🧱 CFC 244Air handling unit and heat recoveryChapter 4 of 10 in the section

Filters: class by use, measured fouling and actual replacement interval

This chapter gives you the tools to select the filtration stages suited to the requirements of standard SIA 382/1, to fit differential pressure taps in accordance with good practice and to define the exact clogging threshold. You will know how to record this setpoint on the air handling unit to avoid excess electricity consumption by the fans.

Key takeaways

  • Standard SIA 382/1 defines the filtration stages according to the quality of the outdoor air.
  • Changing a filter blindly causes electricity costs far higher than the price of the filter medium.
  • Differential pressure measurement requires static pressure taps correctly oriented upstream and downstream.
  • The final replacement threshold must be recorded on a label visible on the casing.

Selecting the filtration class according to air quality and standard SIA 382/1

In an air handling unit, the sizing of the filtration stages is not a matter of construction-site habit but of a strict match between the purity of the outdoor air drawn in (ODA) and the level of cleanliness required in the rooms served (SUP). Standard SIA 382/1 sets these requirements to guarantee the health protection of the occupants as well as the technical integrity of the internal components, in particular plate or rotary heat recovery units and heat exchange coils.

ISO 16890 classification
International standard replacing the former EN 779 classification (G4, M5, F7, F9). It assesses the mass filtration efficiency according to three fine particle fractions: ISO ePM1, ISO ePM2,5 and ISO ePM10, supplemented by the ISO Coarse category for coarse dust.
Typical filtration stage configurations according to standard SIA 382/1
Room useSupply air quality (SUP)First stage (fresh air)Second stage (supply)
Offices, administrative roomsSUP 2ISO ePM10 50% (pre-filter)ISO ePM1 50% to 70%
Multi-unit housing (balanced ventilation)SUP 2ISO Coarse 65% (heat exchanger protection)ISO ePM1 55%
Healthcare facilities, nurseriesSUP 1ISO ePM2,5 50%ISO ePM1 80% or higher
Technical rooms, storage roomsSUP 4 / SUP 5ISO Coarse 60%Not required

Fitting a first stage of coarse filtration directly at the façade or at the inlet of the fresh air casing protects the preheating coil and the heat exchanger against pollen, leaves and heavy soot. The second stage, placed downstream of the supply fan or just before the duct network, retains the respirable fine particles without prematurely loading the final filter medium.

Measuring the pressure drop and recording the permissible final pressure

Waiting for an arbitrary annual maintenance visit to replace the filter cells is a major operating error. As dust accumulates, the airflow resistance of the medium increases continuously. To maintain the hygienic design airflow, the control system speeds up the electronically commutated fan (EC motor). This compensation increases the electrical power absorbed in proportion to the product of the airflow and the overpressure. The extra energy cost quickly exceeds the price of a new set of replacements.

Monitoring must rely on continuous airflow measurement. The installer fits an inclined differential manometer or an electronic differential pressure switch connected on either side of each filter frame. The static pressure taps must be positioned perpendicular to the airflow, outside the turbulence zones created by dampers or intake bends, in order to measure the actual pressure drop without dynamic disturbance.

  1. Reading the initial pressure drop (clean filter)Set the installation to the nominal commissioning airflow. Read the pressure drop value displayed by the differential manometer in Pascals.
  2. Calculating the permissible fouling thresholdAdd the tolerance recommended by standard SIA 382/1 and the manufacturer, generally double the initial pressure drop without exceeding 150 Pa to 200 Pa on a final stage.
  3. Setting the signalling deviceAdjust the calibration screw of the differential pressure switch or configure the alarm threshold of the pressure sensor on the unit's control system.
  4. Permanent marking on the machineFix a rigid label to the access panel stating the commissioning date, the filter dimensions, the type of medium, the initial pressure drop and the replacement limit value.

Airflow drift, electricity cost and differential instrumentation

In an air handling unit, delaying the renewal of filter media on the grounds that they look visually acceptable is a serious economic mistake. On modern installations fitted with electronically commutated motor-fans or driven by a frequency converter, the control system maintains a constant airflow. As dust accumulates in the fibre network, the airflow resistance increases. To compensate for this rise in pressure drop, the fan automatically raises its rotational speed, which causes a cubic increase in the power absorbed at the drive shaft.

Letting a filter reach two to three times its nominal pressure drop makes the client spend far more on electricity within a few weeks than the value of a new set of replacements. Fouling is therefore never assessed by eye, but exclusively by measuring the differential pressure drop between the upstream and downstream zones of the filter casing.

Connecting the differential manometer requires rigorous care in installation. Whether it is an inclined liquid-column manometer, a magnetic diaphragm dial or an electronic pressure transmitter connected to the control system, the measuring connectors pass through the unit's sheet metal via sealed bulkhead fittings. The upstream tap is placed in a stable flow zone, without leading-edge turbulence, while the downstream tap is placed sufficiently far back from the discharge plane of the bags or V-cells. Pinched or twisted plastic capillary tubes immediately distort the signal, preventing detection of the critical fouling threshold.

Recording thresholds on the unit and replacement protocol

To guarantee energy efficiency and preserve the hygiene of the air distribution network, each filter casing must carry an indelible label applied directly to the inspection panel. This notice states the date of the last change, the initial pressure drop measured with a new filter at the design airflow, and the maximum final pressure drop allowed before replacement. According to standard SIA 382/1, operation must combine this pressure drop monitoring with a maximum duration criterion to prevent any bacterial or fungal growth on damp fibres.

Operating thresholds and differential pressure drop limits per stage
Filtration stageAirflow useTypical initial pressure drop (Pa)Recorded replacement threshold (Pa)Maximum time limit
Coarse pre-filtrationProtection of AHU components and heavily loaded fresh air40 to 7015012 months
Intermediate fine filtrationStandard commercial fresh air and general extract air70 to 110200 to 25012 months
Final AHU filtrationHigh-grade office premises and buildings open to the public90 to 13025012 to 24 months

During interventions, the fitters look after their own safety in accordance with art. 3 OPA, the employer taking the protective provisions and measures that meet the recognised rules of technology for handling filter media loaded with fine particles and spores. In practice, the operator wears suitable respiratory protection and switches off the fan before opening the inspection doors.

  1. Isolating the unit and sealed removalStop the supply fan unit and lock the local isolator switch. Release the clamping cams without shaking the frames so as not to release dust into the casing. Immediately slide each used element into a thick airtight bag for removal from the plant room.
  2. Cleaning the fixed frame and checking the sealsVacuum the bottom of the casing and the slides with a vacuum cleaner fitted with a fine dust filter. Check the elasticity and adhesion of the neoprene seal at the bottom of the rebate. Any crushed or detached seal must be redone to rule out stray air paths.
  3. Fitting the new cells and airflow validationInstall the new media following the airflow direction arrow printed on the frames and placing the flexible bags vertically without fail. Tighten the clamps evenly, restart the machine at nominal speed, measure the new differential pressure and record the value on the front label.

Filtration failures, extreme clogging and handling of operating disputes

Neglected filtration on an air handling unit inevitably leads to two critical situations on Swiss installations: mechanical collapse of the medium under excessive differential overpressure, or severe energy drift of the equipment. When the maximum permissible pressure drop defined according to standard SIA 382/1 is ignored, the electronically controlled motor-fan compensates by increasing its rotational speed. The result is disproportionate electricity consumption, premature overheating of the bearings and, in the long run, a sudden collapse of the fresh airflow delivered to the ventilated rooms.

  1. Emergency stop and airflow safety measuresSwitch off the ventilation unit at once at the lockable isolator to prevent torn fibres from being drawn into the fan wheel and to avoid pollutant particles becoming directly embedded in the fins of the heat exchanger.
  2. Fouling diagnosis and cleaning of the casingRemove all the damaged frames and carefully inspect the casing downstream. Methodically vacuum the dust deposits using an industrial vacuum cleaner fitted with very high efficiency filtration in order to avoid any dispersion into the duct network.
  3. Replacement and check of mechanical sealingClean the slides, check that the gaskets are uniformly compressed and insert the new set of filters of the required class. Make sure that no untreated air bypass remains between the supporting frames and the machine casing.
  4. Differential measurement and on-site traceabilityMeasure the initial pressure drop at nominal airflow with a portable manometer. Reset the zero of the inclined-tube manometer or calibrate the differential pressure switch, then enter the date and the final threshold value on the door data plate.

In a dispute with the client or the operator concerning insufficient airflow or abnormal energy bills, the commissioning records are authoritative. Art. 364 CO requires the installer to carry out the work with care and in accordance with the recognised rules of the building trade. The omission of a functional differential manometer, of correctly positioned pressure taps or of the mandatory labelling of the initial and final pressure drops irreparably weakens the fitter's position during expert assessment.

Frequently asked questions

What should you do if the differential manometer indicates zero or abnormally low pressure drop?

A differential pressure close to zero on a filter in service indicates either a torn medium, a dislodged frame, or blocked copper or plastic pressure tap tubes. Switch off the unit, check the physical integrity of the filter and inspect the seating of the seals. Then blow through the measuring tubes towards the manometer to clear any condensate or dust, then check the zero of the dial indicator.

Can a bag filter be dusted off with compressed air to extend its use?

Dusting off with compressed air is strictly prohibited on ventilation installations. This operation tears the microscopic structure of the glass or polypropylene fibres, reducing filtration efficiency to nothing while releasing a cloud of concentrated pollutants into the workshop. Even if the pressure drop falls artificially, the filter loses its efficiency class and lets fine particles pass directly to the exchangers and the treated rooms.

Why must the replacement threshold be calculated according to electricity consumption?

The airflow power absorbed by the fan is directly proportional to the airflow and to the overall pressure drop of the network. The more dust the medium collects, the more the differential pressure increases, forcing the motor to consume more kilowatt-hours. Exceeding the recommended economic threshold means spending more on electricity to force air through than on buying and fitting a new set of filters.

What are the risks for the installer if there is no differential pressure indicator?

The absence of a differential measuring device deprives the operator of any objective means of monitoring fouling. Under the rules of good practice and the compliance obligations of the works, the ventilation contractor incurs contractual liability if insufficient airflow or damage to a coil occurs through lack of monitoring. Fitting a local indicator and displaying the pressure drop values are technical deliverables that are indispensable at acceptance.

Texts and standards cited

  • norme SIA 382/1Ventilation and air-conditioning installations - General principles and required performance
  • CO art. 364contractor's obligations: liability subject to the same rules as that of the employee; he carries out the work in person or under his personal direction; unless custom or agreement provides otherwise, he procures at his own expense the means, equipment and tools required.