🧱 CFC 244Air requirements, flow rates and sizingChapter 8 of 10 in the section

An airtight building requires ventilation: flow balance and residual negative pressure

In an airtight building, even the slightest difference between supply and extract air flow rates causes an immediate pressure change. By the end of this chapter, you will be able to identify the source of pressure gradients across internal partitions, measure the permissible residual negative pressure and adjust the air balancing to ensure comfort and easy door operation.

Key takeaways

  • An airtight envelope eliminates passive infiltration and transfers any airflow imbalance onto the internal doors.
  • The force needed to open a door increases in proportion to the residual negative pressure created by air extraction.
  • The SIA 382/1 standard governs the balance between supply and extraction to protect both comfort and the building.
  • Precise adjustment of dampers and fans ensures an internal pressure compatible with escape routes.

Why an airtight envelope turns every cubic metre of imbalance into a load on openings

On contemporary Swiss construction sites, high levels of thermal insulation and careful attention to vapour barriers turn buildings into almost airtight volumes. In an older building, leaks in the façade or window frames spontaneously compensated for airflow approximations through diffuse infiltration. In a contemporary envelope checked by a blower-door test, air no longer passes through masonry joints or external joinery. If the air-handling unit extracts more air than it supplies, the enclosed volume immediately drops in pressure relative to the outdoor atmosphere or the stairwells.

Residual negative pressure
Negative static pressure difference measured between the inside of an airtight room or compartment and an adjacent reference space, caused by a mechanical extract air flow rate greater than the supply air flow rate.

This pressure difference is not just a figure on the ventilation fitter's differential manometer: it acts physically on every square metre of partition, and first of all on the door leaves. A standard door of about two square metres becomes the direct recipient of this thrust. When negative pressure builds up in a hall, an apartment or a technical landing, the force required to pull the door away from its frame can exceed the physical strength of an ordinary user or, conversely, cause violent slamming when the door closer shuts the door.

Effect of the pressure difference on the opening force of a standard hinged door (0.90 m x 2.10 m)
Pressure difference (Pa)Thrust on the door leaf (N)Force felt at the handle (N)Operational impact on the construction site
10 Pa19 NAbout 9 NSmooth movement, resistance imperceptible to the user.
30 Pa57 NAbout 28 NClear resistance, sharp slamming of apartment entrance doors.
50 Pa95 NAbout 47 NLaborious for children, door closer setting disrupted.
80 Pa151 NAbout 75 NDoor partially jammed, escape routes non-compliant.

Mastering flow balance and permissible negative pressure under SIA 382/1

To avoid mechanical and acoustic problems at openings, the design and commissioning of ventilation and air-conditioning installations are based on the rules of the SIA 382/1 standard. This reference document defines the principles of air renewal, distribution and pressure management in treated rooms. In most administrative, school or multi-family residential buildings, the standard favours a strict balance between overall supply and extraction, in order to maintain a neutral pressure gradient relative to the outside.

Ventilation installations must be designed and adjusted so that pressure differences between inside and outside, or between adjoining rooms, compromise neither the normal operation of doors nor the safety of users.

Norme SIA 382/1

On site, the ventilation system installer must aim for an overall residual negative pressure not exceeding 10 to 15 pascals in living or working rooms. In technical areas or wet rooms where slight negative pressure is sought to contain odours or humidity, this value must be strictly limited. If the negative pressure reaches or exceeds 50 pascals at an escape door, the installation breaches the safety requirements on the opening force of emergency exits, for which the commonly applied limit for manual operating force is below 100 newtons, door closer included.

  1. Checking flow rates at the main outletsMeasure the actual flow rates with a flow hood or Pitot tube on the supply and return branches to check they match the design values calculated in the project.
  2. Measuring the pressure gradient with doors closedPlace an electronic differential manometer between the airtight room and the corridor, doors closed, to check that the residual negative pressure stays below 15 pascals.
  3. Force measurement on the door leafHang a spring scale or dynamometer at the height of the door lever handle and measure the pulling force needed to pull the leaf free under nominal ventilation conditions.
  4. Adjustment using the variable speed drive or balancing dampersCorrect the supply fan speed or close the extract damper slightly until the setpoint pressure is restored without producing any air whistling.

Airflow measurement protocol and force check on hinged doors

On a Minergie construction site or one meeting strict envelope airtightness requirements, commissioning is not limited to recording the fan motor currents. The ventilation fitter must verify the balance between the volume of fresh air supplied and the volume of stale air extracted. If extraction exceeds supply, the building is put under partial vacuum. This pressure difference between inside and outside acts directly on the surface of emergency doors, entrance lobbies and apartment entrance doors opening onto ventilated or unventilated stairwells.

A differential pressure that looks harmless on a manometer produces considerable mechanical forces on a door leaf. A standard door of 2 metres by 90 centimetres has a surface area of 1.8 square metres. A differential of only 30 pascals applies a perpendicular force of 54 newtons spread over the panel. Added to the stiffness of the mechanical door closer, this load makes the door hard to operate for a child or a person with reduced mobility, or even impossible if the leaf opens against the negative pressure.

Effect of the pressure difference on door behaviour and air circulation
Pressure difference (Pa)Force on standard door leaf (N)Observation on the joineryAction required on the installation CFC 244
0 to 5 Pa0 to 9 NSmooth opening, full closing by the door closer without slamming.Ideal theoretical balance; nominal reference setpoint.
10 to 15 Pa18 to 27 NSlight resistance noticeable when pulling, no whistling at the seal.Permissible residual negative pressure range under SIA 382/1.
25 to 40 Pa45 to 72 NDoor closer stalls before the latch or sharp slamming; whistling at thresholds.Critical imbalance; rebalance the floor dampers.
> 50 Pa> 90 NExcessive force at the handle, emergency egress compromised, seals deformed.Partial shutdown or emergency switch-over of the variable speed drives to protect users.
  1. Initial calibration of the monobloc unitCheck the cleanliness of the ISO ePM1 and ePM10 class filters. Measure the overall flow rates at the upstream/downstream measuring sections using the Pitot tube method or a differential measuring cross, then adjust the EC motor frequencies to precisely equalise supply and extraction at the discharge.
  2. Balancing the floor branchesAdjust the motorised or manual balancing dampers on each main duct. Ensure that the ratio between air supplied to the main rooms (offices, living rooms) and air extracted from wet or technical rooms matches the air-handling specifications without short-circuiting.
  3. Recording differential pressures at thresholdsSet up an electronic differential manometer with the outside pressure tap protected from dynamic wind pressure. Measure the pressure drop with doors closed, then test the pulling force on the door handle with a calibrated dynamometer.
  4. Fine adjustment of the residual negative pressureCorrect the speed of the extract or supply fan using the DDC controller to stabilise the building within the tolerated range, while keeping a very slight negative pressure to protect the walls from interstitial condensation in winter.

Resolving pressure drift in operation and airflow faults

Even after acceptance without reservations, the balance between supply and extraction can drift due to uneven clogging of the air filters, seizing of a balancing damper or the starting of uncompensated local extraction hoods. When a user reports that an apartment entrance door no longer latches into its strike plate or that an air drone can be heard at the automatic drop seals, the technician must analyse the duct network before blaming the joiner's hardware.

  • Checking clogging of the filter boxes: an outdoor air filter that clogs faster than the return filter creates an induced negative pressure not managed by fixed-speed control.
  • Checking fire dampers and balancing dampers: a blade jammed at 45 degrees in an extract duct skews the network and shifts suction to the other grilles.
  • Coordination with specific extraction systems: commercial kitchen hoods or workshop extraction must include interlocking with a dedicated tempered compensating air supply.
  • Checking duct network airtightness: a supply network leaking outside the heated volume (in a poorly sealed service duct) extracts air from the building without returning that volume at the supply.

The SIA 382/1 standard demands absolute rigour in keeping the adjustment log. The contractor's general duty of care, recalled in art. 364 CO, means delivering an air-handling installation whose operation does not interfere with the basic use of the building. The final balancing must be recorded with the measured flow rates, floor pressures and forces exerted on the main exits, thus ensuring that energy efficiency and circulation safety coexist perfectly.

Remedial protocol for a jammed door and clearing non-conformities

When the doors of an entrance lobby resist passage or slam violently against their frame, the air-handling network is showing a clear flow difference between supply and extraction. In a passive or Minergie-P labelled building, the extreme airtightness of the envelope allows no parasitic leakage to compensate for this difference. The fitter's first step is to isolate the cause by connecting a differential micromanometer between the indoor environment and the outside. If the differential pressure exceeds 15 Pa, the force required to pull the leaf free exceeds the tolerable threshold set for persons with reduced mobility.

  1. Recording static pressures at the unitsCheck the air velocity in the main duct with a Pitot tube or hot-wire anemometer. Record the pressure drop across the F7 and M5 filters of the monobloc units to rule out uneven clogging that has reduced the supply flow rate.
  2. Checking balancing dampers and non-return dampersCheck the mechanical position of the opposed-blade dampers and the condition of the pressure relief dampers. A damper stuck closed on a sanitary return causes immediate positive pressure in the circulation areas.
  3. Readjusting the frequency drivesAdjust the 0-10 V setpoint of the EC motors or drives on the extract and supply fans to restore strict volumetric balance, including the density correction according to the extract air temperature.

If rebalancing at the air-handling units does not resolve the mechanical stress on the door sets, the technician must check the air transfers between rooms. The absence of undercuts beneath internal doors or clogged acoustic transfer grilles concentrates differential pressures room by room. Under art. 368 CO, the client can assert their rights in the event of defects in the work if the installation delivers flow rates that do not comply with the design values. An acceptance record documenting the pressures and flow hood measurements protects the installation company.

Frequently asked questions

How do you accurately measure the opening force imposed by negative pressure?

The fitter uses a mechanical or digital dynamometer attached to the door handle, perpendicular to the plane of the leaf. Pull slowly until the frame's seal comes away. The maximum value recorded represents the overall force, which combines the mechanical resistance of the door closer, the friction of the hinges and the force applied by the residual negative pressure acting on the total area of the panel.

Why does commercial kitchen extraction destabilise the whole building?

A professional hood extracts very large volumes of air, up to several thousand cubic metres per hour. In an airtight envelope, if the dedicated compensation unit does not supply exactly the same flow of heated air, the entire building falls under strong negative pressure. Apartment entrance doors lock pneumatically, sanitary traps lose their water seal and odours flow back into the service ducts.

What gap under the door should be left to preserve pressure balance?

To ensure air transfer from a living room to the toilets without causing whistling or excessive pressure drop, an undercut of 8 to 10 millimetres is required under internal door leaves for a standard nominal flow rate of 30 m³/h. If airtight Swiss thresholds are required for acoustic reasons, fitting transfer silencers above the door becomes mandatory.

What should you do when negative pressure persists despite balanced flow rates at the units?

This problem often comes from an independent outlet that is not compensated, such as a central vacuum cleaner, a clothes dryer venting directly outside or a fireplace drawing combustion air from the room. Check that there are no uncontrolled parasitic air inlets, then check the calibration of the differential pressure sensors controlling the floor regulating dampers.

Texts and standards cited

  • norme SIA 382/1Ventilation and air-conditioning installations - General principles and required performance for air quality and airflow balance
  • CO art. 368Client's rights in the event of defects in the work