supply outlet and the point where its residual velocity falls to 0.20 m/s. In cooling conditions, the supplied air is denser than the ambient air. If the throw is underestimated or if the induction ratio of the diffuser is insufficient to warm the air stream quickly by mixing, the jet detaches prematurely from the underside of the slab. It then drops at high velocity into the occupied zone located between 0.10 m and 1.80 m above the finished floor.

To protect a seated workstation located only 1.50 m from a diffuser, the ventilation fitter must select units with very high induction. Swirl or helical diffusers generate rapid mixing with the ambient air within the first few centimetres of discharge. This geometry breaks up the kinetic energy of the flow over a short trajectory, reducing the effective throw while maintaining a sufficient flow rate without causing abrupt thermal dumping.

Wall effect, obstacles in the false ceiling and balancing checks

The behaviour of an air jet depends strongly on the presence of guiding surfaces. The ceiling effect allows the air stream to attach to the upper slab thanks to the low pressure created above the flow. However, as soon as the jet meets a vertical wall, a concrete beam downstand or a movable partition rail, the horizontal flow stops abruptly. The wall effect deflects the air stream downwards along the wall. The flow then descends without damping into the occupied zone, sweeping directly across the tables placed against the perimeter partitions.

Jet behaviour and preventive measures according to diffuser geometry
Diffuser technologyJet profile and inductionRisk in the occupied zoneInstallation measure on site
4-way ceiling diffuser with conesGrazing air jet with medium inductionCold dumping along partitions if the throw reaches the wallSet the diffuser back at least 1.20 m from the perimeter wall
Swirl diffuser with slotsRotating jet with very high inductionResidual velocity damped very quickly, short jetIdeal above dense work areas and seated workstations
Linear diffuser with adjustable slotsLaminar one-sided or alternating jetDirect drop if the internal deflectors are poorly orientedAdjust the damper and the directional vanes towards the continuous ceiling
Long-throw wall nozzleConcentrated jet with low inductionHigh-velocity penetration into the comfort zoneReserve for atriums, reception halls or corridors without fixed workstations

Managing structural obstacles requires close coordination with the structural work drawings. A beam projecting 20 cm below the false ceiling breaks the ceiling effect and detaches the jet. If this phenomenon is not anticipated, the dumping of cool air occurs at mid-throw, directly onto seated people. In this configuration, the fitter must insert connection plenums fitted with individual adjustment dampers to reduce the discharge velocity, or lower the diffuser to the level of the underside of the downstand.

  1. Measuring terminal velocitiesPosition an omnidirectional thermal anemometer (hot wire) at 1.10 m above the floor at the seated workstations to verify that the residual velocity remains compliant with the requirements of SIA 382/1.
  2. Adjusting the deflection elementsAdjust the directional vanes and the movable slots of the plenums to redirect the flow towards free circulation areas and avoid direct contact with vertical walls.
  3. Fine aeraulic balancingAdjust the perforated balancing damper in the connection neck of the plenum in order to bring the airflow to the design value without generating noisy turbulence.

On-site remediation: correcting air dumping and excessive velocities

When commissioning is approaching and a user reports an annoying draught at one metre fifty from their workstation, the ventilation installer must objectively document the problem before making any modification. Complaints at seated workstations almost systematically stem from a local residual velocity above the limits defined by SIA 382/1, or from premature dropping of the cooled air stream into the occupied volume. The first reflex on the construction site is to measure the flow velocity and temperature at 1.10 metres above the floor using a calibrated omnidirectional thermo-anemometer.

  1. Diagnosing the detachment of the air streamVisualise the actual trajectory with a smoke puffer to locate the point where the air stream detaches. An abrupt drop frequently indicates a premature breakdown of the Coanda effect caused by a protruding luminaire, a false-ceiling profile or the proximity of a vertical wall.
  2. Modifying the diffusion geometryAdjust the orientable vanes or the internal deflectors in order to widen the induction angle and shorten the throw of the air jet. On a multi-directional or slot diffuser, fitting a sector mask removes the component directed towards the receiving partition.
  3. Adjusting upstream flow ratesCheck the actual volumetric flow rate at the plenum using a measuring hood or an anemometer probe. If the measured flow rate exceeds the project setpoint, the adjustment must be made on the balancing damper located on the duct branch.

If these aeraulic adjustments do not bring the velocities below the critical threshold because of a discrepancy between the ventilation drawing and the actual furniture layout, the fitter records his measurements and sends his technical findings to the site management. Replacing the diffuser with a high-turbulence model or adding a perforated distribution plate in the plenum are the last resorts before relocating the outlet.

Frequently asked questions

What should be done if the air jet drops directly onto an employee's head without reaching the throw stated in the catalogue?

This phenomenon reflects a premature detachment of the air jet due to lack of adhesion to the ceiling. In cooling mode, the negative temperature difference amplifies gravitational forces. Check that there are no protruding obstacles under the false ceiling, such as a luminaire or a partition rail. If the ceiling is clear, replace the diffuser with a model with higher induction or orient its deflectors to hold the air sheet against the surface.

How should residual velocity be measured correctly when accepting an open-plan office?

Carry out the measurement with an omnidirectional thermal anemometer positioned at 1.10 metres above the floor for a seated workstation, or at 1.70 metres for a standing area, in accordance with SIA 382/1. Avoid vane anemometers, which cannot capture low and unstable velocities. Record the mean values over a minimum of three minutes per point, particularly in the zones where air streams cross.

Why does the wall effect generate excessive velocities at floor level even though the flow rate is correct?

When a horizontal air jet meets a partition before it has slowed down, it hits the surface and turns into a jet descending along the wall. The Coanda effect then applies vertically, guiding the air sheet downwards with reduced pressure loss. The air reaches the floor and then sweeps the seated workstations. The direction leading to the wall must then be blocked off, or swirl diffusers with a high induction ratio must be used.

Is it possible to use a linear slot diffuser without a continuous false ceiling?

Without a flat underside to create the low pressure needed for the ceiling effect, the throw of the jet is reduced by approximately one third and the air stream drops downwards. To maintain a stable trajectory under an exposed slab, select a diffuser with a specific spreading profile or orient the vanes upwards, while checking the residual velocities according to SIA 382/1.

Texts and standards cited

  • SIA 382/1Ventilation and air-conditioning installations - General principles and performance