🧱 CFC 244Duct network and airtightnessChapter 9 of 10 in the section

Keeping the system clean: plugs, storage and construction-site dust

By the end of this chapter you will be able to organise watertight storage of ventilation ducts, fit end caps that withstand site conditions and apply self-inspection rules to prevent any ingress of plaster or mineral dust before commissioning under SIA 382/1.

Key takeaways

  • Ducts delivered without protection or unpacked too early accumulate mineral deposits from the structural work.
  • Every interrupted duct section receives a sealed plug, immediately fixed with installation adhesive.
  • Sanding of partition walls turns open ducts into reservoirs of very harmful fine dust.
  • Acceptance of the air duct system requires a systematic internal visual inspection before the very first air blow-through.

Ensure dry storage and systematic sealing from delivery onwards

A balanced-flow ventilation system carries hygienic air directly to living areas and bedrooms. If spiral or rectangular ducts lie directly on a dusty bare slab, or remain exposed to the weather along façades, the residual forming oil inside the zinc coating absorbs moisture and binds cement dust. Cleaning a system fouled by construction-site sludge later on is particularly complex and costly, all the more so as insulated ducts, or ducts built into suspended ceilings, become inaccessible once the plasterboard is fitted.

Temporary sealing
Temporary airtight closure applied to each duct end, branch, tee or distribution box, kept in place from manufacture until the final connection of the diffuser.

Cleanliness management starts in the logistics area. Circular ducts, rigid spiral tubes and oval ducts must be unloaded onto timber blocks providing a minimum ground clearance of 100 mm. The components are stored in a closed, ventilated room free of grinding or cutting dust. If temporary outdoor storage is unavoidable before craning, a waterproof, ventilated tarpaulin must cover the pallets without touching the ground, while the original PE caps remain intact.

  1. Inspection on receipt at the construction siteCheck that the factory plastic covers are present on every duct end. Immediately replace any seal torn off during unloading with a bonded watertight plastic sheet.
  2. Placing in the installation areaBring in only the lengths needed for the day's work section. Never store bare ducts directly on the screed or in a room where mortars are being prepared.
  3. Immediate sealing at the end of the shiftFit a rigid polyethylene cap or a polyethylene film at least 80 micrometres thick, secured with site cloth adhesive tape, on every open end.

Protecting ducts during the finishing work and checking hygiene before start-up

The critical pollution phase occurs during the work of the plasterers and painters. Mechanical sanding of plasterboard joints generates a dense cloud of very fine particles, often smaller than 5 micrometres. If a branch is left uncovered in a room while waiting for its supply air terminal, the system acts as a thermal chimney and draws in this dust by natural draught. At the first start-up of the air handling unit, this mineral deposit is blown directly into the living spaces, clogs the F7 or ePM1 fine filters within a few hours and permanently degrades indoor air quality.

Components and duct systems must be protected against fouling during transport, storage and installation. Openings must be kept closed until the appliances and terminals are fitted.

norme SIA 382/1
Protection measures according to the progress of the other trades
Construction phaseMain air duct riskProtection required
Pouring of liquid screedsSaturated humidity, early corrosionWatertight caps sealed with vapour-tight adhesive
Installation of lightweight partitionsDust from cutting and mineral woolPE plugs kept on all wall branches
Sanding of renders and plastersUltra-fine dust corrosive to motorsWatertight plugs kept in place, use of the system prohibited
Spray painting / finishesMists of solvents and resinsPlastic protection kept until the grilles are fitted

It is strictly forbidden to switch on the controlled mechanical ventilation system to dry out the building or ventilate rooms during finishing work. If the ducts have been polluted because another trade removed a plug without authorisation, the installer must notify the site management. Under art. 365 para. 3 CO, the contractor must notify without delay any circumstances that jeopardise proper execution of the work, so that responsibilities can be established before the system is energised.

The pre-commissioning check is carried out by direct visual inspection with a mirror and a powerful torch at the terminal branches, or with a video endoscope for inaccessible horizontal sections. If whitish traces of plaster or earthy deposits are found, mechanical dust removal by rotary brushing combined with an absolute-filtration extractor is required at the expense of the party responsible for the contamination, before any final fitting of terminal units and air flow balancing.

Pollution from sanding dust: fouling mechanism and sealing rules

On a ventilation construction site, the critical finishing-work phase coincides with plastering, skim-coating and sanding of lightweight partitions. Plaster dust, extremely fine and abrasive, stays suspended in the ambient air for several hours. When a supply or return air system is left open near these operations, a natural thermal draught develops inside the risers. Mineral particles are then drawn into the spiral and rectangular ducts and coat the inner galvanised sheet wall, the sound attenuators and the control devices.

This static deposit is not simply removed by the first air purge. Bound by the residual moisture in the building, the plaster dust clumps in the corrugations of flexible ducts and the slots of balancing dampers. When the system is finally started, the air flow continuously pulls these microparticles loose and expels them directly into the living spaces. This phenomenon can persist for months after the occupants move in, causing hygiene complaints and premature clogging of the terminal diffusers.

  • Immediate fitting of PE plugs on every section when installation work is interrupted for the day.
  • Airtight sealing of slab outlets and wall stubs before the painters and plasterers start work.
  • Strict instruction prohibiting use of the supply air system as a temporary extraction system to ventilate the construction site.
  • Full protection under plastic film of the baffle silencers and terminal coils as soon as they are fixed on their brackets.
Suitability of temporary protection according to location and construction phase
System componentSealing device requiredMechanical resistanceRisk if absent
Spiral circular duct awaiting connectionTight push-fit polyethylene cap plugHigh (withstands knocks from brooms and draughts)Plaster settling at the bottom of the horizontal duct
Rectangular distribution ductThick polyethylene plastic sheet (150 µm) taped around the perimeterMedium (weekly checks mandatory)Fouling of the walls and damage to the sealing gaskets
Silencers and sound attenuatorsComplete cover sealed at the factory, kept closedHigh (original protection kept until connection)Irreversible saturation of the mineral wool absorbent mats
Terminal distribution boxMetal cover for the opening or rigid clip-on sealVery high (withstands splashes of render and paint)Mechanical jamming of the air flow adjustment mechanism

Installation protocols, requirements of SIA 382/1 and validation before commissioning

Air duct cleanliness management does not start during installation but from the supply of materials to the construction site. Under the hygiene guidelines applied in French-speaking Switzerland and framed by SIA 382/1, all duct components must be stored in a dedicated, ventilated, lockable area free of any rising damp. Placing circular ducts directly on the bare slab in the middle of circulation routes exposes the sheet metal to cement soiling, mud and levelling-compound splashes.

  1. Receipt and initial storageSystematic visual check as the load comes off the lorry. Any duct delivered without its factory seals must be plugged immediately or rejected. Storage on pallets or battens is mandatory to prevent any direct contact with concrete dust on the floor.
  2. Assembly in sealed sectionsRemove the plug only from the joint being fitted. The ventilation fitter closes the last free end again as soon as the connection is screwed or riveted, preventing any ingress of polluted air by suction.
  3. Pre-start-up cleanliness checkEndoscopic inspection with a towed camera or visual inspection with a mirror at low points and changes of direction. Sampling by swab or visual test on a white wipe in accordance with the hygiene classes defined in SIA 382/1.
  4. Dust removal and validationIf soiling is found during the check, mechanical rotary brushing under filtered-air negative pressure before any connection to the air handling unit. Drawing up the hygiene conformity record handed to the site management.

Commissioning of a balanced-flow system may begin only once the main final site cleaning has been validated and the floors vacuumed. The temporary site filters on the return air units must remain in place until the air flows are fully balanced, at which point the final set of new filters is installed for the acceptance of the work.

Handling a dust contamination incident and restoring compliance

When ducts are left open during the sanding of plasterboard or the spraying of renders, mineral dust penetrates deep into the horizontal sections and branches. This powdery material settles on the inner galvanised sheet walls and enters the baffle silencers. At the first start-up, the air blows this residual plaster directly into the living spaces. Simply blowing through the system is not enough: the dust settles again downstream and prematurely fouls the diffusers and terminal components.

As soon as dust ingress into the air duct system is found, the foreman records the condition of the ducts with a joint photographic survey. Under art. 365 CO, if a circumstance jeopardises the proper execution of the work, the contractor informs the client. The presence of rubble or plaster powdering caused by another trade is a clear breach of the system's hygiene. All attempts to start the fans must then be stopped until complete decontamination has been carried out.

  1. Isolating the systemFit watertight polyethylene plugs or metal caps without delay on every supply and return air opening to block any further contamination.
  2. Mechanical rotary brushingInsert a motorised rotary brush coupled to a negative-pressure extractor fitted with an absolute HEPA-class filtration unit to dislodge the encrusted plaster.
  3. Replacement of absorbent elementsSystematically remove polluted silencers and flexible ducts; plaster trapped in mineral wool cannot be decontaminated by vacuuming.
  4. Visual inspection and validationRun an endoscopic camera through all the cleaned branches to certify the absence of deposits before the commissioning record is signed.

Frequently asked questions

Is site adhesive tape sufficient to plug ducts awaiting connection?

No. Standard adhesive tape peels off under the effect of humidity or temperature variations in the structural work. Sanding dust ends up infiltrating through the gaps. Use thermoformed plastic cap covers or metal sealing end caps tightened onto the sheet metal, supplemented by a tear-resistant watertight self-adhesive strip.

What should be done if ducts were stored in the rain on the slab?

Standing water combined with dust promotes premature oxidation of the zinc and bacterial growth. Inspect each component before installation. Ducts showing internal moisture or white traces of rust must be cleaned, dried with clean forced air and disinfected. If water retention cannot be eliminated, replace the affected section.

Can the ventilation system be used to air out the building during painting?

This is not permitted. Running the air handling unit during the finishing work draws in solvents and microparticles, contaminating the heat exchanger, the new filters and the distribution ducts. Air renewal on site must be carried out exclusively by natural ventilation or by temporary mobile axial fans fitted with temporary textile exhaust ducts.

How do you formally record the cleanliness of the system before final handover?

Carry out a video inspection with a trolley camera or flexible rod camera on representative sections. The report must include time-stamped photographs of the walls, branches and balancing dampers. Include this inspection document in the as-built file handed to the site management to certify compliance with the hygiene requirements of SIA 382/1.

Texts and standards cited

  • SIA 382/1Ventilation and air-conditioning installations - General principles and performance
  • CO art. 365Material and ground: notice to the client if a circumstance jeopardises the timely or proper execution of the work
  • CO art. 368Client's rights in case of defects in the work: rectification, price reduction or rescission