🧱 CFC 244Air requirements, flow rates and sizingChapter 3 of 10 in the section

Offices and rooms: airflow per person, variable occupancy and air quality sensor

This chapter gives you the on-site method for calibrating fresh air flows in offices and meeting rooms according to standard SIA 382/1. You will learn how to set variable air volume (VAV) dampers and how to position carbon dioxide sensors correctly to eliminate energy waste without degrading air hygiene.

Key takeaways

  • Standard SIA 382/1 sets the calculation bases combining human occupancy and emissions from materials.
  • The base airflow compensates for the building's emissions when the rooms are completely unoccupied.
  • The VAV control box modulates between the minimum unoccupied airflow and the full nominal airflow.
  • The position of the CO2 sensor determines the accuracy of the air-handling control and the ambient comfort.

Calculating fresh air flows between peak occupancy and non-occupancy

Ventilating an empty meeting room at the nominal airflow designed for twenty people causes a permanent heat and electricity loss. In current administrative buildings, airtightness rules out uncontrolled natural ventilation, but maintaining an oversized constant airflow needlessly loads the fans of the air handling unit and the conditioning coils.

Demand-controlled ventilation (VAV)
Air distribution system that adapts in real time the supply and extract airflow of a room by means of a motorised damper controlled by a measured physical parameter, such as carbon dioxide concentration or room temperature.

The design and setting of the installations are based on standard SIA 382/1. This technical reference distinguishes two inseparable components for determining the hygienic outdoor airflow: the pollutant load directly linked to the occupants and the area-related load arising from the building materials, furniture and technical equipment of the room.

The volumetric outdoor airflow must simultaneously cover the dilution needs of human metabolic pollutants and the diffuse emissions from the building and its finishes.

Norme SIA 382/1
Usual sizing values according to standard SIA 382/1 in commercial buildings
Room typeAirflow per personAirflow per m² (building)CO2 setpoint range
Individual office36 m³/h (10 l/s)0.7 to 1.4 m³/(h·m²)800 to 1000 ppm
Open-plan office36 to 40 m³/h1.0 to 1.5 m³/(h·m²)800 to 1000 ppm
Meeting or conference room36 to 50 m³/h1.5 to 2.5 m³/(h·m²)700 to 900 ppm
Archive or waiting roomNot applicable0.5 to 1.0 m³/(h·m²)Fixed hygienic ceiling

In practice, the ventilation fitter sets two setpoints on the VAV terminal controller. The minimum airflow corresponds to the unoccupied area-related purge, intended to remove volatile organic compounds outside periods of presence. The maximum airflow corresponds to the theoretical peak occupancy of the room. Modulation takes place gradually between these two thresholds according to the measurement sent by the CO2 sensor.

Installing and connecting the CO2 sensor to ensure damper responsiveness

The carbon dioxide sensor is the control element for the actuator of the VAV box. If the sensor is poorly positioned, the measurement becomes erroneous and the control loop delivers an unsuitable airflow: either an insufficient airflow causing respiratory discomfort and an excessive CO2 level, or an excessive airflow causing whistling at the diffusers and a waste of air-treatment energy.

  1. Positioning in the occupied zoneFix the wall housing at a height between 1.20 m and 1.50 m above the finished floor, which corresponds to the breathing zone of seated or standing people.
  2. Distance from disturbing sourcesInstall the sensor at least 1.50 m from doors, opening windows and above all fresh air supply outlets so as not to distort the reading with a draught of fresh air.
  3. Connection to the air controllerWire the analogue signal of the sensor to the measurement input of the VAV control box, strictly observing separation from the power cables.
  4. Checking the airflow limitsCheck on the VAV flow controller that the signal voltage correctly modulates the damper between the Vmin and Vmax airflows previously calibrated with a differential manometer.

The air renewal requirement also falls within the legal framework for protecting workplaces. Art. 33 OTConst specifies that air quality is regularly checked and that hazardous substances are discharged to the open air, filtered or diluted by mechanical ventilation. On the construction site, during balancing and commissioning tests, the technician ensures that each VAV box reaches its nominal airflow when the sensor is exposed to a calibration gas, thus guaranteeing that a healthy atmosphere is maintained under full occupancy.

Setting CO2 thresholds and VAV modulation laws

In administrative and school buildings, air-handling sizing is based on standard SIA 382/1. A conference room designed for twenty people has a nominal airflow often above 600 m³/h. If this volume of fresh air is supplied continuously while the room remains unoccupied 70% of working time, the thermal energy used to condition the air and the electricity absorbed by the fans of the unit are wasted with no hygienic benefit. Demand-modulated ventilation (VAV) adapts the air renewal in real time between a minimum unoccupied airflow and the peak airflow.

The control law bridges the area-related need of the room and the occupancy load. In the absence of any human presence, floor coverings, furniture and paints emit volatile organic compounds that require continuous purging. This minimum purge airflow is generally set on an area basis between 0.7 and 1.2 m³/(h·m²). As soon as occupants enter the room, exhaled breath enriches the atmosphere with carbon dioxide. The terminal controller receives the analogue signal from the sensor and translates the opening of the motorised damper along a gradual ramp.

CO2 setpoint ranges and air-handling behaviour of the terminal damper
CO2 content (ppm)Room statusVAV airflow setpointAir quality criterion
Below 600Unoccupied or start-upMinimum purge airflow (area-related)Fresh indoor air close to outdoor air
600 to 900Partial occupancyLinear modulation (30% to 70%)High comfort, gradual dilution
900 to 1200Full nominal occupancyMaximum nominal airflow (100%)Hygiene and mental concentration threshold
Above 1400Temporary overcrowdingMaximum emergency boost airflowStale air, discomfort and drowsiness noticeable

The control algorithm built into the actuator of the VAV box applies a proportional-integral (PI) action. A proportional band that is too narrow causes incessant hunting of the metering damper, generating fluctuating air noise perceptible at slot diffusers or perforated plenums. Integration that is too slow delays the admission of fresh air, creating an unpleasant peak of stuffiness during crowded meetings. The median setpoint is usually locked at 800 or 900 ppm to stabilise the damper travel before saturation.

Interaction between modulating boxes, network pressure and commissioning

The action of a carbon dioxide sensor does not only change the damper of the room concerned: it upsets the dynamic balance of the entire duct section. When several zone boxes close simultaneously as a result of falling occupancy, the pressure drop of the distribution network increases instantly. If the air handling unit runs at fixed speed, the static pressure in the ducts soars. This phenomenon causes whistling at the diffusers that have remained open and forces the fans away from their optimum efficiency point.

  1. Air-handling check of the expansion boxCheck the straightness of the section upstream of the VAV box. Observe a minimum straight length equivalent to three to five times the hydraulic diameter before the differential pressure measuring cross to avoid disturbing eddies.
  2. Calibrating the Vmin and Vmax airflows with a differential manometerConnect a reference flow meter to the pressure tap of the terminal box. Force the manual control to 0 V then to 10 V to rigorously calibrate the logical limits corresponding to the area-related base airflow and the peak airflow per person.
  3. Checking the pressure control of the air handling unitObserve the response of the frequency converter of the supply fan when several boxes switch simultaneously from the nominal state to the minimum state. The duct static pressure sensor must correct the speed without any surging.
  4. Validating the position and tightness of the sensorCheck that the electrical flush box of the wall sensor is sealed with sealing compound. Parasitic air draw coming from inside the lightweight partitions completely falsifies the analysis of the actual room air.

At acceptance of the work according to standard SIA 382/1, the installer records on the balancing report the airflows measured at the voltage thresholds of 2 V (or 0 V depending on the profile chosen) and 10 V. The traceability of this demand-based control guarantees the client that the installation delivers only the energy strictly required by the actual occupants, ensuring the thermal and mechanical durability of the entire network.

Diagnosing modulation malfunctions and clearing defects

On a commercial variable air volume (VAV) ventilation installation, functional drifts appear from the first weeks of operation. The classic symptom remains the unoccupied meeting room whose damper stays wide open at its maximum airflow, or conversely, the overcrowded space saturated with pollutants where the actuator remains stuck at the minimum hygienic airflow. Faced with these anomalies, the ventilation fitter must proceed by methodical elimination between the room sensors, the terminal units and the overall air-handling system.

  1. Checking the sensor positionA carbon dioxide sensor bathed in the jet of a fresh air diffuser reads an artificial value of 420 ppm and keeps the damper closed despite ten occupants. Placed in a dead corner or on a partition exposed to direct sunlight, it measures a stagnant pocket and forces the damper to 100%. The technician must check that the cell is located between 1.20 m and 1.50 m above the finished floor, in the actual occupied zone, on a neutral partition and away from the door swing.
  2. Checking the base airflow and calibrationAccording to standard SIA 382/1, an empty room must not have its ventilation completely interrupted: a minimum area-related purge remains prescribed to remove emissions from materials and furniture. The fitter measures the residual leakage airflow with a Pitot tube or a measuring hood to confirm the low mechanical stop of the damper. In parallel, calibrating the carbon dioxide sensing element by comparison with a certified portable device makes it possible to eliminate a measurement drift of the infrared sensor.
  3. Air-handling stability and duty to notifyHunting of a modulating box often results from an unstable upstream static pressure or from an air reduction ratio outside the range of the internal differential pressure sensor. If the position imposed by the architectural plans makes the measurement inherently erroneous, the contractor applies art. 365 CO and notifies the client in writing that this circumstance compromises the proper operation of the installation.

Frequently asked questions

How do you identify on site a carbon dioxide sensor distorted by its environment?

The technician compares the displayed value with that of a calibrated portable analyser placed in the centre of the breathing zone. A deviation of more than 150 ppm without direct human input indicates a local disturbance. Immediately inspect the fresh air flow from the supply diffusers, unsealed cable entries in the flush box creating a parasitic air depression, or the direct proximity of a user's breath.

Why does a VAV box oscillate continuously in an empty room?

This hunting phenomenon occurs when the minimum airflow setpoint lies below the reliable detection threshold of the differential pressure measuring cross. The control loses its airflow reference, suddenly opens the damper and then closes it again. The minimum airflow parameter in the terminal controller should be corrected to respect the authority range of the damper, or the damping of the actuator adjusted.

What minimum airflow must be guaranteed according to standard SIA 382/1 outside occupancy periods?

Standard SIA 382/1 distinguishes the need linked to people from the area-related need dedicated to the outgassing of building materials and fit-out. With no occupants at all, the installation does not shut down: it modulates towards a predefined area-related base airflow, generally of the order of 0.7 to 1.5 m³/(h·m²), ensuring continuous removal of volatile compounds without consuming the energy of a full air change rate.

Where does the ventilation fitter's scope of intervention end on the VAV chain?

The ventilation installer (CFC 244) installs the VAV damper and its silencers, connects the room sensor to the box's dedicated controller and carries out the air flow measurements. The electrical power connection at the switchboard falls under CFC 232, while the integration of the setpoint into the building management system and the setting of the fieldbus belong to the automation trade (CFC 238).

Texts and standards cited

  • norme SIA 382/1Ventilation and air-conditioning installations - General principles and required performance for indoor air quality and airflows
  • CO art. art. 365 COmaterial and ground conditions: immediate notice to the client if a circumstance compromises the proper or timely execution of the work (para. 3)