Duct network and air-tightness: the execution standard
Intended for ventilation fitters, team leaders and site supervisors, this section brings together the Swiss rules for assembling, supporting, insulating and accepting steel sheet or circular duct networks. It details practical methods to ensure air-tightness, avoid acoustic bridges, prevent condensation-related defects and preserve access for mechanical cleaning without damaging suspended ceilings.
- 10chapters
- 22 000words
- 6sections in the training course
- 60chapters in total
Key values to remember 4
Class C
Standard air-tightness class required for high-performance ventilation duct networks
1.5 m
Maximum recommended straight length for a flexible terminal connection duct
0.15 m/s
Maximum residual air velocity in the seated occupancy zone to avoid discomfort
2 m
Fall height that triggers the installation of guardrails on unprotected openings
Scope of work of the ventilation fitter and limits of supply
The installation of duct networks as part of ventilation and air-handling systems (CFC 244) is subject to strict requirements defined by standard SIA 382/1 and standard SN EN 12237. The ductwork fitter's work begins at the discharge or intake flange of the air-handling unit (or the extract fan) and ends at the mounting frame of the supply diffusers, extract grilles or smoke-extraction dampers. Along this entire route, the installer ensures the air-tight assembly of straight sections, bends, reducers and plenum boxes, the installation of hangers with acoustic bridge breaks, and the fitting of balancing and fire-safety devices.
As regards responsibilities on site, art. 229 CP punishes anyone who, intentionally or through negligence, breaches the recognised rules of construction and thereby endangers the life or physical integrity of persons. The secure suspension of heavy rectangular ducts above circulation routes, scrupulous compliance with fire-stopping at wall penetrations and the certified anchoring of smoke-extraction ducts fall directly under this duty of rigour. As regards worker protection, OTConst requires openings in floors that present a fall hazard to be fitted with a perimeter guardrail or a cover that is resistant to breaking and securely fixed, which applies without reservation to duct openings left open before the risers are installed.
| Installation item | Ventilation contractor (CFC 244) | Other trades |
|---|---|---|
| Through-opening in concrete slab | Supply of dimensioned opening drawings and templates | Opening, formwork and structural work drilling (CFC 211.1) |
| Wall-mounted fire damper | Supply, sealing in accordance with the installation test report and mechanical check | Electrical connection and fire interlocking (CFC 232) |
| Fire-rated penetration without damper | Installation of the fire-resistant duct with its certified clamps | AEAI-approved fire-stopping per manufacturer's instructions (CFC 244 or specialist third party) |
| Terminal water coil | Air-side integration in the duct and sealing of joints | Valves, hydraulic pipework and flow/return connection (CFC 241) |
| Condensate tray and trap | Supply of the ball trap, water seal and upstream slope | Connection to the main drainage network and sewer discharge (CFC 250) |
Step-by-step path: from route design to airflow acceptance
Building an air distribution network tolerates no improvisation. An air-tightness defect or a badly arranged bend in a congested suspended ceiling causes excessive pressure losses, acoustic whistling that cannot be corrected and a drift in the fans' electricity consumption. The progression through the ten chapters of this section follows the exact chronology of execution on the construction site, from the choice of air-tightness classes to the final setting of the diffusers in the occupied space.
- Controlling leaks and assembly technology (K2-01 and K2-02)The network must meet the requirements of the assigned air-tightness class (class B or C according to standard SIA 382/1 and standard SN EN 12237). The opening chapters cover the air-pressure test protocols and detail the mechanical assembly of circular ducts with factory-crimped EPDM seals as against profiled rectangular ducts assembled with frames and corners, prohibiting unsuitable sealants and temporary adhesives.
- Supporting and mechanically decoupling the installation (K2-03)The duct hangers must support the dead weight of the metal and its insulation without residual deflection, while cutting the transmission of mechanical vibrations to the raw slab by means of damping sleeves and correctly sized anti-vibration fixings.
- Managing thermal physics and lasting hygiene (K2-04 and K2-05)External insulation prevents the dew point from occurring in cold or humid surroundings and limits heat losses. Air-tight access hatches must be positioned strategically upstream and downstream of each singularity to allow brushing or camera inspection in accordance with the hygiene guidelines.
- Connecting terminals without aeraulic compromise (K2-06, K2-07 and K2-08)Flexible duct must be limited to short, perfectly taut terminal connections. Passing through fire-rated walls requires strict compliance with the AEAI installation approvals. Finally, the choice and orientation of the air terminal devices ensure the correct residual air velocity in the occupied zone without any risk of uncomfortable draughts.
- Ensuring site cleanliness and arbitrating coordination (K2-09 and K2-10)The cleanliness of the installation requires immediate air-tight capping of the sections during storage and installation. Finally, sharing the ceiling void with cable trays and fluid pipework requires rigorous technical coordination with the site management.
📘 Chapters in this section 10
Airtightness of the network: class B or C, leakage test and consequence of a failure
Avoid costly rework with the pressurising unit by mastering the strict air-tightness criteria for duct networks.
Duct network and airtightnessJoining without leaks: sealing gasket, sealant, tape and what does not hold
Discover reliable mechanical assemblies with crimped seals to eliminate makeshift sealing with mastic.
Duct network and airtightnessHanging the network: support spacing, deflection and vibration noise
Hang your ducts without deflection or vibration noise transmitted to the load-bearing structure.
Duct network and airtightnessInsulating ducts: condensation in an unheated room, vapour barrier and outer duct
Prevent water seepage and damage by controlling the vapour barrier on cold or external ducts.
Duct network and airtightnessBeing able to clean: access hatches, accessibility and blind ductwork
Position access hatches sensibly to ensure easy mechanical brushing with no blind sections of the network.
Duct network and airtightnessFlexible duct: short, taut, straight, or not at all
Learn why and how to restrain flexible duct to save your available airflows and pressures.
Duct network and airtightnessPassing through a slab: opening, fire-stopping seal and sound transmission
Make your fire-stopping in slabs a success without spreading structure-borne noise between the different floors.
Duct network and airtightnessOutlets and diffusers: throw, residual velocity and comfort for seated occupants
Adjust the throw and the Coanda effect of your diffusers to guarantee impeccable seated thermal comfort.
Duct network and airtightnessKeeping the system clean: plugs, storage and construction-site dust
Keep your networks spotless from delivery by systematically capping them against mineral dust.
Duct network and airtightnessFifteen centimetres for three trades: coordination, right of way and arbitration
Defend your clearance in the suspended ceiling against the electricians and plumbers during coordination.