Key takeaways
- The most unfavourable branch depends more on the fittings along the route than on the straight length.
- Local losses such as bends and reducers often account for two thirds of the total pressure.
- The SIA 382/1 standard governs air velocities in order to limit excessive linear pressure losses.
- Fan sizing must include the final pressure loss of the clogged filters.
Identifying the critical branch and adding up the local losses along the route
On a ventilation construction site, the classic mistake is to equate the critical branch with the diffuser geometrically furthest from the air-handling unit. In practice, the most unfavourable branch is the one with the highest cumulative airflow resistance between the fan and the terminal. A short section with high air velocities, two sharp-angle bends, a fire damper, a terminal reheat coil and a high-induction diffuser often generates a total pressure loss greater than fifty metres of regular straight duct.
- Most unfavourable branch
- Airflow path linking the ventilation unit to a given terminal that has the highest sum of linear and local pressure losses. It dictates the minimum useful static pressure required from the fan.
To draw up the calculation sheet according to the SIA 382/1 standard, the fitter or project manager breaks the network down into homogeneous sections of constant flow rate and cross-section. The total pressure loss of a section combines the linear pressure loss due to air friction against the metal wall and the pressure loss of fittings caused by local turbulence.
| Component or fitting | Typical air velocity | Loss coefficient (Zeta) | Average pressure loss |
|---|---|---|---|
| 90° circular bend (r/D = 1.5) | 4.0 m/s | 0.20 to 0.25 | 2 to 3 Pa |
| Rectangular bend without vanes | 4.5 m/s | 1.10 to 1.30 | 13 to 16 Pa |
| 90° branch connection on main header | 4.0 m/s | 0.80 to 1.20 | 10 to 14 Pa |
| Fire damper, open (thin blade) | 3.5 m/s | 0.40 to 0.60 | 3 to 5 Pa |
| Splitter-type sound attenuator (length 1 m) | 4.5 m/s | — | 25 to 45 Pa |
| Ceiling-mounted swirl diffuser | 2.5 m/s | — | 20 to 35 Pa |
Every throttling or transforming fitting causes a pressure drop proportional to the square of the air velocity. Arbitrarily reducing the diameter of a duct to pass through a concrete opening or to avoid a sanitary pipe doubles the local velocity and multiplies the local loss of the fitting by four.
Sizing the filter clogging margin and setting the fan
In a balanced-ventilation installation, the filtration stages are the most variable airflow obstacle in the system. A new filter box presents a moderate initial resistance, but this doubles or even triples as dust accumulates in the filter media. If the fan is set on the pressure loss in the clean state, the fresh air flow drops continuously over the weeks of operation.
To ensure the lasting supply of the hygienic air flow prescribed by the SIA 382/1 standard, the available fan pressure must be calculated by including the filter clogging margin. Two methodological approaches are found on projects in French-speaking Switzerland:
- Constant-flow approach via frequency controller: the fan is sized to overcome the network with the filters at their maximum final pressure loss (final Delta P). The motor runs at reduced speed when new, then accelerates automatically under the control of a differential pressure sensor.
- Fixed-speed setpoint approach: the selection calculation uses the average operating pressure loss, calculated as the arithmetic mean between the initial clean loss (for example 70 Pa) and the tolerated final loss (200 Pa), i.e. 135 Pa. A temporary flow deviation is then tolerated at the end of the maintenance cycle.
- Adding up the critical branch in the clean stateAdd the linear losses of straight duct, all the geometric local losses, the silencers, the balancing dampers and the most demanding terminal diffuser.
- Adding the internal resistance of the air-handling unit componentsInclude the pressure losses of plate or rotary heat recovery exchangers, free-air heating or cooling coils and mixing dampers.
- Adding the clogging margin and the adjustment marginAdd the clogging pressure rise of the filters (difference between final value and clean value) as well as a minimum margin of 10 to 15 % (or 30 to 50 Pa) intended for air balancing at the branch dampers.
Quantifying local losses: from the fire damper to the heat exchange coils
On an air-distribution route in an office building or collective housing, the linear pressure losses due to air friction against the walls of rectangular or spiral ducts commonly account for only a third of the total resistance. The rest of the required static pressure is absorbed by the local losses: bends with or without guide vanes, abrupt reductions, branch connections on headers, splitter silencers and treatment components. The SIA 382/1 standard imposes strict control of the specific fan power, which prohibits arbitrarily oversizing the motors to compensate for a poorly calculated, tortuous network.
- Local loss coefficient (zeta)
- Dimensionless factor specific to each fitting or component geometry, used to calculate the dynamic pressure loss as a function of the air density and the flow velocity in the duct.
Every obstacle introduced into the most unfavourable branch generates a pressure drop proportional to the square of the air velocity. A fire damper that is misaligned or installed in an area where the velocity approaches 6 m/s creates a resistance well above that of twenty linear metres of smooth straight duct. Finned coils (recovery exchangers or in-line treatment coils) and dissipative silencers require particular attention, because their pressure loss values depend not only on the theoretical manufacturer catalogues, but also on the approach profiles of the airflow upstream.
| Component or fitting | Typical geometric factor | Average pressure drop (Pa) |
|---|---|---|
| 90° circular bend without vanes (R/D = 1) | zeta = 0.25 to 0.35 | 4 to 8 Pa |
| 90° rectangular sharp-edged bend without vanes | zeta = 1.20 to 1.40 | 18 to 28 Pa |
| Splitter silencer (length 1000 mm) | Manufacturer data / free passage | 35 to 70 Pa |
| Fire damper with blade open in the airflow | zeta = 0.40 to 0.70 | 8 to 15 Pa |
| Heat exchange coil (tube and fin) | Depending on fin pitch and rows | 60 to 120 Pa |
| Plenum box with adjustable terminal diffuser | Depends on the final throttling | 20 to 50 Pa |
Setting strategy: network balancing and carrying over the filtration margins
In the final calculation of the total pressure required to select the fan, the pressure loss of the filters is never taken in the new state, otherwise the nominal flows collapse after a few weeks of operation on the construction site. Nor is it taken at the maximum final clogging tolerated by the differential pressure switch, because the machine would run permanently beyond its optimum efficiency point for a temporary state. The recognised practice in Switzerland under the SIA 382/1 standard is to include the average pressure loss: initial pressure loss increased by 50 % of the difference up to the replacement limit.
- Determining the route of the critical branchTrace the complete path from the outdoor air intake to the most resistant terminal diffuser. Add up the linear losses and the pressure loss of fittings without applying any flat overall margin at this stage.
- Including the filter clogging setpointAdd the average clogging value for each filtration stage (coarse pre-filtration and F7/ePM1 fine filter). For a filter starting at 70 Pa and saturated at 200 Pa, the calculation value is 135 Pa.
- Defining the authority of the balancing dampersCheck the pressure difference between the most unfavourable branch and the shorter secondary branches. The metering dampers or balancing dampers must be chosen to dissipate this excess without generating excessive noise levels in the suspended ceilings.
- Checking the flow velocitiesMake sure that the velocity in the main ducts stays within the limits prescribed for acoustic comfort and energy efficiency, avoiding extra dynamic losses at the direct discharge of the fan.
At acceptance on the construction site, the contractor checks with an anemometer and a differential manometer that the residual pressure at the critical diffuser corresponds to the balancing sheets. The branch ducts undergo controlled throttling by means of manually or motor-operated dampers, ensuring that the air does not take the path of least resistance to the detriment of the remote rooms. A network rigorously sized according to the principles of the most unfavourable branch guarantees correct air distribution to all volumes without whistling at the supply outlets.
Airflow shortfall during tests: diagnosis and corrective measures on the network
During acceptance airflow measurements on an installation under the SIA 382/1 standard, a fresh air or extract air flow below the contractual tolerances signals an uncontrolled pressure deviation. If the fan runs at its nominal speed without delivering the prescribed air volume to the terminal diffusers, the real pressure loss of the network exceeds the forecast of the calculation sheet. This phenomenon frequently occurs when local losses have been underestimated in favour of a simple linear measurement of rectangular or circular duct.
The first step is to isolate the components of the air-handling unit by measuring the differential pressure across each stage. New filters clogged by construction dust during the finishing phases immediately distort the operating point. If the filter boxes and the exchanger show losses consistent with the manufacturers' data sheets, the origin of the blockage lies in the air distribution outside the unit.
- Measure the static pressure along the route to locate the local loss responsible for the abnormal pressure jump.
- Check the actual position of the fire dampers, control dampers and pressure relief dampers, often throttled by mistake.
- Check the profile of the transition pieces, branch connections and sharp-angle bends installed without guide vanes.
- Measure the current drawn by the fan motor to check the margin available on the frequency drive.
If the network shows excessive resistance attributable to spatial changes imposed by other trades, art. 365 para. 3 CO requires the client to be informed where circumstances jeopardise the proper or timely execution of the work. The ventilation contractor documents the manometer readings compared with the calculation assumptions of the critical branch.
The technical correction first requires the elimination of accidental local losses: replacing a crushed bend with a large-radius model, fitting guide vanes on a change of direction imposed by the concrete, or opening choked terminal dampers. As a last resort, if the network remains physically constrained, increasing the fan setpoint compensates for the excess pressure loss, provided that the acoustic limits and the energy efficiency requirements of the SIA 382/1 standard are respected.
Frequently asked questions
How can the most unfavourable branch be identified with certainty on a complex route?
The most unfavourable branch is not necessarily the longest in linear metres. It is the airflow path with the highest sum of linear and local pressure losses from the fan to the terminal diffuser. To identify it, the resistance of each branch is calculated by adding the dynamic pressures dissipated by the bends, branch connections, fire dampers, silencers and diffusers, taking into account the actual flow in each section.
What value should be used for the filter clogging margin in an air-handling unit?
The clogging margin is the difference between the initial pressure loss of a clean filter and its permissible final pressure loss. To size the fan according to the SIA 382/1 standard, the arithmetic mean between the clean state and the saturated state prescribed by the manufacturer is generally used, often an average value of 100 to 150 Pa for an ePM1 stage, in order to guarantee the average operating flow without oversizing the motor.
Should the pressure loss of the balancing dampers be included in the initial calculation sheet?
Yes. On the critical branch, the terminal control damper is planned in a nearly open position, but a residual pressure loss of 15 to 25 Pa must be kept to allow fine adjustment. On the shorter or less loaded secondary branches, the dampers absorb the excess pressure by throttling to balance the terminal flows without disturbing the total flow of the installation.
What should be done on the construction site if the measured pressure loss exceeds the forecast by 20 %?
The installer first checks the cleanliness of the filter cells and the mounting direction of the grilles and silencers. He then checks the velocity in the ducts using a Pitot tube or a vane anemometer. If a layout change during structural work has multiplied the bends, an airflow readjustment or a revision of the fan speed must be formally submitted to the site management.
Texts and standards cited
- SIA 382/1Ventilation and air-conditioning installations - General principles and energy performance
- CO art. art. 365 al. 3 COImmediate notice to the client if circumstances jeopardise the proper or timely execution of the work