🧱 CFC 244Smoke extraction and fire dampersChapter 10 of 10 in the section

The safety inspection: what is checked, what blocks approval, how to prepare

Acceptance of a ventilation installation by the fire protection authority cannot be improvised at the end of the finishing work. This chapter details the method for compiling the compliance file throughout installation, anticipating the physical checks of the safety devices and organising the clearing of remarks efficiently to avoid any delay in commissioning.

Key takeaways

  • The AEAI quality assurance file is assembled from the initial installation of each fire-resistant element.
  • The real accessibility of the mechanisms and inspection hatches is the first reason for rejection.
  • Each damper requires a signed installation certificate confirming compliance with its specific approval certificate.
  • Airflow function tests must be validated internally before the joint official inspection.

Continuous compilation of the test and compliance file in accordance with AEAI directives

Obtaining the occupancy permit depends directly on the favourable opinion issued by the fire brigade or the cantonal fire protection authority. In air-handling and mechanical smoke extraction installations (CFC 244), the inspector checks that the devices fitted on the ducts exactly match the requirements of the AEAI fire directives. Waiting until the last days on site to gather the documentary evidence almost systematically leads to failure: the partitions are closed, the suspended ceilings are installed and the missing technical data sheets delay the validation of the whole building.

The file is compiled on a just-in-time basis, as the networks progress. Each fire damper, each smoke extraction damper and each section of fire-resistant duct is the subject of a documented self-inspection immediately after its connection and sealing. The team leader records the data in the technical site binder, which will be handed over to the site management and to the person responsible for fire quality assurance.

  • Updated as-built drawings showing the exact location and unambiguous identification of each fire damper and damper.
  • Certificates of use and AEAI certificates of conformity for all dampers, fire dampers and smoke extraction ducts.
  • Installation certificate records signed by the installer, certifying strict compliance with the sealing recommended by the manufacturer.
  • Photographic reports of wall penetrations before the installation of suspended ceilings or technical duct linings.
  • Records of the preliminary tests of mechanical release, airtight closing and resetting for each unit.

For mechanical smoke extraction installations, the file must include the airflow measurement records. The ventilation company records the air velocities, extracted flow rates and residual pressures measured with a Pitot tube or a thermal anemometer. These values demonstrate that the extraction fans and fresh-air intakes exactly meet the smoke extraction concept validated at the building permit application stage.

Critical blocking points during the inspection and procedure for clearing remarks

During the acceptance inspection, the fire brigade carries out visual destructive sampling and functional tests in situ. The presence of the ventilation site foreman is essential: he must operate the equipment, open the hatches and answer precisely questions about special installations. Certain recurring defects immediately block the granting of the certificate of conformity.

Frequent findings of the fire brigade and corrective actions
Item checkedFrequent blocking pointCorrective action required
Inspection hatchesHatch missing, blocked by a profile or too small to operate the bladeReplacement by a removable frame of at least 400 x 400 mm or direct access to the control
Duct sealingMineral wool stuffing without intumescent sealant or uncertified plasterComplete removal and rework in accordance with the AEAI approval report of the damper
Position contactsStandby or closed signal not relayed or inverted during the mechanical testCheck of the dry limit-switch microswitch and rewiring of the junction box
Smoke extraction damperBlade rubbing against the frame under negative pressure or mechanical jammingRealignment of the frame, cleaning of the guides and adjustment of the motor torque

In the event of non-conformity, the fire brigade records reservations in its inspection report and sets a deadline for bringing the installation into compliance. Under the law of contract for work and services governed by the Code of Obligations (CO), the contractor carries out the requested corrections without delay to allow the proper handover of the work. Once the remedial work is completed, a complete photographic file and corrected test sheets are sent to the authority. For critical points affecting fire stability or smoke extraction, a new on-site visit is required before the premises are finally released.

  1. Notification of reservationsImmediate analysis of the official list of remarks issued by the fire inspector and cross-checking with the execution drawings.
  2. Rework on sitePhysical correction of defective sealing, realignment of ducts or widening of technical access with the other trades.
  3. Photographic self-inspectionTaking precise photographs showing the conformity labels, the thickness of the sealing material and the free movement of the devices.
  4. Submission of the clearing reportTransmission of the signed official form for clearing remarks, validated by the ventilation engineer and the person responsible for fire quality assurance.

The full test in the presence of the authority: airflow scenarios and sequences

On the day of acceptance with the fire protection authority, commonly called the fire brigade depending on the canton, the role of the ventilation installer is not limited to showing the technical rooms. The authority requires a full-scale functional demonstration of the scenarios defined in the smoke extraction and compartmentation concept. The AEAI fire directives require all fire-resistant and smoke extraction devices to respond according to the interlocking matrix validated at the building permit application stage.

For the ventilation systems installer, this means directing or assisting with each activation: closing of motorised or fusible-link fire dampers, opening of smoke extraction dampers for collective ducts, starting of axial or centrifugal roof extractors, and starting of jet fans or fresh-air compensation fans. The on-site presence of an equipped fitter, a reset pole for dampers that cannot be reached from the floor and a calibrated vane anemometer avoids downtime and technical doubts.

Operational checks carried out live during the official inspection
Device checkedSimulated actionExpected result on the airflowPhysical check
Terminal or transit fire damperPower cut or thermal releaseAirtight stop of the airflow in the duct, no leakage at the sealVisual position of the blade via the external mechanical indicator
Mechanical smoke extraction damperOpening command for the affected compartmentNominal extraction established, no parasitic backflowFull travel of the louvres, section completely cleared
Smoke extraction fanSwitch to smoke extraction speedExtraction of the required flow rate according to the measurement sheetDirection of rotation of the impeller, no abnormal vibration
Pressurised lobby or stairwellActivation of the overpressure fanPressure gradient maintained relative to the landingMeasurement of the pressure difference and door opening force

During the actual tests, the inspector also checks that the ducts remain intact. Horizontal or vertical smoke extraction ducts made of calcium silicate or of sheet metal protected by spray coating must show no loosening of hangers and no deformation under the sudden negative pressure caused by the start-up of the extractor. The test and compliance file must be open on the table, with each signed self-inspection sheet next to the damper or fire damper being examined.

Handling non-conformities, clearing protocol and second visit

When the fire protection authority identifies blocking points, it issues an official report accompanied by a list of reservations. Two situations arise on the construction site. If the defects are classified as minor, such as the absence of an engraved identification plate on a hatch or a torn-off sealing label, the authority grants a deadline to submit a completed photographic report, without requiring a new on-site visit.

If, on the other hand, a critical point is found — for example a damper that does not close hermetically, a fire-wall penetration seal that does not comply with the AEAI approvals, or a smoke extraction flow rate lower than the requirements of the building permit —, the operating authorisation or occupancy permit is suspended. This situation engages contractual liability under the Code of Obligations (CO), the client being able to invoke the provisions on defects in the work under art. 367 CO and art. 368 CO.

  1. Analysis of the inspection report and targeting of the tradesSeparate the reservations attributable to the ventilation installation (blade tightening, alignment, duct connection) from those depending on the structural work or the electrician (refilling with special mortar, safety power supply).
  2. Carrying out the technical correctionsReplace the defective parts, redo the annular sealing according to the manufacturer's instructions and readjust the airflow balancing dampers.
  3. Internal retest and update of the documentationRepeat the complete operation on each corrected device, record the new flow value or the closing report on the record sheet and attach the detailed photographs.
  4. Summons for the second visitSend the revised test and compliance file to the site management and to the fire brigade to schedule the final re-inspection, limited to the disputed points only.

During the second visit, the cantonal or communal inspector generally limits his check to the items notified in the initial report. Presenting a clear file, in which each remark is ticked off with its date of correction, the fitter's initials and the data sheet of the sealing material used, makes it possible to obtain the signature of the fire certificate of conformity without further technical discussion.

Handling a refusal of acceptance: immediate action plan and second visit

When a smoke extraction test fails or a fire damper refuses to close in the presence of the fire protection authority, the occupancy permit is suspended. This crisis situation requires a methodical reaction from the ventilation fitter, without improvisation on site. The record lists immediately the non-conformities found by the fire brigade. As soon as the inspection ends, the foreman records the malfunctions observed: damper blocked by plaster residue, airflow response time outside tolerance or mismatch of the standby position.

  1. Isolating the causes and recalibratingEach device at fault undergoes a partial dismantling of its casing or access hatch to check the mechanical components. For a fire damper, check for the absence of mechanical stress on the shaft, the cleanliness of the casing and the alignment of the limit-switch microswitches. For the smoke extraction network, the flow rates and differential pressures are measured again using a calibrated differential manometer.
  2. Coordination with third-party tradesIf the problem comes from a missing control command or a loss of feedback signal, the responsibility goes beyond the airflow installation. The ventilation installer organises a technical alignment meeting on site with the electrician and the integrator to physically check the wiring as far as the servomotor connection terminal blocks.
  3. Dry-run dress rehearsalBefore requesting a new inspection, the entire extraction and compartmentation scenario must be replayed internally. No second visit must be scheduled until 100 % of the dampers and fire dampers have validated two complete, consecutive opening and closing cycles under airflow.

The request for a second visit is accompanied by a complete amended file submitted to the site management. This document compiles the corrected self-inspection sheets, the photographs of the sealing rework with fire-resistant mortar and the new signed flow rate readings. This file proves the formal clearing of each reservation even before the fire brigade returns to the building.

Frequently asked questions

What should be done if the fire brigade finds a fire damper that is inaccessible for maintenance?

An inspection hatch that is too narrow or hidden by other pipes is grounds for immediate rejection. The installer must immediately coordinate with the plasterboard fitter or the suspended-ceiling fitter to enlarge the opening. According to the rules of good practice, the clear passage must allow direct visual access to the mechanism, manual resetting of the spring and inspection of the fire blade without dismantling the surrounding air network.

How can a deviation of the smoke extraction flow rate from the fire concept be justified?

If the flow rate measured at the extraction grilles is lower than the values of the approved concept, the fan cannot be accepted as it stands. The installer checks the airtightness of the smoke extraction ducts and recalibrates the balancing dampers. If the network is airtight but undersized, adjustment with the ventilation engineer is required to adjust the rotation speed of the extraction fan.

Who must provide the certificates of conformity for through-penetration sealing?

The company awarded the ventilation package is responsible for the traceability of the compartment penetrations that it carries out or subcontracts. Each penetration of a fire-resistant slab or wall must receive a permanent label indicating the product used, the targeted fire resistance and the date of application. These items are compiled in the self-inspection file handed over to the fire brigade at the final inspection.

Can a fault in the electrical interlocking be attributed to the ventilation fitter?

The ventilation fitter guarantees the airflow connection, the freedom of mechanical movement of the devices and the continuity of the damper's internal terminal blocks. If the motor does not receive the opening or closing command, the problem lies with the electrical installation or the building management system. The ventilation installer must nevertheless prove the correct operation of his equipment by a manual release on site.

Texts and standards cited

  • Directives de protection incendie AEAISwiss fire protection requirements for air-handling installations, mechanical smoke extraction and fire compartmentation.