Commissioning, flow measurement and balancing: the execution reference
Commissioning an air-handling installation is not a matter of flicking a switch on the day the keys are handed over. This section is aimed at ventilation fitters, foremen and test technicians who must measure actual airflows, balance networks using the proportional method, record permissible deviations and hand over a documentation file compliant with standard SIA 382/1, ensuring acceptance without reservations within the meaning of standard SIA 118.
- 10chapters
- 22 000words
- 6sections in the training course
- 60chapters in total
Key values to remember 4
± 10 %
Permissible tolerance on the airflow of an individual room
± 5 %
Permissible deviation on the total flow measured at the air-handling unit
100 mm
Recommended minimum water seal for the trap under negative pressure in the unit
60 days
Legal period for reporting defects in a building work after delivery
Scope of air-handling work and boundaries of responsibility
The work of the ventilation systems installer stops strictly at the air-handling limits of air treatment and distribution. Our responsibility covers the balanced-flow ventilation unit (supply and extract), air distribution through spiral or rectangular ducts, balancing dampers, sound attenuators, supply and extract air terminals, as well as fire dampers and mechanical smoke-extraction dampers. The installer delivers a clean, airtight, quiet installation capable of accurately distributing the volumes prescribed in the technical concept.
Interfaces on the construction site must be clearly defined to avoid disputes over who is responsible for what. The production of hot or chilled water supplying the coils is the responsibility of the heating or refrigeration contractor (CFC 241). The condensate drain connection up to the water-seal trap is the responsibility of the ventilation systems installer, but the downstream wastewater collector is installed by the plumber (CFC 250). The main power supply up to the control cabinet is the responsibility of the electrician (CFC 232), while the programming of the building automation bus or the digital zone control belongs to the MCR integrator (CFC 238).
The connection and mechanical installation of fire dampers are the responsibility of the ventilation fitter, who also carries out the mechanical release and tight-closure tests. By contrast, the overall interlocking with the fire detection control panel and the validation by the fire protection authorities require the involvement of companies certified according to the AEAI requirements. Regarding acceptance on the construction site, under art. 367 CO, the client must inspect the condition of the work as soon as is practicable after delivery; the air balancing report constitutes the technical proof of compliance of the contractual flows.
| Component or element | Ventilation fitter's responsibility (CFC 244) | Adjoining third-party trade |
|---|---|---|
| Heating or cooling coil | Installation in the air casing and checking of the airflow through it | Heating / Refrigeration (CFC 241) for the hydraulic connection |
| Condensate tray of the unit | Installation of the tray and of the trap suited to the negative pressure | Plumber (CFC 250) for the connection to the drainage network |
| Fire damper | Sealing into the wall, air-side connection and mechanical test | Electrician (CFC 232) and fire safety for the detection |
| EC fan motor | Connection to the internal variable-speed drive and setting of the nominal flow | Electrician (CFC 232) for the supply at the head of the switchboard |
Sequential execution method for acceptance without defects
A balanced network cannot be achieved by improvising at the diffusers. To obtain a stable and repeatable result, the fitter must follow a strict chronological order that avoids unbalancing one branch while adjusting the next. The ten chapters of this section have been designed to reflect this physical progression on site, from handling the measuring instruments to filing the operating manual.
- Mastering metrology and tolerancesChapters K6-01 to K6-03 set out the physical fundamentals. You learn to choose the appropriate instrument (balometer, flow hood or thermal anemometer), to apply the proportional method starting from the most unfavourable terminal, and to compare your results with the tolerances permitted by SIA 382/1 in order to validate the compliance of each room.
- Characterising the network and programming the controlChapters K6-04 and K6-05 deal with the physics of the upstream network. By measuring the static pressure in the main headers, you identify abnormal pressure losses or crushed ducts, then you programme the set points for the nominal, reduced and forced modes on the machine interface.
- Organising the handover of the work and the instructionChapters K6-06 and K6-07 prepare for daily use. You train the building's technical manager in the essential tasks (replacing filter media, refilling the traps with water, checking the electrical safety devices) and plan the periodic maintenance schedule that ensures the longevity of the installation.
- Securing acceptance and maintenance from a legal standpointChapters K6-08 to K6-10 close the assignment. In the event of a dispute, art. 368 CO governs the client's rights in respect of defects in the work; you learn to distinguish a minor defect from a fundamental defect, to hand over an impeccable as-built file and to manage the seasonal restart after a prolonged shutdown.
📘 Chapters in this section 10
Measuring an airflow rate: measuring hood, anemometer, uncertainty and repeatability
Master the choice of hoods and compensate for the pressure loss of the measuring instrument.
Commissioning, measurement and air flow balancingBalancing in the right order: proportional method, reference branch and return
Adjust your dampers methodically, starting from the most unfavourable terminal, without unnecessary iterations.
Commissioning, measurement and air flow balancingWhat deviation is acceptable: tolerance per room, sum of deviations and verdict
Distinguish a tolerable deviation from a contractual non-conformity to avoid any dispute at acceptance.
Commissioning, measurement and air flow balancingMeasuring duct pressure: pressure tapping, actual curve and undersized network
Diagnose excessive pressure losses in the ductwork to relieve the fans in the long term.
Commissioning, measurement and air flow balancingProgramming the modes: reduced, nominal, boost, and schedules that hold up in use
Set the reduced and nominal airflows while reconciling air hygiene and electricity consumption.
Commissioning, measurement and air flow balancingHanding over the installation: show the filter, the trap and the circuit breaker
Pass on the right maintenance practices to the operator to prevent premature fouling of the system.
Commissioning, measurement and air flow balancingMaintenance: frequency per component, measured points and a useful contract
Define the intervention frequencies and the critical check points on each air-handling component.
Commissioning, measurement and air flow balancingQualifying the defect: insufficient airflow, excessive noise, major defect
Identify fundamental defects and defend the compliance of your flows against financial retentions.
Commissioning, measurement and air flow balancingThe as-built file: as-built drawings, access hatches, dampers and survey records
Gather the as-built drawings and balancing sheets that ensure a smooth acceptance of the work.
Commissioning, measurement and air flow balancingRestarting after summer: dry trap, clogged filter and bypass left open
Secure the autumn restart by re-priming dried-out traps and closing the summer bypass.