🧱 CFC 244Duct network and airtightnessChapter 6 of 10 in the section

Flexible duct: short, taut, straight, or not at all

This chapter gives you the execution rules for installing flexible connecting ducts in mechanical ventilation. You will be able to determine the maximum permissible length according to the recognised rules of the trade, calculate the airflow impact of a compressed duct, connect the flexible duct properly to a rigid spiral-seam duct and rule out non-compliant bend radii on your construction sites.

Key takeaways

  • The maximum length of a flexible ventilation duct must not exceed one metre fifty in a suspended ceiling.
  • A poorly tensioned flexible duct multiplies the linear pressure loss by four to eight times.
  • Connection to rigid sheet metal requires a sealed collar, a mechanical clamp and aluminium tape.
  • Tight bends crush the effective cross-section and generate turbulence that is destructive to floor-level fans.

Maximum permissible length and airflow physics of the compressed flexible duct

In assembly practice in French-speaking Switzerland under CFC 244, the flexible duct is never a distribution network in its own right. It serves exclusively as a terminal connecting element between the rigid galvanised steel sheet network and the diffusers, extract grilles or ceiling plenums. The rules of the trade require its run to be strictly limited to what is indispensable to absorb installation tolerances and prevent the transmission of mechanical vibrations to the terminals.

The most widespread error is to use an uncut section of flexible duct to get past a passage obstructed by other trades, such as sanitary drainage pipes or electrical cable trays. When a fitter installs two metres of stretchable duct over an actual distance of one metre twenty without cutting off the excess, the internal steel wire helix keeps the wall in concertina folds. The aluminium or pleated polyester coils then behave like a continuous series of rough baffles that shear the air stream.

Comparison of relative pressure losses according to flexible duct tension (constant nominal flow rate)
Installation configurationApparent relative roughnessPressure loss multiplier compared with rigid duct
Rigid spiral-seam galvanised steel ductSmooth reference1.0
Flexible duct fully taut at 100%Low corrugated roughness1.5 to 2.0
Flexible duct compressed by 15% (partial concertina)High annular roughness4.0 to 5.0
Flexible duct compressed by 30% or moreHyper-turbulent regime and vortices8.0 to 10.0

The concertina effect turns a secondary component into a genuine airflow diaphragm. Two metres of bunched-up flexible duct generate as much resistance as about ten metres of equivalent straight rigid duct. The fan of the balanced-ventilation unit has to compensate for this unforeseen pressure increase by raising its rotational speed. This rise in pressure loss immediately results in higher electrical consumption of the motors, flow rates falling outside the ranges set in the energy concept and insidious noise nuisance in occupied rooms.

Sealed mechanical connection and geometric management of bends

Connecting a flexible duct to a rigid duct or a plenum collar follows a precise method that guarantees the overall airtightness class of the installation. Simply slipping the flexible duct on and relying solely on adhesive tape for mechanical hold is prohibited. Thermal ageing of the adhesive and variations in dynamic pressure sooner or later cause the sleeve to come off or continuous air leaks.

  1. Cutting and deburringMeasure the exact distance between the two rigid spigots. Pull the flexible duct to put it under maximum tension, cut the outer membrane and the insulation blanket with a utility knife, then cut the steel spring helix cleanly with cutting pliers.
  2. Inserting the inner wallSlide the inner vapour-barrier duct onto the rigid collar by at least fifty millimetres. The collar should ideally be fitted with a lip or a factory-crimped EPDM rubber seal.
  3. Rigid mechanical clampingFit a mechanical ratchet clamp or a serrated stainless steel band directly onto the inner duct. Tighten firmly with a screwdriver or the specific pliers without tearing the aluminium foil.
  4. Continuity of insulation and bridgingBring the mineral wool blanket and the reinforced outer skin back over the connection. Finish the joint with a pure aluminium adhesive tape at least fifty millimetres wide, pressed down with a spatula to ensure water-vapour tightness.

Tight bends are strictly prohibited on all ventilation and air-handling installations. A flexible duct bent at a sharp angle collapses on its inner radius, causing a local constriction of the flow cross-section. The bend radius at the centreline of the flexible duct must never be less than twice the nominal diameter (R >= 2 x DN). If the radius is smaller, the change of direction must absolutely be made with a rigid steel sheet bend, completed by two short straight collars for the terminal connection.

Suspension, permissible sag and acoustic traps in plenums

Sagging of a flexible duct between two support points is the leading source of airflow and acoustic degradation that becomes invisible once the suspended ceilings are closed. A flexible duct left lying on a metal framework or suspended with too wide a spacing forms a succession of sags. Each hollow acts as an uncontrolled expansion chamber followed by a sudden constriction. The air flow separates from the inner walls, generating stationary turbulence that turns the duct into a low-frequency noise generator, directly above the diffusers.

To guarantee the absence of harmful sag, supporting the flexible duct requires wide suspension straps, with at least 50 mm of contact, so as not to choke the thermal or acoustic insulation blanket or crush the steel wire spiral. Excessive tightening of a wire or a narrow clamp on an insulated duct locally halves the effective air passage cross-section, creating an accidental diaphragm that cannot be compensated by simple balancing at the terminal damper.

Effect of sag and suspension on the air flow
Installation configurationHanger spacingObserved airflow effectAcoustic behaviour
Maximum continuous tensionContinuous span ≤ 1.0 mRegular flow, pressure loss in line with chartsCompliant attenuation, no whistling generated
Moderate sag (50 to 100 mm)Point suspension every 1.5 mResistance increased by about 40%Incipient turbulence, audible background noise
Pronounced sags (> 100 mm)Resting directly on suspended ceiling without hangersPressure loss doubled, insufficient flow at the diffuserCritical regenerated noise at mid frequencies
Pinching on T-profileComplete absence of intermediate supportFlow cross-section reduced by 30 to 60%Localised whistling and vibration transmitted to the ceiling

Operating hygiene, limits of use and substitution by semi-rigid duct

The use of aluminium or reinforced polyester flexible duct quickly conflicts with the hygiene and preventive maintenance requirements in force in Swiss buildings. The inner corrugations retain fine dust, construction site residues and fibres. Any traditional rotary mechanical brushing, standard during cleaning of ventilation networks, irreparably tears the inner foil of a conventional flexible duct. The accumulated dust then becomes inaccessible, degrading indoor air quality over the years.

  • Strictly prohibited in smoke extraction: flexible aluminium has no mechanical fire resistance and no tightness against hot smoke under extraction negative pressure.
  • Prohibited when passing through fire-resistant walls: the continuity of fire compartmentation tolerates no flexible duct passage, even a short one.
  • Excluded upstream of terminal silencers: flexible duct must never be used to compensate for an axis offset between a main network and a sound attenuator.
  • Accessibility obligation: every flexible connection must be able to be inspected and removed from a suspended-ceiling access hatch of at least 400 x 400 mm.

On new construction sites and major renovations, design offices and installers now favour semi-rigid circular duct in double-wall high-density polyethylene or rigid spiral duct fitted to the millimetre. Semi-rigid duct has a smooth antistatic inner skin, compatible with brushing hedgehogs, while retaining bending flexibility without concertina formation. Where space is tight, making custom rigid fittings permanently eliminates uncontrolled pressure losses.

During acceptance of the work under standard SIA 118, air-flow inspection records systematically reveal anomalies caused by careless installation of flexible ducts. An air flow measured 25% below the prescribed value at the supply plenum almost always comes from a flexible duct that is compressed, twisted or crushed against a support of another service. Removal and replacement with rigid galvanised duct is then carried out at the expense of the ventilation system contractor.

Remedies and rectification in case of airflow deviation on a flexible network

During commissioning and balancing, a network whose terminal connections were made with flexible ducts that are too long, bunched or bent betrays itself through two major symptoms: a high-pitched whistle at the plenums and a severe flow deficit measured at the supply or extract grilles. A spiral duct compressed by half multiplies the linear pressure loss by a factor of four to ten compared with an equivalent rigid duct of the same diameter. If the fan of the balanced-ventilation unit is pushed to maximum speed to try to compensate for this unforeseen resistance, the motor's electrical consumption soars and the acoustic comfort requirements set by standard SIA 181 are no longer met.

  1. Airflow and visual diagnosisRemove the suspended-ceiling tiles at the disputed diffusers. Measure the static pressure upstream of the flexible duct and compare the actual volume flow with the values in the balancing record.
  2. Replacing the collapsed or pinched sectionRemove the slack, twisted or crushed flexible duct. Extend the rigid galvanised steel header as close as possible to the diffuser, inserting a factory-made large-radius rigid bend if the route changes plane.
  3. Taut reconnection and mechanical clampingFit a new flexible collar limited to a maximum of one metre, pulled taut to the limit to remove the undulations of the inner wall. Clamp each end firmly onto a sealed collar using a stainless steel clamp.
  4. Final check and recordMeasure the residual flow with the measuring hood or hot-wire anemometer, check that there is no parasitic vibration, then record the final values in the airflow balancing record.

Where the network has sagging or sinuous flexible ducts that do not comply with the recognised rules of the technique, the installation is deemed unacceptable at the tightness and flow tests. Under art. 368 CO, the client may demand rectification of the defective elements. Under standard SIA 118, these anomalies are recorded as formal reservations with a deadline for remedial work before release of the warranty retentions.

Frequently asked questions

What is the maximum permissible length for a flexible duct connected to a diffuser?

On Swiss ventilation construction sites, the usual technical rule limits the length of a flexible duct to 1.20 metres, with a tolerated ceiling of 1.50 metres in case of a proven geometric constraint. The duct must serve only as a vibration-decoupling collar or for final millimetre adjustment. Beyond this distance, the pressure loss becomes excessive and the risk of sagging in the plenum requires the network to be extended in rigid duct.

Why is it prohibited to use a flexible duct to make a 90-degree bend?

Tight bending of a flexible duct crushes the flow cross-section and creases the inner wall. This pinching generates major turbulence and a local pressure loss that can exceed 50 pascals at a modest nominal flow rate. In addition, this turbulence creates a whistling noise transmitted directly into the room through the diffuser. A factory-made rigid bend in galvanised steel must be fitted.

How do you correctly connect a flexible duct to a rigid part to ensure airtightness?

The connection requires a minimum overlap of 50 millimetres on the grooved male metal spigot. The inner duct must be clamped against the sheet metal with a metal ratchet clamp, completed by a reinforced adhesive tape. The thermal insulation blanket and the outer vapour barrier are then folded back over the assembly and fixed with a second clamp to prevent any thermal bridge and condensation.

Can flexible duct be used behind a kitchen hood or in smoke extraction?

It is ruled out in both situations. For kitchen hood exhaust, flammable grease deposits retained in the corrugations create a major fire risk and prevent any mechanical cleaning. In smoke extraction, the fire protection requirements of the AEAI/VKF call for rigid ducts rated to withstand high temperatures. A flexible aluminium duct tears or collapses under extreme thermal and airflow stresses.

Texts and standards cited

  • norme SIA 118General conditions for the execution of construction work
  • norme SIA 181Protection against noise in buildings
  • CO art. 368Client's rights in case of defects in the work