Installing a fire damper: position in the wall, sealing and access

This chapter details the precise positioning of a fire damper where a duct passes through a fire-resistant separating wall. You will learn how to locate the axis plane of the pivoting blade, carry out the sealing in accordance with the Swiss approval certificate, and provide the access needed for resetting and periodic tightness checks.

Key takeaways

  • The blade axis must coincide with the median plane of the separating wall.
  • Any uncertified offset destroys the fire resistance of the construction and invalidates the installation.
  • Sealing requires full mortar or approved coated mineral wool boards.
  • The inspection hatch must give direct access without dismantling the ventilation ducts.

Positioning the damper casing and the blade axis within the thickness of the wall

In comfort ventilation as in specific extraction systems, the fire damper is the mechanical device that restores the integrity of a fire compartment crossed by an air duct. The VKF/AEAI fire protection guidelines require the fire resistance of the separation to be fully restored at the opening. A positioning error of a few centimetres is enough to ruin the effectiveness of the device. If the damper is pushed out of the wall, the thin sheet-metal casing exposed to the fire deforms prematurely under thermal action, letting hot smoke and combustion gases through even before the thermal fuse or the motorised actuator operates.

Approved closing plane
Zone marked on the damper's mounting casing by a groove or a factory label, showing the pivot axis of the blade. This reference line must be located within the thickness of the concrete wall, masonry or lightweight partition tested in the official tests.

Each damper model has a declaration of performance and a VKF/AEAI certificate of use. These documents set the minimum and maximum distance between the outer face of the wall and the pivot plane of the blade. In a solid reinforced-concrete or clay-brick wall, the blade should generally be located in the central third of the separating element. Installation tolerances rarely exceed plus or minus fifteen millimetres relative to the marks stamped on the sheet metal.

Where the blade axis cannot be aligned within the partition because of space constraints, the ventilation contractor must use an offset solution expressly described in the supplier's technical file. This assembly involves a steel sleeve covered with fire-resistant insulation along its entire intermediate length, sealed continuously up to the damper flange.

Carrying out the approved sealing and freeing the service clearances

Once the damper has been levelled and suspended from its own angle brackets or threaded rods anchored in the structural work, the annular gap between the casing body and the masonry opening must be sealed airtight. Two main methods are recognised by the VKF/AEAI fire protection guidelines, each of which must match the specific approval certificate of the device.

  • Wet sealing by completely filling with cement mortar or non-shrink fire-resistant plaster for solid concrete or brick walls.
  • Dry sealing with rigid high-density rock wool boards, coated with an ablative paste or an approved intumescent fire sealant.
  • Mechanical fixing with metal brackets screwed onto a frame for penetrations through lightweight reinforced plasterboard partitions.
  • Strict compliance with the prescribed annular gaps, generally between 20 and 60 millimetres depending on the method chosen.

The duct connection on either side of the wall is then made so that the ducts are decoupled, ensuring that thermal expansion or collapse of the duct in a fire does not tear the damper out of its seal. Flexible non-combustible connectors or specific socket joints absorb the residual mechanical stresses without transmitting any shear force to the sealed damper casing.

Sealing materials according to the type of supporting wall
Type of supporting wallApproved sealing materialMinimum inspection clearance
Concrete wall or solid brickPure cement mortar or sealing plaster200 mm around the mechanism
Lightweight partition on a frameCompact mineral wool + ablative coating300 mm in front of the hatch
Concrete slab, vertical penetrationNon-shrink fluid concrete poured into formworkFull access from the lower level

The last critical point is permanent accessibility to the release mechanism and the blade. A tight inspection hatch must be provided in the duct or built directly into the body of the device. The VKF/AEAI guidelines prescribe regular visual and functional checks. Leaving a damper hidden behind a fixed false ceiling without an inspection hatch of at least 400 by 400 millimetres is grounds for immediate rejection at acceptance by the cantonal fire safety services. Removable false ceilings or plaster access hatches must be marked with a visible identification plate.

Offset installation and special penetrations: maintaining the certified performance

On Swiss construction sites, the congestion of technical ducts and the density of the reinforcement sometimes make it impossible to embed the damper at the exact centre of the fire-resistant wall. Offsetting the damper by ten centimetres out of the masonry without an approved device destroys the fire protection: under heat, the steel sheet of the duct deforms, letting flames bypass the closed blade. The VKF/AEAI fire guidelines allow offset installation only by strictly applying the manufacturer's approval report. This assembly requires a certified sleeve or a fire-resistant enclosure of equivalent class (EI 30 to EI 90) between the wall face and the damper, ensuring continuity of the compartmentation.

Installation configurations and requirements according to the approval
ConfigurationGeometric conditionSealing / InsulationSuspension required
Embedded in a solid wallBlade axis located within the thickness of the concrete (min. 100 mm)Non-shrink mortar or plaster all aroundIndependent suspensions on both sides
Surface-mounted on the wallPlate bolted directly onto the supporting wallIntumescent strip and fire sealant under the frameDamper's own support anchored in the concrete
Offset outside the wallConnecting duct protected up to the wall crossedRock wool sections with EI facingThreaded rods sized for fire for duct and damper
Lightweight partitionReinforced trimmer with steel studs and crosspiecesCompressed rock wool and intumescent sealantNo mechanical load transmitted to the framework

Mechanically fixing the duct requires constant technical rigour. In a fire, the creep of the steel and thermal expansion can tear out the seals if the upstream and downstream ducts share the damper's anchors. The ventilation fitter therefore separates the loads: the damper has its own suspension system anchored in the concrete slab with fire-resistant metal anchors, while the adjacent network rests on separate brackets. If the duct sags or gives way under thermal action, it must be able to detach from the damper without damaging the penetration or blocking the pivoting of the movable blade.

Access hatches, self-inspection and acceptance of the installation

A fire damper is an electromechanical safety device subject to mandatory periodic maintenance. The VKF/AEAI fire guidelines and the building authorities refuse acceptance of the work if the release devices remain inaccessible. Access is organised on two distinct physical levels: external access to the control mechanism to test the thermal fuse, reset the spring or check the servomotor, and internal access to the blade to clean off dust, check the integrity of the intumescent seal and ensure the damper blade rotates freely without rubbing against the casing.

  1. Positioning the air duct hatch on the ductFit a tight, quick-closing inspection hatch less than 200 mm from the damper. Its size must allow the introduction of an inspection mirror and an arm to clean the seal and the internal mechanism.
  2. Coordinated opening in the finishing workCoordinate the opening with the false-ceiling installer. The false-ceiling hatch must have the same fire resistance as the wall crossed (EI 30 to EI 90) and provide a clearance of at least 400 x 400 mm in front of the casing.
  3. Kinematic closing and tightness testCarry out the manual closing test: trigger the thermal fuse or cut the power to the servomotor. Visually check that the blade is fully seated against its stops and that it locks mechanically without rubbing.
  4. Identification plate and certificate of conformityComplete the metal identification plate riveted to the damper: VKF/AEAI approval number, date of installation and installer. Draw up the self-inspection record and send the certificate of conformity to site management.

Handover of the installation requires flawless documentary traceability. The installer records on the revision plans the exact location of each device with its air-duct reference number. This mapping accompanies the fire conformity declaration handed over to site management. Under art. 365 al. 3 CO, if a circumstance jeopardises the proper execution of the work, the contractor informs the client. As soon as a false ceiling is built without an access opening in front of a damper, report this obstruction in writing to relieve yourself of liability.

Managing non-conformities: realignment and remaking of seals

A fire damper whose blade axis extends beyond the wall opening outside the range certified by the VKF/AEAI fire guidelines loses its approval validity. Hot gases can lick the sheet-steel duct upstream of the damper, causing rapid deformation and early failure of the compartmentation. As soon as an axis offset or inadequate sealing is found during installation, the installation team must suspend the upstream and downstream duct connections to prevent the opening from being concealed before correction.

  1. Joint inspection record and documentationMeasure the installation deviation with a tape measure relative to the face of the fire-resistant wall and check the tolerances against the VKF/AEAI approval diagram. Draw up a formal notice for site management, accompanied by photographs showing the blade axis and the condition of the opening.
  2. Removal or mechanical realignmentRemove the flexible connectors and decouple the frame. If the installation dimension cannot be made up by the adaptation devices validated by the manufacturer, remove the damper to reposition the pivot axis precisely in the median plane of the fire-resistant wall.
  3. Clearing out and remaking the sealRemove completely any non-approved products such as ordinary expanding foams. Clean the wall reveals, dampen the mineral substrate, then carry out the sealing with non-shrink mortar or with high-density mineral wool boards coated with certified ablative sealant, according to the technical data sheet.
  4. Freeing access and resettingMove third-party services located less than 200 millimetres from the mechanism. Fit a tight inspection hatch on the duct or coordinate an inspection hatch in the suspended ceiling to guarantee direct access to the casing, the fusible element and the reset lever.

The remedial work requires a complete functional check: simulation of thermal release, verification of the airtight closing of the blade and a test of manual or motorised resetting without abnormal resistance. The installer completes the identification plate riveted to the casing and fills in the self-inspection record. This traceability document is handed to the quality assurance manager to be included in the final work file at acceptance by the fire protection authorities.

Frequently asked questions

Can the annular gap around a damper be filled with commercially available fire-resistant polyurethane foam?

The use of an expanding foam, even one labelled as fire-resistant, is subject to the indications of the VKF/AEAI certificate of conformity issued for the installed model. The great majority of manufacturers prescribe exclusively standard cement mortar, dense plaster or rock wool boards covered with ablative coating. Applying a foam that is not approved for this specific assembly destroys the fire resistance of the construction and leads to complete removal of the seal before acceptance.

What should be done if the damper's pivot axis protrudes fifteen centimetres outside the concrete wall?

Positioned outside the load-bearing wall, the damper cannot fulfil its thermal compartmentation role without a specific arrangement. Either the device must be removed so that the mechanism is reinserted within the thickness of the wall in accordance with the technical data sheet, or an added protective enclosure or a fire-resistant duct expressly certified by VKF/AEAI for this configuration must be installed. Without this approved addition, the fire protection authority systematically refuses acceptance of the installation.

What minimum dimensions must be respected for inspection hatches in false ceilings and on ducts?

The VKF/AEAI fire guidelines require permanent access allowing the blade to be inspected and the mechanism to be operated without destructive dismantling. In false ceilings, a hatch of at least 500 by 500 millimetres is provided opposite the control. On the air duct network, the tight inspection frame must measure at least 400 by 300 millimetres to allow direct visual inspection of the blade, the condition of the intumescent seal and replacement of the fuse.

Which trade is responsible for filling the penetration around the damper?

According to the rules of the trade and the provisions of standard SIA 118, fire sealing belongs to the ventilation package, which alone knows the requirements of the device's approval certificate. Where the contract documents assign this task to the mason, the ventilation fitter must pass on the approved sealing data sheet, supervise the installation of the materials and validate the work on his self-inspection sheet before connecting the duct sections.

Texts and standards cited

  • Directives incendie AEAIFire protection requirements concerning fire compartmentation and air-handling installations
  • norme SIA 118General conditions for the execution of construction work and technical coordination