🧱 CFC 244Air handling unit and heat recoveryChapter 1 of 10 in the section

Positioning the air-handling unit: maintenance clearances, door and filter replacement

After this chapter, you will be able to determine, and defend before the structural work trades, the set-back distances essential around an air-handling unit. You will check door widths, the clear height under the slab including the plinth and the trap, and the maintenance access requirements for extracting filters and heat recovery units without obstruction.

Key takeaways

  • The service face requires a free set-back at least equal to the width of the monobloc unit.
  • The access corridor must allow the filter drawers to be withdrawn fully along their axis without any obstruction.
  • The ceiling height must always include the concrete plinth, the drainage slope and the water seal.
  • The door of the plant room is sized on the bulkiest of the removable components of the installation.

Service clearances per face and extraction corridors for internal components

Positioning an air-handling unit in a plant room tolerates no spatial approximation during the structural work phases. A positioning error against a concrete wall prevents the inspection doors from opening and makes periodic maintenance impossible. The ventilation installer must fix the openings and the clearance distances on the coordination drawings well before the walls and slabs are poured.

Each face of the monobloc unit serves a specific function. The rear face, which has no access panels or measurement points, can be placed close to a masonry wall provided that an installation and acoustic insulation clearance of 100 to 150 mm is kept. The service face, on the other hand, groups the hinged doors, the clamping handles, the inspection windows and the condensate connections. This side requires a continuous free frontal clearance, at least equal to the depth of the internal sliding sections.

Minimum clearances to be reserved according to the components to be extracted
Internal componentType of workMinimum frontal clearance requiredObstacles prohibited in the zone
Filtration stageReplacement of filter cells and bag filtersFrame depth + 200 mm (minimum 800 mm)Hydraulic pipework, vertical cable trays
Water coil (heat exchanger)Lateral sliding for descaling or refurbishmentTotal width of the unit + 100 mmLoad-bearing pillars, suspended sanitary collectors
Plate heat recovery unitRemoval of the heat exchange blockWidth or diagonal of the exchanger casingElectrical control cabinets, rising ducts
Enthalpy wheelReplacement of belt or drive motorWidth of the monobloc unit facing the frameDrain pipes, fixed sub-frames
Plug-fan motor-fan unitRemoval of the motor-wheel assembly on a trolleyShroud diameter + 400 mm of passageRoof framing cross-members, continuous raised thresholds

The exit path must be thought out in three dimensions. A 600 mm deep bag-filter drawer slides horizontally on its rail. If a secondary supply duct drops down in front of the access panel, the filter cannot come out straight and tears against the retaining angles. The vitiated air and the accumulated particles then spread directly inside the clean casing.

Clear height under the slab, access to the room and maintenance access requirements

The gross height under the slab of the plant room is never the height available for the unit. The ventilation mechanic must deduct the thickness of the blinding or anti-vibration concrete plinth, the height of the main duct network suspended above the machine, and the passage of the fresh-air and exhaust ducts. A residual space of 500 mm above the casing remains essential to access the dampers, the actuators and the upper inspection hatches.

  1. Sizing the plinth and the trapProvide for the unit to be raised by 150 to 250 mm above the finished slab. This height allows the installation of a condensate drain trap with a water seal sufficient to overcome the negative pressure created by the suction fan.
  2. Checking openings and passage doorsCheck that the clear width of the doors giving access to the room exceeds the largest dimension of the removable monobloc units or exchanger frames. Swing doors must open outwards so as not to block the emergency escape routes.
  3. Marking out the sliding routeCheck the mechanical strength of the floor and the absence of insurmountable steps between the outside access (opening, goods lift) and the final slab for the transport of heavy parts by pallet truck or trolley.
  4. Positioning the fixed service pointsCoordinate the installation of a sealed linear luminaire directly above the filter access face and of a single-phase 230 V socket to connect the airflow measuring instruments and the cleaning tools.

The general lighting of the plant room often proves insufficient when it is masked by the very bulk of the unit. A row of industrial luminaires must be installed above the service aisle to light the inside of the casings directly when the inspection doors are opened. The 230 V service socket makes it possible to power a portable lamp and an electronic differential pressure gauge without running cables through the building's fire doors.

Escape route and access dimensions: taking out filters and heavy components

Defending the positioning of an air-handling unit is not limited to reserving a corridor in front of the casing doors. The ventilation fitter must validate the entire removal chain, from the sliding rail of the filter cells to the goods lift or the unloading dock. Too often, a masonry opening is poured with only the passage of a technician carrying a tool bag as reference. When the operator has to remove clogged filter frames of the standardised 592 by 592 millimetre format or replace a free-wheel motor-fan, the construction site runs into doors that are too narrow, blocking corridor corners or flights of stairs without a hoist.

Space constraints and transit corridors for the components of an air-handling unit
ComponentTypical unit sizeClearance in front of casingClear passage at room door
Bag filters (F7 / ePM1)592 x 592 x 600 mmFrame depth + 300 mm900 mm minimum
Compact pleated filters592 x 592 x 292 mmCell depth + 200 mm900 mm minimum
Plug-fan motor-fan unit600 to 1100 mm in diameterWheel diameter + 400 mmMotor width + 200 mm (min. 1000 mm)
Monobloc plate heat exchanger800 to 2200 mm edge lengthTotal width of the blockBlock width + 250 mm with double leaf
Rotary heat recovery wheelDiameter of 1000 to 2800 mmFull wheel diameterDirect roof access or dedicated hatch

For cross-flow or counter-flow heat exchangers, the cell block cannot be folded. If the casing is built in between two concrete cross-walls without providing a removable front or a re-openable structural opening, replacing a punctured exchanger requires the demolition of existing partitions. The ventilation installer's execution drawings must show a red dash-dot line marking the removal path of the recovery block, with an express note that it must not be occupied by the other trades such as plumbing, heating or electrical.

  1. Checking thresholds and stepsRequire door thresholds that are flush, without protruding metal stops, so as to allow the rolling of hand trucks, filter trolleys or manual lifting devices carrying heavy loads.
  2. Checking turning areasMark out the turning diagram on the floor for long items. A corridor 1200 millimetres wide does not allow a filter frame or a terminal coil casing of 1500 millimetres to be turned.
  3. Reserving the upper anchor pointsHave anchored metal profiles or lifting rings installed in the upper slab above the motor-fan unit to allow lifting without a temporary hoist fixed to ducts.

Setting up the work area: lighting, sockets and technical connections

A maintenance corridor that complies with the mechanical dimensions becomes unusable if the working-environment requirements are neglected during technical coordination. The ventilation fitter must work with the electrician to position the luminaires not on the theoretical axis of the room, but precisely above the manoeuvring space of the inspection doors. A lighting strip positioned behind an air collector or above a network of galvanised sheet-metal ducts leaves the technical faces of the machine in total semi-darkness, forcing the operator to work by torchlight during the delicate replacement of filter gaskets.

  • Minimum illuminance: provide an illuminance level suited to fine inspection and mechanical adjustment work on each access face to the dampers and motors.
  • Service electrical distribution: provide at least one sealed 230 V type 13 or type 23 socket in the immediate vicinity of the filter access points to connect airflow measuring instruments, anemometers and industrial vacuum cleaners.
  • Power supply: provide a 400 V three-phase socket of type 15 or type 25 if the unit includes equipment requiring a high-pressure cleaning unit or a temporary hoist.
  • Position of isolating devices: the lockable maintenance switches of the motors must remain accessible without entering the opening radius of the casing's swing doors.

The height at which the machine is set also determines the effectiveness of condensate drainage maintenance. The unit must rest on a base frame or anti-vibration mounts providing a ground clearance calculated according to the static pressure prevailing in the treatment section. In casings under negative pressure (cooling coil placed upstream of the suction fan), gravity drainage requires a ball trap or a swan-neck trap whose water height balances the maximum negative pressure plus a safety margin.

Compliance with the general occupational safety requirements obliges the installer to ensure that each inspection point remains freely accessible without climbing over ducts or stepping over condensate pipes on the floor. The drain pipes of the condensate tray must run down vertically and then along the feet of the casing without cutting across the operator's path, before joining the building's sanitary disconnecting funnel.

Positioning conflicts and uncoordinated partitions: what to do

On the construction site, a clearance is frequently reduced when an offset concrete wall is poured, a masonry partition is unexpectedly raised or a sanitary collector is run without coordination in front of the inspection doors. When the remaining corridor no longer allows a filter frame to be tilted out or a plate exchanger to be withdrawn, the machine becomes unusable. Continuing the air duct connection without reacting directly engages the installer's liability.

  1. Record the dimensional deviations on siteAs soon as the setting-out is done or after the structural work has been stripped of its formwork, measure the clear distance between the finished face of the walls and the envelope of the unit. Check whether the 90-degree opening of the doors and the sliding axis of the filters remain clear of third-party cable trays and pipework.
  2. Notify the obstruction by written noticeSend a reasoned notice to the site management without delay, with a dimensioned sketch and an extract from the manufacturer's data sheet. Under art. 365 para. 3 CO, if a circumstance compromises the proper or timely execution of the work, the contractor must inform the client, failing which he bears the consequences.
  3. Freeze the installation of rigid connectionsStop assembling the supply and return ducts until a decision has been made. Fitting the flexible connections to a badly positioned unit tacitly validates its defective positioning and makes later corrections technically complex and costly.
  4. Examine technical fallback solutionsIf demolition of the wall is ruled out by the designer, examine splitting the filter cells on slides, reversing the opening direction of the doors or pivoting a section of the casing with the written agreement of the manufacturer.

Access to the hatches, full removal of the heat recovery unit and operation of the control valves must appear in the acceptance record. Any refusal to modify a third-party structure that blocks maintenance requires express reservations to be issued under the SIA 118 standard, relieving the ventilation contractor of the operating extra costs and future damage.

Frequently asked questions

What should be done if a concrete pillar prevents the plate heat recovery unit from being fully withdrawn?

The site management must decide before the ducts are installed. If the pillar is load-bearing and cannot be moved, the machine must be slid aside if space allows. Failing that, ask the manufacturer to supply an exchanger split into coupled modules or study substituting a run-around coil system with the agreement of the consulting engineer to maintain the required thermal efficiencies.

Can a heating pipe run through the maintenance corridor of an air-handling unit?

No. The volume in front of the access doors must remain free of any fixed obstacle. Hydraulic, sanitary or electrical networks must never use the dismantling access zone of the fans and filter drawers. If an installer encroaches on this zone, report the spatial incompatibility immediately at the technical coordination meeting so that the pipework is rerouted at his expense.

How can a refusal to fit smaller filters in order to get around a wall be justified?

The airflow sizing of a unit is based on a face velocity and a filter surface defined to guarantee the filtration class and control the pressure drop. Reducing the thickness or surface of the filter leads to higher electricity consumption, premature clogging and a risk of airflow breakdown. Present the unit's airflow selection sheet to demand that the planned set-back be respected.

Who bears the cost of a handling rail system not provided for in the project?

If the plant room does not have the necessary space to manoeuvre heavy components such as a fan or a rotor, and the initial coordination drawings made no mention of lifting means, this constitutes an additional service. The installer submits a price request for the supply and installation of a monorail with hoist before starting the installation of the machine.

Texts and standards cited

  • CO art. 365material and ground: the contractor is responsible for the good quality of the material he supplies; if the material supplied by the client or the ground designated by him is found to be defective, or if another circumstance compromises the proper or timely execution of the work, he informs the client immediately, failing which he bears the consequences (para. 3).
  • norme SIA 118General conditions for the execution of construction work, rules on handling notices of defects, order modifications and construction site reservations.